Attachment 1 - Section L 25 Sep 26.docx
DOCX document 52 KB Posted
- Attached to
- FY 27 A-E IDIQ Solicitation
- Solicitation number
- FA561326R0004
About this file
This is Section L (Instructions, Conditions, and Notices to Offerors) from a solicitation for Architect-Engineer (A-E) Services under solicitation number FA561326R0004. The Department of the Air Force, 86th Airlift Wing (USAFE) is soliciting qualifications for a Multiple Award Indefinite Delivery Indefinite Quantity (IDIQ) contract with an anticipated awardee pool of eight (8) firms. The contract will support the 86th Civil Engineering Group at Ramstein Air Base and 52 CES at Spangdahlem Air Base, with a ten-year ordering period. A-E firms must be located in Germany or have a branch office in Germany. Offerors must include a German sales tax identification number (USt-ID-Nr.) with their submission.
Submissions must follow strict formatting requirements using the SF330 Architect-Engineer Qualifications form with searchable PDF files in Adobe Acrobat Reader format (version 1.7 or earlier), 12-point Arial font, single-spaced, with one-inch margins. Offerors must submit five interdisciplinary example projects completed within the past three years demonstrating Title I and/or Other A-E Services across multiple disciplines, with detailed project information including scope, objectives, cost, design period, and key personnel. All proposals, including Past Performance Questionnaires, must be submitted via the Procurement Integrated Enterprise Environment (PIEE) no later than 16:00 Central European Time (CET) on 09 October 2026. Questions must be submitted by 14:00 CET on 18 September 2026, with consolidated answers published as an amendment on 25 September 2026. The Procurement Contracting Officer is Sibel Wright (314-489-7999, sibel.wright@us.af.mil).
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
86TH AIRLIFT WING (USAFE)
FA561326R0004
--- SECTION L ---
--- INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS ---
ATTENTION: THE INSTRUCTIONS PROVIDED IN THIS DOCUMENT ARE IN ADDITION TO THOSE PROVIDED ON THE SF330, ARCHITECT-ENGINEER QUALIFICATIONS.
ATTENTION: ARCHITECT AND ENGINEERING (A-E) FIRM SHALL BE LOCATED IN GERMANY OR HAVE A BRANCH IN GERMANY
FORMATTING REQUIREMENTS FOR SF330
1. Use of the SF330 template is required. If all required fields, including their numbering, are retained, the layout may be adjusted. (Attachment 5).
2. Offerors can download the required SF330 Architect-Engineer Qualifications form directly from the GSA Forms Library or each of the isolated sections of the SF330. Offerors may utilize these sections to customize their SF330 submission, provided that all required information is included. Please use the following link to access the form: https://www.gsa.gov/forms-library/architect-engineer-qualifications
FORMATTING AND PAGE LAYOUT REQUIREMENTS FOR ALTERNATIVE DOCUMENTATION
1. Pages: For electronic documents not utilizing a SF330 sheet, a page is defined as one side of an 8.5" x 11" sheet (or closest metric equivalent) with at least 1-inch margins on all sides. Files must be saved in searchable PDF format compatible with Adobe Acrobat Reader (PDF version 1.7 or earlier). Documents will not include passwords.
2. Typography: Text must be single-spaced, using non-compressed 12-point Arial font. Tables, captions, and graphics must also be formatted in font no smaller than 12-point.
3. Alternative documentation (AD) is permitted only when specifically authorized below or elsewhere in this solicitation.
PAGE LIMITATIONS AND CONTENT REQUIREMENTS
1. The table below establishes the strict page limitations for each section. Any pages or projects submitted in excess of these limitations will be discarded without evaluation.
| Section |
| Reference |
| Information / Instructions |
| Page Limit |
| SF330 |
| Cover Letter, Table of Contents and Acronyms |
| On submitted PDF, include in this order: |
• Cover Letter (list the solicitation number/title, firm's name, complete address (with postal code), Unique Entity Identifier (UEI), CAGE code, and the name, phone, and e-mail of your POC (provide this same information for subcontractors)).
• Table of Contents (with hyperlinks)
• Optional: If acronyms beyond those identified in the documents are used, a one-page Acronym List may be included.
No Page Limit (NPL)
| I |
| SF330 Part I, Sections A–C |
| Contract-Specific Qualifications |
| NPL |
| II |
| SF330 Part I, Section D |
| Organizational Chart of Proposed Team |
• Provide a graphical org chart depicting the relationship of the Firm to each subcontractor and the proposed type and percentage of work to be subcontracted to each 2 pages (AD Permitted)
| III |
| SF330 Part I, Section E |
| Resumes of Key Personnel and other professionals that worked on the example projects including attachments of education, training, licensing, credentials, etc. |
| 2 pages per person (50-page limit) and attachments with NPL and no formatting restrictions |
| IV |
| SF330 Part I, Section F |
| Example Projects |
• Submit five (5) interdisciplinary projects completed within the past three (3) years that demonstrate the firm’s experience, technical competence, and ability to perform the required Title I and/or Other A–E Services across multiple relevant disciplines.
