FA5685-14-R-0012-0003.doc
DOC document 104 KB Posted
- Attached to
- Roads and Grounds IDIQ Base Contract Federal contract opportunity
- Solicitation number
- FA5685-14-R-0012
About this file
Amendment 0003
View the file
Other files for this federal contract opportunity
Show all 50
Roads and Grounds IDIQ Base Contract has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
INSTRUCTION TO OFFERORS
1. To assure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein. Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors or subfactors. Failure to meet a requirement may result in an offer being ineligible for award. Offerors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale. The response shall consist of four (4) separate parts; Part I – Contract Documentation, Part II - Price Proposal, Part III - Technical Proposal, and Part IV – Past Performance.
a. Proposals for the work described herein, must be received no later than the date and time indicated on Standard Form 1442, Page 1, Section 13. A., at the following address:
39 CONS/LGC - FA5685 (FOREIGN)
39 UNCU KONTRAT SUBAYLIGI
BINA NO. 485 10.NCU TANKER
US KOMUTANLIGI
INCIRLIK/ADANA
TEL: 90-322-316-8076 FAX: 90-322-316-1090
The envelope used in submitting your reply must be plainly marked with the solicitation number, FA5685-14-R-0012, title “Incirlik Roads and Grounds IDIQ” along with date and local time set forth for receipt of proposals.
FAX and email proposals will NOT be acceptable.
2. The Contracting Officer (CO) has determined there is a high probability of adequate price competition in this acquisition. Upon examination of the initial offers, the CO will review this determination and if, in the CO’s opinion, adequate price competition exists, no additional cost information will be requested and certification under FAR 15.406-2 will not be required. However, if at any time during this competition the CO determines that adequate price competition no longer exists; offerors may be required to submit information to the extent necessary for the CO to determine the reasonableness and affordability of the price.
3. THE MAGNITUDE OF CONSTRUCTION is more than $ 10,000,000.00 IAW FAR 36.204(h).
4. Specific Instructions:
a. PART I – CONTRACT DOCUMENTATION
i. Complete blocks 14, 15, 17, 18, 19, 20 and 22 of the SF 1442. In doing so, the offeror accedes to the contract terms and conditions as written in the RFP Section A through M.
ii. For Sections F through M, the offeror shall submit only those pages that require a fill-in..
iii. Acknowledgement of all amendments to the solicitation in accordance with the instructions on the SF 30 (Amendment to Solicitation/Modification of Contract)
b. PART II – PRICE PROPOSAL
i. Offerors will be required to provide a total unit price for each item and for each contract period within the Bid Schedule based upon the total amounts for each contract period within the bid schedule. Bid schedule will be totaled for each year proposed on the solicitation. Pricing proposed within the Bid Schedule will include labor, other direct costs, overhead and profit. The Bid Schedule will be totaled to obtain the combined amount (base year and (4) option periods). The proposed combined price of the Bid Schedule will be placed in Block 22 SF 1442. The combined amount of the Bid Schedule will be used for evaluation purposes to determine the price fair and reasonable along with a comparison to the IGE. Offerors will only propose on a quantity of one (1) for each identified item on the Schedule of Items. The Bid Schedule SHALL be incorporated in the resultant contract.
ii. Additionally, pricing for each seed project will be provided on the cost breakdown documents (INC 1101). The individual breakdowns may be used for further evaluation to assist in price comparison with proposed items listed on the Bid Schedule. This will ensure the pricing used on the seed projects compare directly to the Bid Schedule.
iii. CLINs on the resulting contract are Not Separately Priced (NSP). Prices are provided on the Bid Schedule and seed projects. (INC 1101).
c. PART III – TECHNICAL PROPOSAL
i. Subfactor 1 – Quality Control: The offeror shall submit a quality control plan (QCP), to provide information that effectively represents their quality control program and methodology. The offeror’s QCP and approach shall address and provide all the required content outlined in the Project Specifications – IDIQ Specifications Section 01 45 04.00 10 para 3.2.1 (Page. 87, “Content of the QCP”). Any innovative procedures or methods shall be explained in detail.
ii. Subfactor 2 – Technical Capabilities: The offeror shall provide information that effectively represents their technical expertise and project management capabilities. All techniques and resources shall meet or exceed commercial standards routinely used by the construction industry for same or similar projects and be in accordance with the regulations and standards as stated in the specifications. Any innovative procedures or methods shall be explained in detail. As a minimum, offerors shall include:
1. A detailed shop drawing and narrative of how you would construct a typical two-lane asphalt roadway on Incirlik Airbase, complete with conversion of open to closed storm drain, relocation of water lines and high voltage electrical lines, and installation of sidewalks, curbs and AT/FP walls, in accordance with the standards, specifications, and bid schedule of this contract. In your narrative, provide details of means and methods of construction and the order that things will be built. The drawings shall represent the offeror’s technical capabilities and expertise to understand basic design principles for roadways and incidental infrastructure systems (crossing the roadway, transversely). Also, list the make and model of the equipment that needs to be used to conduct all facets of roadway project.
