RFI Q&A for Industry 20 Mar 18

View the file

Other files

File Type Posted
Notice_of_Contract_Award.pdf PDF
Attachment_1_USAFA_CE_BMS_PWS_rev_4.2_dated_11_April_2018.pdf PDF
Notice_to_Industry_11_April_2018.pdf PDF
FA7000-17-R-0012-0004.pdf PDF
RFI_Q&A_for_Industry_-_Part_II.pdf PDF
Notice_to_Industry_28_Mar_18.pdf PDF
FA7000-17-R-0012-0003.pdf PDF
Dorm_Occupancy_Rates_2015-2017.xlsx XLSX spreadsheet
Attachment_7_DBA_Residential_CO180014_dated_2_March_2018.pdf PDF
Attachment_14_ITO_Attachment_6_CLIN_Schedule_Spreadsheet_Rev_1.xlsx XLSX spreadsheet
CO_Conveyance_Inspection_Guidance060617.pdf PDF
Attachment_8_DD_Form_254.pdf PDF
DD_FORM_254_Continuation_Page.pdf PDF
Pest_Management_Plan__2012_(With_2015_udpates)-re-sized.pdf PDF
CO_ConveyanceRegulations040117.pdf PDF
Attachment_5_DBA_Heavy_CO180012_dated_2_March_2018.pdf PDF
Solicitation_Changes_Sheet_20_Mar_18.pdf PDF
_FA7000-17-R-0012-0002.pdf PDF
Attachment_1_USAFA_CE_BMS_PWS_Rev_4.1_dated_20_Mar_18.pdf PDF
_FA7000-17-R-0012-0002_CONFORMED.pdf PDF
A17.1--2013.pdf PDF
Notice_to_Industry_20_Mar_18.pdf PDF
CO_Conveyances-Statutes_2017.pdf PDF
Attachment_4_DBA_Building_CO180032_dated_2_March_2018.pdf PDF
Notice_to_Industry_1_Mar_18.pdf PDF
DBA_Residential_CO180014_dated_2_February_2018.pdf PDF
DBA_Heavy_CO180012_dated_2_February_2018.pdf PDF
SCA_WD_Rev_9_dated_10_January_2018.pdf PDF
DBA_Building_CO180032_dated_2_February_2018.pdf PDF
ITO_Attachment_5_Past_Performance_Questionnaire_(PPQ).docx DOCX document
DBA_Highway_CO180018_dated_2_February_2018.pdf PDF
FA7000-17-R-0012-0001.pdf PDF
FINAL_Amendment_1_Slides.pdf PDF
Notice_to_Industry_8_Feb_18.pdf PDF
_FA7000-17-R-0012.pdf PDF
Attachment_2_SCA_WD_15-5418_Rev8_26_Dec_17.pdf PDF
Attachment_5_DBA_Heavy_CO180012_5_Jan_18.pdf PDF
Attachment_10_ITO_Attachment_2_Sample_Client_Authorization_Letter.docx DOCX document
Attachment_6_DBA_Highway_CO180018_5_Jan_18.pdf PDF
Attachment_8_RESERVED.pdf PDF
Exhibit_A_Contract_Data_Requirements_List.pdf PDF
Attachment_9_ITO_Attachment_1_Sample_Consent_Letter.docx DOCX document
Attachment_1_USAFA_CE_BMS_PWS_rev_4_dated_19_Jan_18.pdf PDF
Attachment_3_CBA_USAFA_1_Sep_15.pdf PDF
Attachment_14_ITO_Attachment_6_CLIN_Schedule_Spreadsheet.xlsx XLSX spreadsheet
Attachment_13_ITO_Attachment_5_Past_Performance_Questionnaire_(PPQ).pdf PDF
Attachment_11_ITO_Attachment_3_PPI_Tool.accdb MDB file
Attachment_7_DBA_Residential_CO180014_5_Jan_18.pdf PDF
Attachment_12_ITO_Attachment_4_PPI_Tool_Instructions.pdf PDF
Notice_to_Industry_19_Jan_18.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI) QUESTIONS AND ANSWERS TO

SOLICITATION FA7000-17-R-0012

1. Reference Appendix A-13 paragraph 3.4.1.4 and 3.4.1.5. The Air Force provides an estimate for parts and materials at $900,000/yr for preventive maintenance and $1,500,000/yr for DSW work or, a total of $2,400,000 per year for parts and materials. Also, in Appendix A-13 there is mention that the contractor is expected to include 120,000 gallons of glycol. Is the cost of 120,000 gallons of glycol already included within the $2,400,000 parts estimate or is the glycol in addition to the estimated $2,400,000 per year in parts and materials?

ANSWER: The cost of glycol is not included in the part estimate of $2,400,000 per year. The amount of glycol is listed separately to allow the Service Provider (SP) a more distinct amount for proposal and budgeting purposes.

2. Reference Appendix A-14 paragraph 3.4.1.6. The Air Force has estimated subcontracting for DSW to be $1,000,000/yr.

a. Does this include subcontract estimate for all DSW and preventive maintenance?

ANSWER: No, the estimated subcontracting amount referenced above is only for DSWs.

This is an estimated subcontracting amount for proposal purposes. How the successful offeror decides to execute the PWS requirements could influence this number.

b. Is the $1,000,000 estimate also inclusive of the professional engineering, installation management, environmental management, cultural resource management, operating engineering, snow removal, water and wastewater distribution, waste water treatment plant, heat plant, emergency management, and general officer quarter housing CLINs? If not, please clarify.

ANSWER: No. This is an estimated workload for Civil Engineering Facility Operations (see Question 2a). How the successful offeror decides to execute the PWS requirements could influence this number.

3. Reference Appendix A-14 paragraph 3.4.1.6 and the required minimum staffing listing. To eliminate the potential risk to the prime contractor for subcontract costs above the Air Force estimated $1,000,000 per year we request that the Air Force provide a listing of all subcontractors included in the $1,000,000 government estimate of subcontract cost per year so that bidders can contact current subcontractors to get their estimates of actual costs. We also need this listing to ensure that the required minimum staffing listed on page 110 of 172 is sufficient when combined with the subcontract functions required. Please provide a listing of all subcontract functions and subcontractor names.

