RFP Attachment 4b Instruction for 35 Design
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP.: FA5270-14-R-0019
Attachment #4
INSTRUCTION FOR PRELIMINARY 35% DESIGN SUBMITTAL
The review of this submittal is primarily to ensure that the contract documents and design analysis are proceeding in a timely manner and that the design criteria are being correctly interpreted. All design analyses, drawings, and specifications should address and show compliance with Unified Facilities Criteria and all other applicable codes and regulations.
3.3.1 The submittal shall consist of the following:
Design analysis, developed to 35%
Drawings – schematic (35%) design
Specifications (i.e.: a guidance of specifications that will be developed for the 35% submittal)
3.3.2 Submittal Requirements:
The 35 % Submittal shall contain as a minimum, the following design discipline requirements:
3.3.2.1 Architectural Requirements
3.3.2.1.1 Design Analysis:
Schematic Project Scope
Schematic Code Analysis including life safety and the Americans with Disabilities Act (ADA) Accessibility
Schematic Design narrative of functional space relationships, as well as circulation
Schematic Anti-terrorism / Force Protection Requirements
3.3.2.1.2 Drawings and Design Information:
Draft Floor plans, new and demolition
Draft Enlarged floor plans as necessary
Draft Roof plan
Draft Exterior elevations
Draft Building Section
Draft Anti-terrorism / Force Protection Requirements
3.3.2.2 Structural Requirements:
3.3.2.2.1 Design Analysis:
Schematic Project Scope
Schematic Foundation report and recommendations
Schematic Code Analysis including Seismic and Wind Load requirements
Life Safety Code 101
3.3.2.1.2 Drawings and Design Information:
1268782474U Typewritten Text
1268782474U Typewritten Text
1268782474U Typewritten Text b
Draft Foundation plans
Draft Framing plan
Provide loading information and identify source for all listed loads
3.3.2.3 Civil Requirements:
3.3.2.3.1 Design Analysis:
Schematic Description of Site Conditions
Schematic Technical references (codes, manuals, directives)
Schematic Drainage Storm water routing
Schematic boring logs (laboratory data shall be summarized in tables)
Schematic Analysis of the existing systems and new work requirements
Schematic Traffic volume and type
Schematic ATFP Standoff Distances
3.3.2.3.2 Drawings and Design Information:
Draft Location and Vicinity Map
Draft Site Plan with typical section cuts and pavement cuts
Draft Show new and existing storm drain lines and inlets
Draft Utility Plan showing all utilities and associated products, (cleanouts, manholes, fire hydrants, etc.) Show all new work in association with the topographic survey as required.
Draft Soils boring logs & Subsurface investigation site plan
Draft ATFP Standoff Distances
3.3.2.4 Mechanical Requirements:
3.3.2.4.1 Design Analysis:
Schematic plumbing design analysis: system narratives with thorough discussion of domestic water, rainwater, sewer and vent piping systems
Schematic Air Conditioning and heating design analysis: system narratives
Schematic Ventilation design analysis: system narratives with thorough discussion of the building mechanical room ventilation, and miscellaneous building exhaust systems
Schematic gas piping, container gas piping and tanks
Schematic Anti-terrorism / Force Protection Requirements
Calculations and information to include the following:
o Heating/Cooling load calculation o Duct sizing o Pipe sizing o Hydraulic calculation o Storm demand calculation o HVAC load calculation
3.3.2.4.2 Drawings and Design Information:
Draft Mechanical equipment and fixture schedules
Draft Plumbing layout plans
Draft Heating, Ventilation, and Air Conditioning (HVAC) layout plans and system diagrams
Draft Plumbing diagrams
Draft Utility layout plans
Draft Anti-terrorism / Force Protection Requirements
3.3.2.5 Electrical Requirements:
3.3.2.5.1 Design Analysis
Schematic scope of new work to be performed o Lighting illumination calculation o Load calculation o Short circuit calculation o Voltage drop calculation
Schematic Communication system to include the following:
o Describe the existing system and the changes to be made to the existing system to accommodate the project.
o Scope of new work to be performed o Description of system components such as the type of cables, outlets and patch panel o Describe Special Systems: LAN System, Public Address System, Program Clock system, Base Fire Reporting System (transponder, antenna), etc.
Schematic Anti-terrorism / Force Protection Requirements
3.3.2.5.2 Drawings and Design Information:
Draft Exterior lighting plan
Draft Electrical one-line diagram / Details
Draft Site Plan: feeders, transformers, telecommunications and cable service entrances
Draft Receptacle and lighting plan
Draft Special Systems: communications and cable
Draft Communication system to include the followings:
o One-line diagram / Details o One-line diagram for other special systems such as: Public Address System, Program Clock system, Base Fire Reporting System (transponder, antenna), etc.
Draft Anti-terrorism / Force Protection Requirements
3.3.2.6 Fire Protection Requirements:
3.3.2.6.1 Design Analysis:
Building code analysis (i.e., type of construction, height and area limitations, and building separation or exposure protection)
Classification of occupancy
Compliance with UFC 3-600-01 and National Fire Codes
NFPA 101, Life Safety Code
Prepare a comprehensive fire protection design analysis
Provide description of overall fire protection systems
Schematic Communication system to include Base Fire reporting system (transponder, antenna), etc.
Interior finish ratings
Fire Department access
3.3.2.6.2 Drawings and Design Information:
Draft Sprinkler systems and suppression systems plan
Draft Site Plan: water supplies and location of fire hydrant
Draft Water supply line sizing, location of fire hydrant, equipment and riser layout
Draft Respective design density and floor area coverage
Draft Communication system to include the one-line diagram for program Clock system Base Fire Reporting system (transponder, antenna), etc.
Draft Fire Protection System Plan to include Fire Alarm Plan one-line diagram