2. A narrative description of a situation where you would use lime stabilization of the subgrade. Include any innovative techniques, procedures, and alternative materials that you might use for these special cases. Also, list the make and model of the equipment that needs to be used to conduct all facets of soil stabilization.
3. A narrative description of the procedures and materials that you would use to conduct a patch repair on the airfield, including spall repair, partial slab repair (i.e. half surface area/half depth), full slab repair (entire surface area, full depth). Also, list the make and model of the equipment that needs to be used to conduct all facets of airfield patch repair.
4. A narrative description of the procedures, methods, and materials that you would use to construct a concrete paved parking lot. Describe procedures to install/repair new and existing joints in sidewalks, curbs, retaining walls, and airfield pavement.
5. A narrative description of the procedures, methods, equipment and materials to apply infrared asphalt patching. Also, list the make and model of the equipments that needs to be used to conduct all facets of infrared asphalt patching.
6. Seed Projects: The offeror shall submit the following for the seed projects listed below:
a. LJYC 10-1099 Repair Storm Drainage, B500. Provide the following:
i. proposed materials for the major elements
1. Civil Works.
1. Catch Basin
2. Sump Pump
3. HDPE pipe
b. LJYC 13-1095 Repair Various Base Roads
i. proposed materials for the major elements
1. Civil Works.
1. Total number of crews, size of each crews (i.e, number of personnel)
2. Traffic Paint
c. LJYC 13-1096 Repair Various Base Roads
i. proposed materials for the major elements
1. Civil Works.
1. Total number of crews, size of each crews (i.e, number of personnel)
2. Traffic Paint
Technical Capabilities: A narrative shall demonstrate the Offeror’s technical capabilities, expertise, and a sound approach and method for accomplishing work requirements for all three (3) seed projects listed above with the appropriate skills, equipment, and materials, in the appropriate quantities to meet standards IAW 2012 Specifications for Roads and Grounds ID/IQ Contract. Each offeror shall submit proposed materials for each seed project IAW with Schedule of Materials Submittals listed in Section J. The offeror’s proposed material listing, subcontracting plan, and proposed equipment shall be incorporated into any resultant contract.
Project Schedule (PS): A progress schedule for all major construction elements for the three (3) seed projects shall be provided based upon the Offeror’s proposed performance period. Offerors shall use both the AF Form 3064 or equivalent, and a Gantt chart. All milestones shall be annotated with actual dates with a line graph. .
d. PART IV – PAST PERFORMANCE - The offeror shall provide recent and relevant past performance on no more than three (3) contracts with no more than five (5) pages per contract listed.
i. Recent Past Performance Information: To be recent, the effort must be ongoing (at least 50% complete) or must have been completed within the past three (3) years from the date of issuance of this solicitation. Past performance information that is not recent will not be evaluated to assess performance.
ii. Relevant Past Performance Information: Relevancy is defined as efforts which are similar in magnitude and complexity. Relevancy in regards to complexity includes performance for similar work relating to performing road construction/repair. Relevancy in regards to magnitude includes contracts/projects with a minimum value of $3M or a combined value of $3M annually.
iii. Provide any information currently available (letters, metrics, customer surveys, independent surveys, etc.) which demonstrates customer satisfaction with overall job performance and quality of completed product for relevant past efforts/contracts. In addition, explain corrective actions taken in the past, if any, for substandard performance and any current performance problems such as cost overruns, extended performance periods, numerous warranty calls, etc.
iv. Performance Surveys/Past Performance Questionnaires: Offeror will complete and return the Past Performance Questionnaire (PPQ) as provided in Section J of this RFP for up to three (3) projects. The PPQ must be completed by the raters and not by potential offerors. Furnish the following information for each contract listed:
1. Company/Division name
2. Product/Service
3. Contracting Agency/Customer
4. Contract Number
5. Contract Dollar Value
6. Period of Performance
7. Verified, up-to-date name, address, fax & telephone number of the contracting officer
8. Comments regarding compliance with contract terms and conditions
9. Comments regarding any known performance deemed unacceptable to the customer, or not in accordance with the contract terms and conditions.