ANSWER: The list of subcontractors is proprietary to the incumbent contractor and will not be released.

4. In order to prepare a competitive proposal for the CE services at the Air Force Academy all bidders will need information that is relative to the requirements of this contract. Please provide a complete relevant RPIE and RPSE that the contractor will be responsible to maintain. And, please provide each facility that the contractor will be responsible for with square footage per facility.

ANSWER: The complete and relevant RPIE/RPSE listing and facility listing can be found in the CEI and CEO folders of the Technical Library.

5. Reference paragraph 3.4.19. The majority of the pools listed in Table 2 are year around pools. The annual cleaning is to be performed when the pools are empty. How long will the pools be allowed to be out of service each year for the annual cleaning? Also, the daily, weekly and periodical cleaning needs to be performed when the pool areas are closed to swimming activities. Please provide the hours that the pool will be open.

ANSWER: The SP is expected to work with the End Users when scheduling work. End Users are willing to work with the SP to limit impacts to both the SP and the End Users’ mission requirements. Current contractor is conducting daily and weekly requirements during the overnight hours, and periodic/annual requirements are being accomplished during school breaks.

6. Reference paragraph 3.4.20 and 3.1.5. According to paragraph 3.1.5 the vertical transportation maintenance is provided under separate contract. Paragraph 3.4.20 indicates that the CE contractor is responsible for the independent 3rd party inspections (5 year, 3 year and annual testing). However in paragraph 3.4.20.7 (1 and 2) references service calls. Will the CE contractor be responsible for service calls to the vertical transportation or will these tasks be accomplished by the VTE contractor?

ANSWER: PWS paragraphs 3.4.20.7.1 (and subparagraphs) and 3.4.20.7.2 (and subparagraphs) outline the SP requirements for elevator service calls.

7. Please provide the current annual amount for the FFP portion of the incumbent’s contract.

ANSWER: The values that were included in the pre-proposal conference slides posted with Amendment 1 (slide 8) showed the total firm fixed price value for all four years of the incumbent contract, to include the current year.

8. Please provide a listing of ADPE that will be provided per PWS 4.1.3.7.

ANSWER: This listing was inadvertently omitted from the PWS. This is now Appendix N. See revised PWS. The file will be attached in www.fbo.gov in conjunction with Amendment 2.

9. Please provide a listing of furniture, shelving, lockers, etc. that the Government is providing for the Government Provided Facilities.

ANSWER: The Government will not be providing a list of furniture, shelving, lockers, etc. The SP is welcome to use what is available in the spaces being provided. See Appendix A Section 4.1.2 for further guidance on furniture provisions.

10. Reference Appendix C, Government Furnished Property/Equipment/Vehicles. Appendix C identifies a Zamboni Ice Resurfacer, however, the PWS does not identify equipment to resurface ice at the ice arena. Is it the SPs responsibility to resurface the ice arena ice? If so, how often is this required?

ANSWER: No, the SP is not responsible to resurface the ice. This piece of equipment has been removed from the GFP listing (Appendix C).

11. Reference Appendix C, Government Furnished Property/Equipment/Vehicles. The “Trailer Boiler” is identified as unavailable yet listed. Please clarify what the trailer boiler is used for and is the SP is required to have one other than the one listed in Appendix C?

ANSWER: The trailer referenced is no longer in the GFP inventory. This piece of equipment has been turned in to DRMO, but has not been removed from the GFP listing (Appendix C). The SP is not required to replace this particular listed trailer.

12. Reference Appendix C, Government Furnished Property/Equipment/Vehicles. Please clarify how “turn-in” condition is defined. By what criteria did the AF determine that the aforementioned equipment is designated as “turn-in”.

ANSWER: This equipment has been classified for “turn-in” to DRMO for disposal. It is still in the process of disposal and disposition has not been completed at this time. This is to inform offerors that this equipment will either not be available at contract start, or the SP will be required to complete the “turn-in” process at the start of their contract. This equipment will not be available for use to the SP at the start of contract performance.

13. Reference Appendix C, Government Furnished Property/Equipment/Vehicles. Is equipment identified as “turn-in” condition available to the SP for use on this contract?

ANSWER: See answer to Question 12.

14. Reference Appendix C, Government Furnished Property/Equipment/Vehicles. Is the Air Force responsible for the maintenance and repair of GFP listed in Appendix C.

ANSWER: See revised PWS paragraph 4.1.1.2. “All GFP repairs and maintenance shall be provided by the SP. When required items become unserviceable through normal usage, they shall be replaced at the SP’s expense. At that point, the SP-purchased items become the property of the SP. Properly dispose of unserviceable items.”

See PWS paragraph 4.1.3.1, “All equipment repairs and maintenance shall be provided by the SP.”

PWS paragraph 4.1.3.3 has been revised.

15. Reference 4.1.3 Government-Furnished Equipment. See Appendix A-1 GFE CE.pdf. See Appendix A-2 GFE EM.pdf. We did not see this document released with the RFP. Will the AF please provide this document?

ANSWER: The above referenced Government Furnished Equipment – Civil Engineering listing is included with the revised Appendix C, Government Furnished Property/Equipment/Vehicles.

The Government Furnished Equipment – Emergency Management listing was inadvertently omitted from the PWS. This is now Appendix O. See revised PWS. The file will be attached in www.fbo.gov in conjunction with Amendment 2.

16. Reference 4.1.3.7 Government-Furnished IT Equipment. See Appendix A-3 IT Equipment CE.pdf.

We did not see this document released with the RFP. Will the AF please provide this document?

ANSWER: This listing was inadvertently omitted from the Technical Library. The file will be attached in www.fbo.gov in conjunction with Amendment 2.

17. Reference 4.1.4 Government-Furnished Vehicles. See Appendix A-4 GFV CE.pdf. We did not see this document released with the RFP. Will the AF please provide this document?