• Minimum project information required must be documented in accordance with (IAW) Page Limitation and Content Requirements, Section 2.
Maximum 5 pages per project (25-page limit)
| V |
| SF330 Part I, Section G |
| Key Personnel Participation |
| 2 pages |
| VI |
| SF330 Part I, Section H |
| Any Additional Documents |
• ATTENTION: Must include German sales tax identification number (USt-ID-Nr.)
5 pages (AD Permitted)
| VII |
| SF330 Part II |
| General Qualifications |
• Provide 1 SF330 Part II page for the A-E Firm’s local office and 1 additional SF330 Part II page for each branch office and subcontractor.
• ATTENTION: Firms with $0.00 in revenue from Federal Work over the last 3 years must enter “0” for the index number in Block 11 instead of “1”.
NPL
| SF33 and Solicitation Package |
| • The first page of this solicitation (Standard Form 33) must be fully completed and signed by an authorized representative of the Offeror. Specifically, Blocks 15 through 18 must be filled in. The Offeror’s legal business name and address in Block 15 must exactly match the entity's active registration profile in SAM.gov. |
• Offerors must not submit pricing, rates, or complete any pricing-related fields, including Section B of the SF33, with their qualification package. The Government will request pricing from firms selected to proceed to the next phase of the acquisition.
• Additionally, the Offeror must complete and return all solicitation clauses and provisions that require fill-in information.
NPL
| Past Performance Questionnaire |
| All Past Performance Questionnaires (PPQs) have been submitted to Clients |
• Utilized only for projects submitted under Section F of the SF330 that do not reside within the CPARS database N/A
| Past Performance Questionnaire |
| Confirmed that all PPQs have been completed and sent directly to Point of Contacts (POC). |
• Utilized only for projects submitted under Section F of the SF330 that do not reside within the CPARS database N/A
2. Minimum Project Information REQUIRED (SF330, Part I, Section F, Block 24):
a. Number and title of example project (match to SF330, Part I, Section G, Block 29)
b. Location (State/Country)
c. Customer/Client
d. Identify if your firm was a prime contractor or subcontractor and include the percentage of work performed.
e. Period of Performance (PoP) (Project start date, planned project end date, actual end date)
f. Type of project
i. Study, charette, 100% design, etc.
g. Main project objectives (use bullet points)
i. i.e. New dormitory, landscaping, restore airfield etc.
h. Estimated construction costs
i. Design period (Start date, period of performance and completion date)
j. A-E’s services (use bullet points)
i. Architecture, Civil, HVAC etc.
k. A-E’s secondary services (use bullet points)
i. Fire safety assessment, survey, etc.
l. A-E’s Title II Quality Assurance (Construction Inspection, SIOH)
m. Key figures (use bullet points)
i. i.e. Building footprint/area, capacity, etc.
n. Brief project description
QUESTIONS AND ANSWERS
Offerors shall submit all questions regarding this solicitation in writing to the procurement team referenced in the Points of Contact (POC) section of this document. All questions must be received no later than 14:00 Central European Time (CET) on 18 September 2026. Answers to all questions received will be consolidated and published as an amendment to the solicitation on 25 September 2026.
PROPOSAL PACKAGE SUBMISSION
1. Quantities and Formats:
a. Submission Deadline:
i. All packages (including PPQs) must be received no later than 16:00 (CET) on 09 October 2026. Late submissions will be processed in accordance with RFO 15.107(b).
b. Submission Instructions:
i. Digital delivery of proposals is required following the procedures below:
1. Proposal information shall be transmitted to the Procurement Contracting Officer (PCO) via the Solicitation Module within the Procurement Integrated Enterprise Environment (PIEE) found at https://piee.eb.mil/.
2. The direct link for submissions is: https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?noticeId=FA561326R0004¬iceType=SolicitationNotice
3. Offerors must obtain the "Proposal Manager" role in PIEE for the Solicitation Module. The following website may be used to help obtain this role: https://piee.eb.mil/xhtml/unauth/web/homepage/vendorCustomerSupport.xhtml Click the "Go To Web Based Training" link. Then click the "Solicitation Module". Review the various training resources. Offerors may also obtain assistance via the PIEE help desk, phone +1 866-618-5988
4. If the offeror is unable to submit its proposal via the PIEE Solicitation Module, the offeror is responsible for coordinating with the PCO no later than 12:00 (CET) on 06 October 2026 in order to determine an alternate means of submitting the completed proposal.
5. Proposals may be withdrawn by written notice received at any time before award.
6. No physical copies will be accepted.
POINTS OF CONTACT
PCO: Sibel Wright, 314-489-7999, sibel.wright@us.af.mil Contract Specialists: Fatima Berlitz, 314-489-7616, fatima.berlitz.de@us.af.mil; TSgt Jonathan Brekken, 314-489-8470, jonathan.brekken@us.af.mil image1.png
File details come from the government source that posted it. Updated .