An English speaking representative point of contact, including name, phone number, fax number and email address (if possible) should be provided for each project submitted.
NOTE – If a teaming arrangement is contemplated, provide complete information as to the arrangement, including any relevant and recent past performance information on previous teaming arrangements with the same partner. If this is a first time joint effort, each party to the arrangement must provide a list of past and present relevant contracts.
Subcontractor Consent: Past performance information pertaining to a subcontractor cannot be disclosed to the prime offeror without the subcontractor’s consent. Provide with the proposal a letter from all subcontractors that will perform major or critical aspects of the requirement, consenting to the release of their past performance information to the prime contractor.
5. Providing a Fully Responsive Proposal. An offeror package that fails to contain the following may result in proposal being considered nonresponsive and therefore not considered for award. Documents submitted in response to this RFP must be fully responsive to and consistent with the following:
a. Requirements of the RFP (CLINs & PWS) and government standards and regulations pertaining to the SPECIFICATIONS.
b. All required entries in the Bid Schedule
c. All Attachments which require fill-in information.
d. Ensure SF 1442 is completed, signed and dated. The redacted digital copy of the proposal shall not include any information such as stamp, name, etc., which indicates the offeror’s identity.
e. Evaluation Factors for Award in Section M of this RFP.
f. Any limitation on the number of proposal pages. Pages exceeding the page limitations set forth in this Section L will not be read or evaluated, and will be removed from the proposal.
g. Acknowledgement of all amendments to the solicitation in accordance with the instructions on the SF 30 (amendment form)
6. Format for Volumes I, II, and III shall be as follows: This section provides general guidance for preparing proposals. Offeror’s proposals must include all data and information requested by this solicitation and must be submitted and conducted in strict accordance with these instructions. Non-conformance with the specific organization, content, and page limitations may result in mis-evaluation of proposals or depending on the magnitude of the non-conformance; the proposals may be eliminated from further consideration. Telegraphic offers and alternate proposals will not be considered.
a. The proposals will be 8 1/2” x 11” paper except for fold-outs used for charts, tables, or diagrams, which may not exceed 11” x 17”.
b. A page is defined as one face of a sheet of paper containing information.
c. Typing shall not be less than 12 pitch.
d. Elaborate formats, bindings or color presentations are not desired or required.
e. Copies/Page Limit: copies of each volume shall be submitted in accordance with the chart below:
| Part |
| Title |
| Copies |
| Other Instructions/Limitations |
| I |
| Contract Documentation |
| 1 Original + 1 Digital Copy |
| Be sure to sign 1442 upon submission (and acknowledge amendments if applicable). |
| II |
| Price Proposal |
| 1 Original + 1 Digital Copy |
| Bid schedule and seed project 1101 filled out. |
| III |
| Technical Capability |
| 1 Original + 1 Digital Redacted Copy |
| -Limited to 75 pages |
| IV |
| Past Performance |
| 1 Original + 1 Digital Copy |
| -Up to three(3) projects |
f. All text must be legible and easily read. All text shall be typed single-spaced. Margins (1-inch) shall be clean and clear. Each volume shall be contained within a separate 3 or 2-ring binder (no heat or spiral bound volumes). The Quality Control Plan and Technical Capability section shall be separated within Volume II. Project Schedules shall be developed in Microsoft Project format, printed, and sufficiently sized for clear readability.
g. Each proposal volume shall reflect the volume number, offeror name, address, and telephone number on the cover. Each volume shall contain a Table of Contents, List of Tables, List of Figures, List of Appendices, and List of Acronyms. Page and volume numbers shall appear on the bottom of each page.
h. Proposal clarity, organization, and cross-referencing are mandatory. No material shall be incorporated by reference. General cross-references or cross-referencing guides will not be considered as appropriate cross-reference. In order for the proposal to receive an in-depth evaluation, it is necessary that the proposal be presented in a manner, which will provide clarity, organization and cross-referencing as required.
i. Each evaluation factor shall be described in a separate section, appropriately tabbed in a report form. The information in all volumes shall be concise.
j. ALL PROPOSALS SHALL BE IN ENGLISH.