ANSWER: The above referenced Government Furnished Vehicles listing is included with the revised Appendix C, Government Furnished Property/Equipment/Vehicles.

18. Is there a technical library available for review by bidders?

ANSWER: Yes. See RFP, FA7000-17-R-0012, Addendum to FAR 52.212-1, paragraph 2.16, Technical Library.

19. Reference PWS Section 3.1.2.3 states "The SP shall provide a full time professional registered Chief Engineer, lead engineers (mechanical, electrical, structural, and civil), and architect. The Chief Engineer shall not be the Civil Engineering Manager. Maintain fully trained and qualified professionals, certifications, and licensing.” Please clarify if this means the Lead Engineers and Architects must be professionally registered in addition to the Chief Engineer.

ANSWER: PWS Section 4.4.2.5 outlines the requirements for the positions in question.

20. Reference PWS Section 3.2.1.2 Provide Professional Engineering Services states "The SP shall be responsible for performing all duties related to multi-disciplinary in-house designs and external design contracts.” PWS Appendix A (Page A-4), Section 3.2.1 Project Design and Management shows two tables (one for number designs/year and one for number of construction projects funded per year) with the following statements:

Designs included in the table include those designs being conducted/funded by a third party and require Liaison Duties and/or Design Contract Oversight in order for the design to be completed to meet USAFA Mission Requirements.

Construction Projects included in the table include those projects being managed by a third party and require Liaison Duties and/or Construction Contract Oversight in order for the projects to be completed to meet USAFA Mission Requirements, USAFA Design Standards, and USAFA Facility Excellence requirements.

a. By dollar amounts shown in the first table, what percent of the average and inserts/emergent projects will be performed via in-house designs versus external design contracts?

ANSWER: This is for the SP to decide based on their business model. There is no specific percentage of projects to designed in-house. See revised PWS paragraph 3.2.1.2.1.2.

b. By dollar amounts shown in the second table, what percent of the average and inserts/emergent projects will involve construction management via third party with liaison duties versus formal construction contract oversight?

ANSWER: All MILCON and UMMC projects can be assumed to be managed by a third party (see PWS paragraphs 3.2.1.2.10 and 3.2.1.3.6). Contractors can assume approximately 14 – 24 additional projects per year of various sizes being managed by a third party. This includes construction and/or design projects.

21. Will the Government provide workload data for PWS paragraph 3.4.14 for Pest Management Services?

ANSWER: The Pest Management Plan was inadvertently omitted from the Technical Library. The file will be attached in www.fbo.gov in conjunction with Amendment 2. The Pest Management Plan is currently under its 5-year review.

22. Attachment 1. Will the Government provide a list of all subcontracted services currently existing on the incumbent contract?

ANSWER: See answer to Question 3.

23. Will the Government provide a separate CLIN for Utilities/Electrical Services?

ANSWER: No, the Government will not provide a separate CLIN for Utilities/Electrical. The requirements of PWS paragraph 3.2.2.3 are included as part of the Engineering Management CLIN.

24. Will the Government provide a more specific breakout of Direct Scheduled Work for CLINs X006 and X007?

ANSWER: No. The estimated workload is the same for both CLINs. The duration to complete the work is different. See Performance Requirements Summary (PRS) Items 67, 68, and 69. The Government will exercise either, but not both, of these CLINs for each option period.

25. For CLIN X008 the Government has provided a lump sum of 45,000 man-hours. Will the Government provide a more specific breakout of the preventive work orders so we may develop a more accurate staffing profile?

ANSWER: See the Technical Library (CEO folder) for more information.

26. For Attachment 1, Appendix D. Will the Government provide workload data for the elevator work.

Will the Government update the MTC to include elevator maintenance personnel?

ANSWER: PWS Section 3.4.20 outlines the SP requirements for frequency of elevator inspections. The Government will not revise the MTC, since the MTC reflects the minimum amount of staffing necessary for specified areas; it does not represent the total workforce.

27. The Solicitation does not provide equipment listings where preventive maintenance and repair is required. Will the Government provide detailed equipment lists for pricing and estimating purposes?

ANSWER: It is assumed this is referring to RPIE and RPSE equipment. See answer to Question 4.

28. Attachment 1, Appendix B. For the P&E Supervisor, what does P&E stand for?

ANSWER: Pavements and Equipment

29. Will the Government provide a timeframe for any system or function that may be privatized?

ANSWER: Any privatization efforts are undetermined at this time. The Government will coordinate with the SP once the timeframes are known.

30. For the repair or maintenance of any item listed in Attachment 1, Appendix C-1, in which CLIN does the Government want personnel priced?

ANSWER: Include cost for snow/sweeping repair and maintenance under the Snow Removal/Pavement Sweeping CLIN. All other GFP/E repair and maintenance cost should be included in the Operations Engineering CLIN.

31. Reference Attachment 1, Appendix A, paragraph 3.4.1.6. Will the Government confirm that any hours shown in the table are above and beyond the MTC personnel requirements?

ANSWER: The offeror needs to determine the personnel required that are necessary to meet PWS requirements. Per PWS 4.5.1, the MTC is defined as the required minimum amount of staffing necessary for specified areas of performance. While the MTC identifies a minimum number of FTE personnel for specified areas of performance, it DOES NOT represent the total workforce that is required to fully perform the requirements of the PWS.

32. Reference Attachment 1, page A-21. Is the work shown in the table included in the Government’s estimated MTC staffing?

ANSWER: See answer to Question 31.

33. Reference Attachment 1, page A-21. Will the Government identify the basic type of personnel (by labor category) required to support the events listed?

ANSWER: Unless specifically identified, the SP is to determine which labor categories are required to support the event.

34. Reference Attachment 1, paragraph 3.5. Will the Government confirm if all of the work described in paragraph 3.5 is to be included under CLIN X014?

ANSWER: No. Refer to the descriptions for Installation Management CLIN and the General Officers Quarters (GOQ) Housing CLIN regarding PWS Section 3.5.

