Attachment 06 Addendum 002 rev 1.pdf

PDF 19 KB Posted

Attached to
Mitchell Hall Renovation Phase 7 Federal contract opportunity
Solicitation number
FA7000-12-R-0015
Issued by
Department of the Air Force Headquarters Air Force Academy

About this file

Attachment 06 Addendum 002 rev 1

View the file

Other files for this federal contract opportunity

Other files attached to Mitchell Hall Renovation Phase 7, newest first.
File Type Posted
01 FA7000-12-R-0015-0004 Amendment.pdf PDF
MEMORANDUM TO OFFERORS 5 Sep 12.docx DOCX document
Bid-RFI-Responses-Mitchell Phase 7 RFI Clarification Final.pdf PDF
01 FA7000-12-R-0015-0003 Amendment.pdf PDF
Attachment 06 Addendum 002 rev 1.pdf PDF
Bid-RFI-Responses-Mitchell Phase 7 Final.pdf PDF
Attachment 12 CS17754-125-R1 soils investigation.pdf PDF
Attachment 14 bid phase sketch sk-1.pdf PDF
Attachment 09 Praxis Rpt II.pdf PDF
Attachment 17 Exposed Aggregate Concrete - Type 2.pdf PDF
Attachment 18 SECTION 02716 Drainage Mat.pdf PDF
Attachment 16 Hot Fluid Applied Rubberized Asphalt Waterproofing.pdf PDF
Attachment 13 USAFA Mitchell Hall ACM Specification.pdf PDF
Attachment 11 Door Project Asbestos Report.pdf PDF
Attachment 05 Addendum 001 rev 1.pdf PDF
Attachment 07 Addendum 003.pdf PDF
Attachment 15 bid phase sketch sk-2.pdf PDF
Attachment 03 Davis Bacon Wage Determination 08172012.pdf PDF
Attachment 08 Praxis Rpt I.pdf PDF
Attachment 10 Praxis Rpt III.pdf PDF
01 FA7000-12-R-0015-0002 Amendment.pdf PDF
FA7000-12-R-0025 Mitchell Site Vist and attendance Sheets.pdf PDF
01 FA7000-12-R-0015-P02 Amendment.pdf PDF
Brand Name Justification Notifier.pdf PDF
Brand Name Justification Siemens.pdf PDF
Attachment 06 Addendum 002.pdf PDF
Attachment 03 Davis Bacon Wage Determination.pdf PDF
FA7000-12-R-0015 Solicitation.pdf PDF
Attachment 04 Past Performance Questionnaire.pdf PDF
Attachment 05 Addendum 001.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

10TH MISSION SUPPORT GROUP

USAF ACADEMY, COLORADO

NOTICE: Failure to acknowledge all amendments may cause rejection of the offer.

ADDENDUM 002 REV 1

Repair Mitchell Hall Phase 7.

Date of Issue: 24 August 2012

Project Number: XQPZ 09-0103G

SUBJECT: ADDENDUM No. 002 Rev 1 Drawings and specification for construction of Repair Mitchell Hall Phase 7.

TO: Prospective Offerors and Others Concerned-

The Drawings and Specifications for subject project are hereby modified as follows (revise all Drawings indices lists, Specification indices, table of contents, sections, and attachments lists accordingly)

CLIN 0001:

The contractor shall provide a separate line item pricing for all other items not shown or identified in the drawings below. This will be classified as repair construction by the Government

CLIN 0002:

The contractor shall provide a separate line item pricing for the following items shown in the drawings. This will be classified as minor construction by the Government.

1) Sheet A-401: Key Note 3, 15, 30, 31 and 56.

2) Sheet A-404: Key Note 5, 7, 8, 20, 26, 29, 33 and 38.

3) Sheet A-406: Key Note 16.

4) Sheet A-601: Door 110A, 110B and 110C.

5) Sheet F-101: Key Note 4.

6) Sheet M-101: Key Note 7.

7) Sheet M-103: Key Note 10.

8) Sheet M-110: Key Note 2.

9) Sheet P-101: Key Note 10.

10) Sheet EL-101: Key Note 1.

11) Sheet EP-101: Key Note 5.

12) Sheet EY-101 Key Note:1.

DEPARTMENT OF THE AIR FORCE

10TH MISSION SUPPORT GROUP

USAF ACADEMY, COLORADO

NOTICE: Failure to acknowledge all amendments may cause rejection of the offer.

Revision 1 to this addendum is to add demolition instructions and clarifications.

DEMOLITION INSTRUCTIONS:

Drawing Sheet MD-101 Note 3.

Drawing Sheet MD-103 Note 3.

Drawing Sheet MD-106 Note 3.

Drawing Sheet MD-107 Note 3.

Drawing Sheet MD-110 Note 3.

Drawing Sheet MD-111 Note 3.

Drawing Sheet MD-112 Note 3.

Drawing Sheet MD-113 Note 3.

Drawing Sheet MD-115 Note 3.

Drawing Sheet MD-116 Note 3.

Drawing Sheet MD-402 Note 3.

Drawing Sheet MD-403 Note 3.

The General Demolition Note 3 for each of the drawings shown above reads as follows:

Contractor shall remove all materials as required and shall give the owner the opportunity to inspect such materials for potential salvage. Contractor shall remove from the site all materials deemed “non-salvageable” by the owner. Contractor shall turn over to the owner all materials deemed “salvageable” by the owner.

CLARIFICATION:

For bidding purposes, the contractor shall be responsible for the disposal of all materials removed as part of the demolition work.