7. Important Information
a. SITE VISIT. A site visit/pre-proposal conference will be conducted in accordance with clause 52.236-27. Offerors are urged and expected to inspect the site where work will be performed.
PLEASE NOTE: In the event a contractor is denied access from TURAF on the date of the Pre-Proposal Conference, a copy of the CD-ROM (which contains all necessary proposal documents) will be furnished. NO ADDITIONAL SITE VISIT WILL BE CONDUCTED.
b. Contractors should be aware that this is a Turkish Installation and that all access to this installation is granted by the TURAF, the US Government shall not be responsible for late proposals due to base entry procedures. Therefore SOME DELAYS SHOULD BE ANTICIPATED WHEN HAND CARRYING PROPOSALS. Offeror should allow sufficient time to arrive and submit the proposals to Contracting Office prior to the set closing time. Late proposals will be processed in accordance with the provisions “Late Submission, Modifications, and Withdrawals of Proposals”. If a gate access is not granted please contact the CO immediately. The contractors are responsible for coordinating and processing gate pass requests in a timely manner. Furthermore, contractors must consider that although the duty day is Monday through Friday from 07:30 to 16:30, contractors may not get to the job site at 07:30 due to TURAF gate entrance procedures. Also, contractors need to exit the base by 16:30. This may require contractors to stop work, prepare to leave the base, and clean up prior to 16:30. Contractors are encouraged to take this into consideration when proposing a delivery or performance time. The US Government shall not be responsible for delays due to in-processing or out-processing the base.
c. All contractors’ questions in response to this solicitation must be emailed to zeynep.kis.1.tr@us.af.mil and kurt.mckay@us.af.mil no later than 16 July 2014 at 16:00 local time. All questions/answers resulting from this solicitation will be disseminated via email or posting to FBO.
d. The US Government may award a contract based on initial proposals received, without discussion of such proposals, to the offeror providing the best value to the US Government as evaluated using applicable factors. Accordingly, each initial proposal should be submitted on the most favorable terms from a price and technical standpoint that the offeror can submit to the US Government. However, the US Government may request additional information from offerors of proposals, which clarifies, supplements and/or changes, any proposal as submitted.
e. Each offeror’s ability to perform the work set forth in this solicitation will be evaluated on the basis of personnel knowledge and understanding of the work, the quality provided by personnel total proposal and personnel capability and responsibility to accomplish the project. The evaluation will be based on the offeror’s proposal. The proposals shall represent a comprehensive straightforward analysis of the resources and expertise required to perform the work. While knowledge of the RFP requirements is a prerequisite to preparing proposals, restatement of the RFP requirements shall be avoided. Proposals shall emphasize knowledge and understanding of work performance, not work identification.
f. Bond Requirements. All firms shall submit a Bank Letter of Guarantee in the amount IAW Section H, Incirlik Instructions 02 of this solicitation and shall be submitted within 10 calendar days upon award of the contract. Alternatively, firms may submit a bid bond and Performance Bond in accordance with FAR 52.228-1 Bid Guarantee and FAR 52.228-15 Performance and Payment Bonds-Construction. In addition to their Bank Letter of Assurance or Bank Letter of Guarantee, offerors may be required to provide additional information at a later date if needed to verify financial responsibility to perform the contract.
g. In accordance with AFFARS 5332.703-2(e) funds are not presently available for this project. No award will be made under this solicitation until funds are available. The US Government reserves the right to cancel this solicitation, either before or on 30 Sep 14, with no obligation to the offeror by the US Government.
h. DECA Statement. In Accordance with FAR Part 6.101(a) and (b) Policy, this requirement is being solicited as Full and Open without exclusions.
However, due to an established economic agreement between the United States Government and the Government of Turkey, the U.S. Air Force anticipates to award this solicitation to a business concern within the country of Turkey; as required by the Defense and Economic Cooperation Agreement, Supplementary Agreement 3, Article VI “For the purposes of this Agreement, material, equipment, provisions, supplies, services, and civilian labor required by the Government of the United States shall be procured in Turkey to the extent feasible.” If it is discovered that award to a business concern within the country of Turkey is not feasible, the U.S. Air Force reserves the right to make award to a business concern that is not within the country of Turkey.