35. Are the personnel required to support the work identified in Attachment 1, Appendix L included in the

MTC?

ANSWER: See answer to Question 31.

36. Are the personnel required to support the work identified in Attachment 1, Appendix K included in the MTC?

ANSWER: See answer to Question 31.

37. Are the personnel required to support the work identified in Attachment 1, Appendix J included in the

MTC?

ANSWER: See answer to Question 31.

38. Reference Attachment 1, paragraph 4.4.2.2. Are the medical worker positions included in the Government’s MTC?

ANSWER: See answer to Question 31. The requirements in PWS Section 4.4.2.2 have been revised.

39. Reference Attachment 1, paragraph 4.4.2.4.7. Are the Cathodic Protection Inspectors/Testers included in the Government’s MTC?

ANSWER: See answer to Question 31.

40. Reference Attachment 1, paragraph 4.4.2.4.12. Is the Playground Inspector included in the Government’s MTC?

ANSWER: See answer to Question 31.

41. Will the Government provide the list of work orders performed for the most recent year of the current contract?

ANSWER: See the Technical Library (CEO folder) for this information.

42. Is there a list of deferred maintenance items? If so, does the MTC staffing cover the deferred maintenance items/work?

ANSWER: The Government cannot currently determine what deferred maintenance items will exist at the start of the contract.

43. Reference CLINs X006 and X007, DSW work. The DSW work is referenced in the minimal staffing chart (appendix B-1) and appendix A, page A-14, paragraph 3.4.1.6. At the pre-proposal conference it was said that the division between CLINs X006 and X007 was approximately 25% effort to CLIN X006 and 75% effort to CLIN X007. It was also stated that the awardee will be required to maintain at least the minimum required staff (as provided by the Air Force) and that the only excuse will be for authorized absences. Later in that same discussion it was mentioned that the CLINs X006 and X007 are “option” CLINs and that they should both be fully funded because the Air Force may only fund one of the CLINs.

If they are both to be fully funded then both CLINs would have 100% of the minimum required staff (as presented by the Air Force) attached to them for DSW work because of the fact that we will be required to maintain the minimum staff as indicated in the required minimum staff provided by the Air Force.

However, the two CLINs have different levels of effort assigned to them. As an example, CLIN X006 completion time potentially is 180 days while CLIN X007 is more aggressive and has a completion time of 30 days. Therefore, the level of effort is vastly different between the CLINs. Are bidders to bid 100% of the labor requirements for DSW, subcontracts for DSW and parts/materials needs of the DSW in each CLIN (X006 and X007) or are we to reduce our level of effort and resulting cost in CLIN X006? Please clarify.

ANSWER: See the Technical Library (CEO folder) and PRS 67, 68, and 69 for DSW performance level requirements. Offerors need to provide full pricing for AFCOLS level of effort requirements on the Direct Scheduled Work (DSW) – AFCOLS CLIN. Offerors need to provide full pricing for USAFA level of effort requirements on the Direct Scheduled Work (DSW) – USAFA CLIN. The Government will exercise either, but not both, of these CLINs for each option period, so the offeror must have full pricing for each CLIN.

44. On the site visit it was mentioned that pool operation and maintenance has been added to this procurement and was not included in the current contract. There are 7 swimming pools that must be cleaned daily, plus weekly and annual services performed.

a. Does the required minimum staff (in appendix B-1) take into consideration that this now requirement for operations and maintenance to these 7 pools?

ANSWER: See answer to Question 31.

b. Please provide the opening and closing times for the pools so that we can clean and treat the pools prior to them being occupied.

ANSWER: See answer to Question 5.

c. We assume that the swimming pool and garden pool maintenance will fall into the Direct Scheduled Work of the contract so, does the $1,500,000 include all cleaning agents and chemicals to service the pools and garden pools of the contract?

ANSWER: Yes, the annual estimated DSW material cost shown in Appendix A, Section

3.4.1.5 does include all cleaning agents and chemicals to service the pools and garden pools.

45. Regarding the amount for material (parts, materials and supplies) of $900,000 for preventive maintenance and the $1,500,000 for DSW:

a. Will the Air Force consider a modification to the contract if these amounts are exceeded within each contract year?

ANSWER: If the amounts in the workload are exceeded, the contractor may submit a request for equitable adjustment. Refer to DFARS 252.243-7002, Request for Equitable Adjustment for further information.

b. Also, is our assumption correct that these amounts are only relative to Preventive Maintenance, DSW work, utility plant operations and swimming pool O&M and that Engineering Management, Installation Management, Environmental Management, Cultural Resources, and Emergency Management material costs are not included in these amounts provided by the Air Force?

ANSWER: Yes, that is correct.

46. Regarding paragraph 3.4.1.6 on page A-14, there is an amount of $1,000,000 per year for subcontracts associated with DSW.

a. When this $1,000,000 is referenced towards DSW, does that include preventive maintenance, plant maintenance, roads and grounds, maintenance and repair to facilities and appurtenances, etc?

ANSWER: No, see answer to Question 2a.

b. Are we to assume that this does not include subcontracting for Engineering Management, Installation Management, Environmental Management, Cultural Resources or, Emergency Management?

ANSWER: Yes, see answer to Question 2b.

c. Will the Air Force allow for a modification if this subcontracting amount of $1,000,000 is exceeded?

ANSWER: No, the Government will not allow a modification if the subcontracting amount of $1,000,000 is exceeded. This is an estimated subcontracting amount for proposal purposes.

How the successful offeror decides to execute the PWS requirements could influence this number.

47. We noticed many current deficiencies present on the AFA, such as deficient pavement, etc.

a. Will the Air Force allow a deficiency inspection relative to all of the requirements of this contract?

ANSWER: A formal deficiency inspection is not required by the PWS, nor required during transition.

b. If so, what will be the procedure to have such an inspection during the phase-in Period and the actual procedures to remedy such deficiencies?

