INC Form 1101 Untabulated COST ESTIMATE FOR 13-1096
View the file
Other files for this federal contract opportunity
Show all 50
Roads and Grounds IDIQ Base Contract has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IDIQ Price
| 100% | FOR OFFICIAL USE ONLY | This is NOT a comprehensive cost estimation macro. The User | |||||||||||
| CONSTRUCTION COST ESTIMATE BREAKDOWN | SH: 1 OF 3 | is required to do many of the revisions manually. The User | |||||||||||
| CONTRACTOR | ADDRESS: | INCIRLIK HAVA ALANI-ADANA/TURKEY | must be capable of using a spreadsheet with minimum help. | ||||||||||
| WORK LOCATION: | INCIRLIK HAVA ALANI-ADANA | ||||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | The cost form is prepared for Quattro Pro version 4.0. The printer | |||||||||||
| REPAIR VARIOUS BASE ROADS | $ | 0.00 | selected is Canon Laser Printer LPB-4. Hovewer, as the program's | ||||||||||
| PURCHASE REQUEST NUMBER: | PROJECT NUMBER | soft fonts are used, changing a printer should not present problems. | |||||||||||
| LJYC 13-1096 | |||||||||||||
| UNIT OF | TOTAL COST | It is possible that, at the first trials, problems with page fitting may | |||||||||||
| LINE | MEASURE | QUANTITY | $ | $ | arise. The User should experiment with the size of the first | ||||||||
| NO | UNIT | TOTAL | font on the font table. | ||||||||||
| ITEMS | |||||||||||||
| (2) | (3) | (4) | (5) | The User is recommended to work in protected mode initially to avoid | |||||||||
| erasing any formulas. | |||||||||||||
| R E C A P I T U L A T I O N | |||||||||||||
| RECAP sheet formulas and the discipline totals at the end of each | |||||||||||||
| discipline need to be manually revised with every new estimate. | |||||||||||||
| There are three utility macros that can be started by pressing | |||||||||||||
| simultaneously, the <Alt> key and one letter (See below). | |||||||||||||
| 1 | CIVIL WORKS TOTAL | $0.00 | <Alt>C ....... Erases the contents of one page of cost estimate | ||||||||||
| <Alt>Z ....... Inserts a new cost estimate page | |||||||||||||
| <Alt>X ....... Adds a new cost estimate page at the very end | |||||||||||||
| Macros <Alt>C and <Alt>Z must be started with the cursor parked | |||||||||||||
| in column A, and right below the cell containing page break, just | |||||||||||||
| before the page the contents of which are to be erased, or | |||||||||||||
| before the location of the new page to be inserted. | |||||||||||||
| To insert new items in a page use and empty page as a holding tank | |||||||||||||
| and rearrange items by copying ("copy special, contents", to avoid | |||||||||||||
| disturbing the cell formats) to and from it. Do not use "move" | |||||||||||||
| untill you feel comfortable with the spreadsheet. | |||||||||||||
| TOTAL | $0.00 | ||||||||||||
| 0.00 | |||||||||||||
| 12 | Demolish asphalt road, asphalt only | CM | $0.00 | ||||||||||
| 17 | Excavation by hand | CM | $0.00 | ||||||||||
| The form is designed using for A4 size, for 8.5"x11" minor | |||||||||||||
| 18 | Unclassified excavation (Bulk), including concrete, hauling, loading and disposal w/machine | CM | $0.00 | adjusments may be required. To print on A4, set page break | |||||||||
| options in the printer page layout to "NO". | |||||||||||||
| 21 | Compaction by hand with plate or rammer compactor | SM | $0.00 | ||||||||||
| 28 | Provide & Install Graded Crush Aggregate Base Course, including loading, hauling, spread | CM | $0.00 | ||||||||||
| 42 | Provide & Install Type II Asphalt Binder Course | CM | $0.00 | ||||||||||
| The discipline totals must be centered, written in uppercase, | |||||||||||||
| 43 | Provide & Install Primer Coat (MC30) | TON | $0.00 | ||||||||||
| The discipline totals must be centered, written in uppercase, | |||||||||||||
| 74 | Saw cut construction joints | LM | $0.00 | ||||||||||
| 221 | Conduct Compaction Test | EA | $0.00 | ||||||||||
| 119 | Provide and Apply one reactive comp.paint (KANAT PAINT , KANTEX 64710 or equal) c/w type 1glass beads, by machine | SM | $0.00 | ||||||||||
| 225 | Provide & Install Temporary Construction Fencing | LM | $0.00 | ||||||||||
| TOTAL | $0.00 | ||||||||||||
| feet - SF, linear feet - LF, board feet - BF, each - EA, pound -LB). | |||||||||||||
| Col 3 Quantity. Contractor's estimate of quantity required in terms of unit of measure (column 2). Items and units of measure will be | |||||||||||||
| funished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will | |||||||||||||
| be issued. Otherwise, the contractor is responsible for determining quantity estimates. | |||||||||||||
| Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1. | |||||||||||||
| Col 6, 7 and 8 Labor Costs. Enter in Col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. | |||||||||||||
| Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost. | |||||||||||||
| Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the contract | |||||||||||||
| and of significant dollar value. | |||||||||||||
| Col 10 Line Total. Self-explanatory. | |||||||||||||
| NOTE: In addition to the other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last | |||||||||||||
| page as follows. | |||||||||||||
| TOTAL MATERIAL COSTS | $ | N/A | |||||||||||
| ------- | |||||||||||||
| TOTAL LABOR COSTS | $ | N/A | |||||||||||
| ------- | |||||||||||||
| TOTAL OTHER DIRECT COSTS | $ | N/A | |||||||||||
| ------- | |||||||||||||
| TOTAL DIRECT COSTS | $ | 0.00 | |||||||||||
| Included | ------- | ||||||||||||
| OVERHEAD | In Unit Price | $ | N/A | ||||||||||
| ------- | |||||||||||||
| SUBTOTAL | $ | 0.00 | |||||||||||