i. Technical tradeoff will not be made and no additional credit will be given for exceeding acceptability. Award will be made to the acceptable offeror with the lowest evaluated price, which deemed responsible in accordance with the Federal Acquisition Regulation and whose proposal conforms to the solicitation requirements, specifically Contract Line Items (CLIN). The solicitation requirements include all stated terms, conditions, representation, certifications, and other information required by this solicitation. Therefore, each initial offer should contain the offeror's best terms from a price and technical standpoint
SECTION M - EVALUATION FACTORS FOR AWARD
The following have been modified:
EVALUATION
BASIS FOR AWARD
M-1
1. Basis for Contract Award. This is a Lowest Price Technically Acceptable (LPTA) source selection conducted in accordance with FAR Part 15. The Government intends to award a minimum of two (2) with a target of four (4) IDIQ contracts from proposals deemed to be the best value to the US Government. The Government will award a task order in the amount of the minimum guarantee to each IDIQ awardee at the time of basic contract award for a post-award conference.
Awards may be made to the offerors who are deemed responsible in accordance with the FAR Part 9.1, as supplemented, whose proposals conform to the solicitation’s requirements (to include all stated terms, conditions, representations, certifications, and all other information required by Section L of this solicitation) and are judged, based on the evaluation factors and subfactors, to represent the lowest price technically acceptable proposals. While the Government will strive for maximum objectivity, the source selection process, by its nature, is subjective; and therefore, professional judgment is implicit throughout the entire process.
M-2 EVALUATION FACTORS
1. Evaluation Factors and Subfactors. The following evaluation factors and subfactors will be used to evaluate each proposal. The Government will evaluate proposals for acceptability, but will not rank the proposals by the non-price factors or subfactors.
Factor 1: Price Factor 2: Technical
Subfactor 1: Quality Control Plan
Subfactor 2: Technical Capability
Subfactor 3: Schedule
Factor 3: Past Performance
a. Contract Documentation: In order to be considered for award, proposal must fit guidelines outlined in section L of this solicitation titled: Part I – Contract Documentation.
b. Price: Prices will be evaluated for completeness, reasonableness, and balance IAW FAR 15.305(a)(1) and FAR 15.404. Offerors will be required to provide a total unit price for each item and for each contract period within the Bid Schedule based upon the total combined amount (base year and (4) option periods). This amount will be shown in block 22 of the SF 1442. Only offers in United States Dollars (USD) currency will be accepted. Additionally, pricing for each seed project is to be provided on the cost breakdown documents (INC 1101). The individual breakdowns may be used for further evaluation to assist in price comparison with proposed items listed on the Bid Schedule. This will ensure identical pricing rates are being used on the three (3) seed projects and Bid Schedule.
i. The Bid Schedule will be evaluated for balance by selecting the listed twenty (20) line items as well as randomly selecting 20% of the remaining line items for evaluation. The random 20% will be produced using http://www.randomizer.org/form.htm. In an effort to avoid redundancy, the government will randomize 30% via the website and skip over any number generated that corresponds to the 20 high use items already identified.
a. Listing of 20 High use Items
| Item Number |
| Description |
| 19 |
| Unclassified excavation (Bulk), soil only, hauling, loading and disposal w/machine |
| 20 |
| Trench Excavation by machine |
| 25 |
| Provide & Install Select Satisfactory fill includes hauling spread and compaction |
| 26 |
| Provide & Install Lime Treated Subgrade including compaction |
| 28 |
| Provide & Install Graded Crush Aggregate Base Course, including loading, hauling, spread |
| 31 |
| Grading (by machine) c/w roller type compaction |
| 36 |
| Provide & Install Plant Mix, including loading, hauling, spread and compaction |
| 42 |
| Provide & Install Type II Asphalt Binder Course |
| 43 |
| Provide & Install Type III Asphalt Surface Course |
| 44 |
| Provide & Install Primer Coat (MC30) |
| 55 |
| Provide & Install Seal Coating |
| 59 |
| Provide & Install Formwork, wood |
| 65 |
| Provide & Install BS 25 Plain Concrete |
| 66 |
| Provide & Install BS 30 Plain Concrete |
| 71 |
| Furnish & Install various size steel (smooth & deformed) reinforcing bars |
| 81 |
| Provide and Install Joint Sealers (Sikaflex 2B, or equiv.), c/w Bond Breaker Rod |
| 120 |
| Provide and Apply one reactive comp.paint (KANAT PAINT , KANTEX 64710) c/w type 1glass beads, by machine |
| 132 |
| Seeding |
| 223 |
| Conduct Compaction Test |
| 230 |
| Provide & Install Temporary Construction Fencing |
c. Technical Factor. The Government’s technical evaluation team shall evaluate the technical proposals on an acceptable or unacceptable basis, assigning one of the ratings described below for each subfactor. Any subfactor evaluated as “Unacceptable” will render the entire proposal unacceptable and, therefore, unawardable. Only those proposals determined to be technically acceptable, either initially or as a result of discussions, will be considered for award. However, the offeror is reminded that the Government reserves the right to award this effort based on the initial proposal, as received, without discussion.