ANSWER: N/A

48. Reference Appendix B-1, Minimum Staffing Levels. At the bottom of the left-hand column there is a section entitles CEX. We could not find any description of the acronym for CEX. What does CEX represents so that we can call the Manager and 7 Techs what they are required to be titled and required to perform?

ANSWER: CEX represents Emergency Management and Readiness.

49. Would it be possible to know how many CEN personnel are currently under contract with Aleut who are working for KIRA in bldg. 8120?

ANSWER: This information is proprietary to the incumbent contractor and will not be released.

50. Reference ITO Instruction 4.10 Project Citations, pg 123.

a. Is there a minimum number of Citation Projects to submit?

ANSWER: No, there is no minimum number of citations to submit.

b. Please consider increasing the maximum page limit per citation. The information for the contract, Key Individuals, and POC takes up almost 2 pages by themselves.

ANSWER: The Government has revised the maximum page limit from two pages per citation to four pages per citation. See revised ITO Instruction Section 2.12, Table 1 and Section 4.10.1.

51. Reference ITO Instruction 4.10.4 PPQ, pg 124. May we use CPAR in lieu of PPQs? A few of our completed project (within past 5 years) CORs have moved to other sites?

ANSWER: No. Offerors are to provide the information requested in the solicitation. The Government will review CPARS during the evaluation. Reference ITO Instruction 4.4, Independent Government Performance Information.

52. Reference ITO Instruction 3.6.1.1.1 Staffing Qualifications for Each Position, pg 120. May the Staffing Qualifications be eliminated from the Page count, as they could take the majority of the page count; or is a summary qualification table permissible?

ANSWER: Offerors need to meet the requirements as stated in ITO Instruction 3.6.1.1.1 and ensure they are within the page limit as specified in ITO Instruction 2.12.

53. Reference PWS 3.4.3.4.1.1, PWS 3.4.3.4.1.2, PWS 3.4.3.4.1.3, PWS 3.4.3.4.2.1, PWS 3.4.3.4.2.2, PWS 3.4.3.4.2.3. All of the referenced PWS areas state calendar days. Will the Government please consider changing the references to “Business Day” instead?

ANSWER: No, the references will remain unchanged.

54. Since CLINs X006 and X007 are shown as OPTIONS, at what point will the Government select the service level they desire? Can the service level change month to month or year to year? Please clarify how the service level is determined and how it will be exercised by the Government.

ANSWER: The Government will exercise one of the option CLINs based upon 1) an approved waiver to exceed AFCOLS levels of service and 2) availability of local funding. The level of service will not change month to month, however, the level of service could change for each option year. The Government will provide notification in accordance with FAR 52.217-9, Option to Extend the Term of the Contract.

55. Reference Appendix A 3.4.1.4. What level of PM program back log can the contractor expect at contract start date?

ANSWER: Assume one month of backlog. See revised Appendix A Section 3.4.

56. Reference Appendix A 3.4.1.5. What level of DSW back log can the contractor expect at contract start date?

ANSWER: Assume one month of backlog. See revised Appendix A Section 3.4.

57. PWS 3.5.1 References AFI 32-6005, paragraph 1.2.8. There is no paragraph 1.2.8 in the instruction, please clarify.

ANSWER: The reference to AFI 32-6005 paragraph 1.2.8 is removed from the PWS. See revised PWS paragraph 3.5.1.

58. PWS 3.5.1 does not address the role of the SPs Dorm Manager, a MTC position. What role does the Dorm Manager have in supporting the UH Manager, a Government position? Is the Dorm Manager deemed a Housing Manager as spelled out in the AFI?

ANSWER: The Dorm Manager/UH Manager is a Government position. This position is now removed from the MTC. See revised Appendix B.

In addition, the General Officer Quarters Manager is a Government position. This position is removed from the MTC. See revised Appendix B.

59. Reference Appendix A 3.5 Housing Support. The workload provided does not appear to support the PWS requirements provided for 3.5.2 General Officer Quarters Requirements. Which PWS requirements are supported by the workload listed in Appendix A, 3.5 Housing Support?

ANSWER: The workload for PWS Section 3.5.2 General Officer Quarters requirements can be found in Appendices G – J. The workload listed in Appendix A, 3.5 Housing Support has been removed. See revised Appendix A.

60. MTC Section CEI lists a Dorm Maintenance position at 0.50. 3.6 Performance Requirements #71 references PWS 3.4.3.1. Is the Dorm Maintenance position priced to CLIN X006 or X007?

ANSWER: All maintenance work for the Dorms is performed under DSW requirements. The requirement should be proposed under Direct Scheduled Work (DSW) – AFCOLS CLIN and the Direct Scheduled Work (DSW) – USAFA CLIN. See revised Appendix B.

61. In accordance with FAR 4.1705(a) ‘This clause is not required for actions entirely funded by DoD contracts awarded with a generic entity identifier. As the PWS already includes Manpower reporting, will Contractors also need to report in SAM? Will the Government please remove 52.204-14 Clause from the solicitation?

ANSWER: FAR Clause 52.204-14 has been removed. See revised solicitation.

62. The MTC is defined as the required minimum amount of staffing necessary for specified areas of performance. Is the MTC that has been provided in Appendix B, the MTC that should be applied for the base year, for each of the option years (OY1-OY4) and for each of the 2 incentive periods?

ANSWER: Yes, that is correct.

63. Will the Government consider increasing the page limits for past performance citations to either 4 pages per citation or 40 pages total for all 10 citations? The formatted portions of the PPI tool take up over one page leaving limited space to describe relevancy.

ANSWER: See answer to Question 50b.

64. Will the Government consider adding in FAR clause 52.248-1?

ANSWER: The Government will not be adding FAR 52.248-1 (Value Engineering).

65. In order to properly compute the vacation time off pay for continuous years of service, will the Government provide the Seniority list from the CBA or a listing of the employees accrued vacation hours?

ANSWER: This information is not available to the Government.

66. Reference 5.7, Section 3: CLIN Schedule and Section M 5.1.1. Referenced section states "Provide all unit prices and extended prices for each CLIN that requires proposed pricing in the CLIN Schedule (ITO Attachment 6), as follows". Does this imply that the contractor should add columns in the attachment 6 table for the quantities and unit pricing to go along with the extended price in each contract period?