| Included | ------- | ||||||||||||
| PROFIT | In Unit Price | $ | N/A | ||||||||||
| ------- | |||||||||||||
| TOTAL PRICE | $ | 0.00 | |||||||||||
| -------- | |||||||||||||
| DATE : | FIRM NAME : | ||||||||||||
| ------------------------------------- | --------------------------------------------------- | ||||||||||||
| TITLE : | BY : | ||||||||||||
| ----------------------------------- | ------------------------------------------------------------------- | ||||||||||||
| REPAIR VARIOUS BASE ROADS | |||||||||||||
| INSTRUCTIONS TO OFFERORS | |||||||||||||
| 1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and | |||||||||||||
| estimated costs (and attached supporting information) suitable for detaied review and analysis. Prior to the award of a contract resulting from | |||||||||||||
| this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data | |||||||||||||
| (see ASPR 3-807.3(e) and 3-807.4) | |||||||||||||
| 2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit with this | |||||||||||||
| form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an appropriate review and | |||||||||||||
| analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clear understanding of | |||||||||||||
| a. The existing, verifiable data. | |||||||||||||
| b. The judgmental factors applied in projecting from known data to the estimate, and | |||||||||||||
| c. The contingencies used by the offeror in his proposed price. | |||||||||||||
| In short, the offeror's estimating process itself needs to be disclosed. | |||||||||||||
| 3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate), | |||||||||||||
| and made available to the contracting officer or his authorized representative upon request. | |||||||||||||
| 4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the | |||||||||||||
| purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate | |||||||||||||
| evaluation of such cost or pricing data, along with the computations and projections used herein. This right may be exercised in connection | |||||||||||||
| with any negotiations prior to contract award. | |||||||||||||
| (Reverse of Computer Generated AF Form 3052., AUG 93) |
back
| INSTRUCTIONS FOR COMPLETING AF FORM 3052 | SH: 3 OF 3 | |||||
| Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to | ||||||
| permit itemizing of all direct costs. | ||||||
| Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples : square yards - SY, cubic yards - CY, square | ||||||
| feet - SF, linear feet - LF, board feet - BF, each - EA, pound -LB). | ||||||
| Col 3 Quantity. Contractor's estimate of quantity required in terms of unit of measure (column 2). Items and units of measure will be | ||||||
| funished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will | ||||||
| be issued. Otherwise, the contractor is responsible for determining quantity estimates. | ||||||
| Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1. | ||||||
| Col 6, 7 and 8 Labor Costs. Enter in Col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. | ||||||
| Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost. | ||||||
| Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the contract | ||||||
| and of significant dollar value. | ||||||
| Col 10 Line Total. Self-explanatory. | ||||||
| NOTE: In addition to the other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last | ||||||
| page as follows. | ||||||
| TOTAL MATERIAL COSTS | $ | N/A | ||||
| ------- | ||||||
| TOTAL LABOR COSTS | $ | N/A | ||||
| ------- | ||||||
| TOTAL OTHER DIRECT COSTS | $ | N/A | ||||
| ------- | ||||||
| TOTAL DIRECT COSTS | $ | $0.00 | ||||
| Included | ------- | |||||
| OVERHEAD | In Unit Price | $ | N/A | |||
| ------- | ||||||
| SUBTOTAL | $ | $0.00 | ||||
| Included | ------- | |||||
| PROFIT | In Unit Price | $ | N/A | |||
| ------- | ||||||
| TOTAL PRICE | $ | 0.00 | ||||
| -------- | ||||||
| DATE : | FIRM NAME : | |||||
| ------------------------------------- | ||||||
| TITLE : | BY : | |||||
| ----------------------------------- | ||||||
| REPAIR VARIOUS BASE ROADS | ||||||
| INSTRUCTIONS TO OFFERORS | ||||||
| 1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and | ||||||
| estimated costs (and attached supporting information) suitable for detaied review and analysis. Prior to the award of a contract resulting from | ||||||
| this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data | ||||||
| (see ASPR 3-807.3(e) and 3-807.4) | ||||||
| 2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit with this | ||||||
| form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an appropriate review and | ||||||
| analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clear understanding of | ||||||
| a. The existing, verifiable data. | ||||||
| b. The judgmental factors applied in projecting from known data to the estimate, and | ||||||
| c. The contingencies used by the offeror in his proposed price. | ||||||
| In short, the offeror's estimating process itself needs to be disclosed. | ||||||
| 3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate), | ||||||
| and made available to the contracting officer or his authorized representative upon request. | ||||||
| 4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the | ||||||
| purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate | ||||||
| evaluation of such cost or pricing data, along with the computations and projections used herein. This right may be exercised in connection | ||||||
| with any negotiations prior to contract award. | ||||||
| (Reverse of Computer Generated AF Form 3052., AUG 93) |