TABLE 1 - TECHNICAL RATINGS
| Rating |
| Description |
| Acceptable |
| Proposal clearly meets the minimum requirements of the solicitation. |
| Unacceptable |
| Proposal does not clearly meet the minimum requirements of the solicitation. |
The proposals shall be evaluated against the following technical subfactors.
i. Subfactor 1 - Quality Control Plan: This subfactor evaluates an offeror’s QCP IAW Section L, Technical Subfactor 1. This subfactor will be met when the offeror’s QCP and approach for the seed projects successfully demonstrates the requirements of the 2012 Specifications for Roads and Grounds ID/IQ Contract Section 01 45 04.00 10 para 3.2.1 (Page. 87, “Content of the QCP”).
ii. Subfactor 2 – Seed Projects: This subfactor is met when the Offeror successfully demonstrates the contractor’s capability to manage all resources required to meet the requirements for all three seed projects IAW Section L. The offeror’s progress schedule for all major construction elements shall be provided on both the AF Form 3064 or equivalent and a Gantt chart with all milestones annotated with actual dates and a line graph.
d. Past Performance Factor: To be considered acceptable, the proposal will be evaluated on recency and relevancy. This rating is based upon information provided by the offeror or information obtained from any other sources that are deemed recent and relevant.
i. Recency Assessment. An evaluation of the past performance information will be made to determine if it is recent. To be recent, the effort must be ongoing (at least 50% complete) or must have been completed within the past three (3) years from the date of issuance of this solicitation. Past performance information that is not recent will not be evaluated.
ii. Relevancy Assessment. The US Government will conduct an evaluation of all recent performance information obtained to determine the degree of relevance in regards to magnitude and complexity.
1. Complexity. Relevancy in regard to complexity will be evaluated based on, but not limited to, similar work relating to performing road construction/repair.
2. Magnitude. Relevancy in regard to magnitude will be evaluated based on contracts/projects with a value of $3M annually or an aggregate of contracts/projects totaling $3M.
The US Government will use the following definitions when evaluating past performance:
| RATING |
| DESCRIPTION |
| Acceptable |
| Based on the offeror's performance record, the US Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror's performance record is unknown. (See note below.) |
| Unacceptable |
| Based on the offeror's performance record, the US Government has no reasonable expectation that the offeror will be able to successfully perform the required effort. |
Note: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a)(2)(iv)). Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability, "unknown" shall be considered "acceptable."
1. Award Process. The Government intends to award to the lowest priced, technically acceptable offeror with an acceptable past performance rating. The Government reserves the right to hold discussions at any point during the evaluation. The evaluation process is as follows:
a. Price: The Government will first evaluate all proposals for price, ranking the offerors from lowest to highest total proposed price. A price fair and reasonable determination will be made on the apparent successful offer prior to award.
b. Technical: The lowest price proposal will then be evaluated for Technical Acceptability. Proposals must be rated “Acceptable” for all technical subfactors in order to be determined technically “Acceptable”. If the lowest priced offeror’s technical proposal is “Unacceptable”, the next low offeror’s technical proposal will be evaluated, continuing until an offeror with an “Acceptable” technical rating is identified.
c. Past Performance: The lowest priced, technically “Acceptable” offeror’s past performance will be evaluated. The Government reserves the right that if the lowest priced, technically “Acceptable” offeror’s past performance is determined to be “Acceptable”, the evaluation process will stop and the award will be made to that offeror.
d. Award of Seed Projects: As past performance and technical has been evaluated, award of the seed project will be based upon the lowest evaluated price.
2. The government will award minimum of two (2) with a target of four (4) IDIQ contracts to offerors whose proposals represent the lowest price, technically acceptable offers with acceptable past performance. Award shall be made to those offeror’s without further consideration of any other offers, unless further evaluation is determined to be in the best interest of the Government.
(End of Summary of Changes)