ANSWER: No. Unit price should only be included in a copy of the Model Contract in accordance with the revised ITO Instruction Section 6.3. The request for unit pricing has been removed from ITO Instruction Section 5.7 and Section 5.1.1.

67. Will the Government allow for a 2 page introduction to past performance volume? Offerors that are providing a past performance from a predecessor/subsidiary company must provide a narrative description of people, processes, or tools that will directly benefit the USAFA on this contract to be compliant with FAR subpart 15.305(2)(iii).

ANSWER: No. Offerors are to provide the information requested in the solicitation. Per ITO Attachment 4_PPI Tool Instructions, all areas mentioned can be provided within each citation. Reference answer to Question 50b regarding increase in citation page limit.

68. Reference Section 6 Contract Documents 6.6.4. Offeror and relevant Subcontractors must submit financial statements and year to date financial information. How should this information be submitted?

Can the subcontractors provide sealed packages to the prime to include in their proposal but only to be opened by the Government? Please provide specific instructions on how subcontractors should provide sealed packages with their financial information.

ANSWER: Two options will be acceptable to the Government. The subcontractor can provide a fully disclosed financial statement in a sealed package to the prime contractor which can be submitted with the prime proposal, only to be opened by the Government. If the subcontractor would instead prefer to send a fully disclosed financial statement directly to the Government, the subcontractor must ensure it states which prime proposal it is associated with. In addition, the prime proposal must clearly state that the subcontractor is providing a fully disclosed financial statement directly to the Government.

69. The RFP states that the font requirements for tables and graphics is no less than TNR 8 point. If the offeror is providing screen shots in the proposal response they will not be compliant with this requirement since they are directly from the internet. Will the Government confirm that screen shots will not be held to this requirement?

ANSWER: Per RFP Section 2.12.4, the font size shall be no less than Times New Roman 8-point font.

“Any text within tables, charts, graphs, and figures that do not meet this requirement will not be considered in the evaluation.”

70. This contract is a Small Business Set-Aside and therefore additional Small Business Subcontracting Goals do not apply. As such, will the Government remove the following two sections from the PPI Tool to allow for additional space to establish project relevance in other areas?

a. Include relevant information concerning your compliance with FAR 52.219-8, Utilization of

Small Business Concerns, on the contract you are submitting, if applicable.

b. Identify whether a subcontracting plan was required by the contract you are submitting. If one was required, identify in percentage terms the planned versus achieved goals during contract performance. Explain why goals were not met, if applicable.

ANSWER: No, the Government will not remove this requirement, it must be included with the Past Performance Volume.

71. Reference 3.6.1.2 – Organizational Chart. Request clarification. Is the Government requesting an organizational chart that maps to the AFCOLs or USAFA the level of service? Should we include one or two organizational charts – one that depicts AFCOLs manning levels and a second one that depicts the USAFA level of service?

ANSWER: The offeror is to provide information in accordance with the solicitation. If the organizational chart will change based on the different levels of service, then the offeror can provide that information.

72. Section 3.1, last paragraph, contains the following statement: “Any information provided that is not specifically requested as part of the subfactors will not be evaluated or considered in the award determination.”

The instructions for each subfactor lead with a general statement (e.g., “3.7.1 Offeror’s proposal shall describe offeror’s approach to provide civil engineering facility operations to meet PWS requirements, to include:”), followed by very specific instruction for topics to be included in the offeror’s response.

Will the Government please confirm that only the PWS items and or subjects specified in the subfactor criteria be included in the Offerors Technical proposal?

ANSWER: The offeror’s technical proposal will be evaluated in accordance with the Addendum to FAR 52.212-2, Evaluation – Commercial Items.

73. Reference 4.11 Organizational Structure Change History. There is a 2 page restriction for this section.

Would the Government consider increasing the page restriction to a total of 4 pages to accommodate not only a sufficient description for the primer offeror, but also teaming partners?

ANSWER: No. The page limit for the Organizational Structure Change History will remain at two pages.

74. RFP 2.12.10. Any instances of cross-referencing within a proposal volume shall include the page number and paragraph number. Will the Government allow for section numbers and not paragraph numbers since not all paragraphs in each section will be numbered?

ANSWER: The offeror is to provide information in accordance with the solicitation.

75. Reference Appendix A 3.5.22.1.1. Unaccompanied Personnel Housing. Data shown are for years 2010

– 2012. Request more recent data [through 2016] and number of change of occupancy workload for those years.

ANSWER: This listing has been updated to reflect data from Feb 2015 – Dec 2017. The updated listing will be attached in www.fbo.gov in conjunction with Amendment 2. During this timeframe, there were 209 Change of Occupancies (COM).

76. PWS Section 3.4.7.1 Locksmith Services. PWS states “Cadet dormitory keys are tracked by the Class System”. Please clarify if CE BMS SP has responsibility for this “Class System” tracking system or does the Cadet Support Services (CSS) Contract have this responsibility?

ANSWER: The SP does not have responsibility for the “Class System” tracking system. This is managed by the Cadet Wing’s Key Tracking system.

77. Cultural Resources Techs positions are listed in Appendix B but there are no position descriptions for these labor categories. Will the Government please provide position descriptions for these labor categories?

ANSWER: See PWS Sections 3.2.2.2 and 3.3.5.3 for Cultural Resource requirements. See PWS Section

4.4.2.5.11 for position qualification requirements.

78. Due to the expected amendment and answers to Q&A, will the Government please confirm there will be another opportunity to ask additional questions after the amendment is released?

ANSWER: The Government does not plan to provide for an additional Q&A period.

79. The PWS paragraphs listed in Section B do not include 3.1.1 (Strategic Vision and Transformation Initiatives). 3.1.3 & 3.1.4 (Program Compliance, Data Management), or 3.2.1 (Project Management).

Which CLINs should include these activities? Or are these not separately priced?

ANSWER: See revised Section B for CLIN descriptions.

80. The set formatting in the PPI tool formatting does not allow for all information requested to be included in the two pages allocated for each PPI citation. Would the Government consider increasing the page count to three pages per contract?

ANSWER: See answer to Question 50b.

81. Sections 3.7.1.2 and 3.4.1.2 ask the offeror to discuss its approach to prioritizing, managing, scheduling and executing preventive maintenance and recurring work. However, according to PWS 3.4.3, the cited work priorities and the dollar thresholds relate to direct scheduled work. Please confirm that the Government wants offerors to also address direct scheduled work and amend the RFP.

ANSWER: See revised ITO Instruction 3.7.1.2 and Section 3.4.1.2. This has been corrected to reflect Direct Scheduled Work.

82. Reference Section 6.4. Offerors are instructed to complete representations and certifications electronically. Please advise if the Government requires a printout of the completed electronic submission or instead, a statement confirming electronic submission is complete.

ANSWER: Per RFP Section 6.4, “…the offeror verifies, by submission of this proposal, that the representation and certifications currently posted electronically are correct.”

83. PWS 3.4.2.1 states: "SP shall develop the PM Program IAW RPIE Manufacturer's recommendations," yet in PWS 1.3, the scope directs the SP to use an Asset Management approach for facility maintenance and repair. Is there the latitude to use industry best practices and asset management principles rather than a strict OEM maintenance approach when developing the PM Program?

ANSWER: PWS paragraph 3.4.2.1, in its entirety, outlines the requirements for establishing the PM Program. “The SP shall prevent deterioration of RP beyond fair wear and tear and manage the life cycle cost of ownership through implementation of Preventive Maintenance (PM)/Recurring Work program, also referred to as Work Priority 2A, on all RP, RPIE, and RP Similar Equipment (RPSE). The SP shall develop the PM program IAW higher headquarters guidance, AF approved Preventive Maintenance Task Lists (PMTL), and IAW RPIE manufacturer’s recommendations. SP shall perform annual validation of all PM actions required to ensure PM actions are scheduled in Government designated database(s) system.

The SP shall ensure all new items as a result of acquisition, construction, repair by replacements, or items Found on Base (FOB) are included in the PM Program and information is entered/updated/maintained in BUILDER and all other pertinent Government databases (i.e. Real Property databases).”

84. PWS 3.4.2.4 requires the MMP to include a list of critical assets whose replace-upon-failure costs exceed DSW thresholds. Determining how much effort this will take requires a list of the critical assets.

Will the Government please provide the critical assets listing?

ANSWER: Per PWS Section 3.4.2, the contractor is required to develop the critical assets list. See Technical Library (CEO and CEI Folders) for current asset values of RPIE and RPSE covered under the PM program.

85. Appendix A shows 6,000 labor hours, $140,000 material cost, and $40,000 subcontract cost for USAFA Events. Is this the historical workload for CLIN X200 Special Events? How does this relate to the $160,000 base for proposal evaluation for CLIN X200? Does the Government anticipate a reduction in special events in the future?

ANSWER: Appendix A Section 3.4.1.6 represents the historical workload for USAFA Events. Events for CLIN X200 are in addition to those shown in Appendix A Section 3.4.1.6.

86. Reference Appendix A 3.4.1.6. Which CLINs should include the AF 1219 work and CWON work?

ANSWER: Direct Scheduled Work (DSW) – AFCOLS CLIN, Direct Scheduled Work (DSW) – USAFA CLIN, and Preventive Maintenance CLIN.

87. Reference Appendix A 3.4.1.5. Is this a monthly average or an annual average of DSWs?

ANSWER: See title of table – Monthly Average.

88. Reference PWS 3.3.1.1.2. PRS 38 identifies that the SP is responsible to conduct inspections annually (survey installation boundaries to identify any possible encroachments). Will the Government provide workload data on the quantity of annual installation boundaries that SPs will be required to survey?

ANSWER: See Appendix A, Workload, Section 3.3.1 Real Property Actions.

89. Reference PRS 37. Can the Government clarify if the Space Utilization Dataset is 100% accurate at this time or if Offerors will be responsible within their FFP to bring the data to a current state? If data is not 100% accurate at this time can the Government please provide Industry with an estimated percentage of accuracy of the current Space Utilization Dataset?

ANSWER: The Space Utilization Data Set is constantly evolving, and is required to be changed and updated as necessary. The SP performance requirements are outlined in PWS paragraph 3.3.1.2.

90. Reference PRS 8. Can the Government confirm that legacy GIS data (Table Maps) and data provided from external sources (i.e. CSU, CDOT) will not subject to a discrepancy for the SP?

ANSWER: Performance requirements for data provided from external sources is outlined in PWS paragraph 3.2.1.4.4.1.

91. Reference PWS 3.1.1. Can the Government clarify that for unknown Government designated replacement system(s), Section 1 language associated to variance in the workload of any area of more than 10% (plus) from the listed workload data applies, and that the SP may request a contract modification for associated cost?

ANSWER: If the amounts in the workload are exceeded, the contractor may submit a request for equitable adjustment. Refer to DFARS 252.243-7002, Request for Equitable Adjustment for further information.

92. Will the Government provide Industry with the dates of the last five (5 year) and three (3 year) inspections for equipment identified in Appendix D - Vertical Transport Equipment Listing?

ANSWER: The intent of the performance requirement is to perform a 5-year inspection in the base year of the contract to “reset the clock” for inspections now under the USAFA CE BMS contract. The 3-year inspection performance requirement has been deleted, see revised PWS paragraph 3.4.20.6.5.

93. Will the Government identify for Industry what percentage will be in-house designs?

ANSWER: See answer to Question 20a.

94. Reference PWS 3.2.1.4.4.3 Can the Government identify what the SP responsibility will be associated to the requirement for "development" of linear segmentation maps?

ANSWER: The contractor will be responsible for meeting the requirements of PWS paragraph 3.2.1.4.4.3.

95. Can the Government clarify if the BUILDER data is 100% accurate at this time or if Offerors will be responsible within the FFP to bring the data to a current state? If data is not 100% accurate at this time, can the Government please provide Industry with an estimated percentage of accuracy of the current BUILDER data?

ANSWER: The BUILDER database is constantly evolving, and is required to be changed and updated as necessary. The SP performance requirements regarding BUILDER are outlined throughout the PWS.

Reports from BUILDER are provided in the Technical Library (CEO Folder).

96. DIACAP was replaced with RMF, and EITDR was replaced with ITIPS. Will the Government be revising the PWS to reflect these changes?

ANSWER: See revised language in PWS paragraphs 3.3.2.3, 3.4.15.1.1, and Appendix A Section 3.3.2.

97. Can the Government confirm that legacy Utility Data is identified on existing as-builts? Can the Government clarify if Tab Map Data identifies with current, accurate Utility Data? If not, can the Government clarify if Offerors are required as part of their FFP to analyze Utility Data ensuring it is brought to a current state?

ANSWER: Legacy Utility Data is identified on existing as-builts. The legacy Utility Data system is constantly evolving, and is required to be changed and updated as necessary.

98. Reference PWS 3.4.22.11. Equipment Management identifies that CBRNE is GFP. Can the Government clarify if the SP is responsible within the FFP for the cost to maintain, repair, replace

CBRNE?

ANSWER: Requirements are clearly outlined in PWS paragraph 3.4.22.11. SP is responsible to maintain and repair CBRNE equipment. Revised PWS paragraph 3.4.22.11 states Government will replace CBRNE equipment.

99. Can the Government clarify the requirement identified in PWS 3.4.22.10? AFI 90-201 appears to remove this requirement unless requested by unit leadership.

ANSWER: AFMAN 32-1007 dictates the requirements outlined in PWS paragraph 3.4.22.10. See revised language in PWS paragraph 3.4.22.10.

100. Reference PWS 3.4.22.12. The SP is accountable to advise Government personnel of training requirements. Can the Government clarify if the SP will be held accountable for Government personnel to accomplish training?

ANSWER: The SP is required to show they advised Government personnel of the required training and made reasonable attempts to schedule the required training with the Government personnel. The SP will not be held accountable for the failure of the Government personnel who do not accomplish the training.

101. Reference PWS 3.4.22.14. Can the Government clarify? The USAFA IDP does not appear to reconcile with this requirement.

ANSWER: The Mobility Deployments Processing Line Briefings requirement is clearly defined in PWS paragraph 3.4.22.14.

102. For Priority 4 (Enhancements), the SHPO review can take, at minimum, 30 days to complete which would be outside of the SP control. Can the Government clarify if SHPO processing time will be considered/excluded from the completion metric?

ANSWER: See revised language for PWS paragraph 3.4.3.5.

103. Reference PWS paragraph 3.4.3.2. For Emergency Calls that occur after hours, weekends, or holidays, can the Government clarify if the requirement will be for the SP to order Emergency Materials the following duty day that the call was received?

ANSWER: Per PWS paragraph 3.4.3.2, “Material requirements for all Emergency CM work shall be ordered the same day the call is received.”

104. Reference PWS paragraph 3.4.3.2 – 3.4.4.3. As it relates to the DSW $50,000 deductible and the current identified metric, can the Government clarify if/how it will consider, within the identified metric, the potential time the SP will require to develop scope, costs, as well as potential material long lead times, for larger dollar efforts, particularly those associated to CLIN 0010?

ANSWER: Performance metrics and timelines are clearly defined in PWS Sections 3.4.3.2 – 3.4.4.3, as well as associated PRS items. There is no “CLIN 0010” work associated with DSW level work.

105. Reference PWS paragraph 3.4.9.1.1. For lightning protection that is required, but not currently installed, can the Government clarify if the SP is required to include associated costs within the FFP? If so, can the Government identify for Industry the anticipated required lightning protection requirements that are to be included in the FFP?

ANSWER: These types of requirements would be captured via the 332 process and would become part of either a planned Construction Project or DSW workload. Lightning protection is included in the workload (both in the DSW and project workloads)

106. The Government provided GFE identifies with the following categories of status; usable, operational, turn-in, marginal. Can the Government clarify if Offerors are to assume that GFE that is coded as turn-in, is no longer available to the SP? If so, can the Government please clarify if Offerors are responsible to include GFE categorized as turn-in, as part of the SP FFP cost? Can the Government please clarify if the SP is responsible for replacement cost of GFE (after its useful life) as part of the SP FFP? If so, will the Government please provide to Industry condition status of the GFE?

ANSWER: See answer to Question 12 regarding “turn-in”. Per PWS Section 4.1.1.2, “When required items become unserviceable through normal usage, they shall be replaced at the SP’s expense.”

107. PWS 4.4.2.2 Medical Facilities Maintenance Workers identifies with current certificate requirements for SP employees assigned to work in Medical Facilities. Can the Government clarify? There are no Medical type facilities identified as part of the performance requirements.

ANSWER: See revised PWS Section 4.4.2.2. This certification requirement has been removed.

108. PWS 4.5.1.1 Identifies that Supervisors must be provided in addition to the MTC, and that Supervisors shall be utilized in leadership roles only and shall not also be serving as MTC laborer/trades personnel. The MTC identifies Managers. Managers serve leadership and supervisory roles. Can the Government clarify that MTC identified Managers can perform supervisory roles and that Offerors are required to provide, in addition to the Managers identified in the MTC, Supervisors that Offerors determine are required above and beyond the MTC identified Managers?

ANSWER: Yes, this is correct.

109. INDRAC appears to no longer be available. Can the Government clarify the 3.4.22 Readiness and Emergency Management annual INDRAC requirement?

ANSWER: The SP is required to perform the requirement as stated in Appendix A paragraph 3.4.22.

110. With the requirements Section M identifies that Offerors are required to cover within Past Performance citations, will the Government consider adding additional page count from 2 pages each to 5 pages each?

ANSWER: See answer to Question 50b.

111.…