Pax Terminal RFIs - 2024.04.12.pdf

PDF 284 KB Posted

Attached to
Renovate Passenger Terminal B17002 and Provide New Temporary Facility for Passenger Terminal, Andersen Air Force Base, Guam
Solicitation number
FA524024R0005
Issued by

About this file

This document is a collection of Questions and Answers related to a Request for Proposals (RFP) for the renovation of Passenger Terminal B17002 and provision of a new temporary passenger terminal facility at Andersen Air Force Base in Guam.

The key details include: the renovation project has a total period of performance of 720 calendar days, with an additional 420 days for the temporary facility. The government is procuring the work as a Small Business set-aside, with a NAICS code of 236220 Commercial and Institutional Building Construction. Bidders were able to attend site visits on March 20 and 29, 2024, with no additional visits planned. Proposals are due by April 30, 2024, with no extensions anticipated. The government does not intend to provide any financial support for the project. Specific details are provided regarding the mechanical and electrical systems, demolition requirements, and expectations for temporary utilities and facilities during construction.

View the file

Other files

File Type Posted
Pax Terminal RFIs - 2024.04.16.pdf PDF
Attachment 8 - Air Force Meter Data Management Plan.pdf PDF
Solicitation Amendment - FA524024R00050007.pdf PDF
Solicitation Amendment FA524024R00050007 SF 30.pdf PDF
Pax Terminal RFIs - 2024.04.11.pdf PDF
Solicitation Amendment FA524024R00050006 SF 30.pdf PDF
Solicitation Amendment - FA524024R00050006.pdf PDF
Attachment 1 - PART G - B-17002 AC Ducts.pdf PDF
Solicitation Amendment FA524024R00050005 SF 30.pdf PDF
Attachment 1 - PART F - B-17002 Site Pictures.pdf PDF
Attachment 1 - PART E - Overall Floor Plan B-17002 Showing Boundaries of Other Units.pdf PDF
Pax Terminal RFIs - 2024.04.05.pdf PDF
Solicitation Amendment - FA524024R00050005.pdf PDF
Solicitation Amendment FA524024R00050004 SF 30.pdf PDF
Solicitation Amendment - FA524024R00050004.pdf PDF
Attachment 1 - PART A - Statement of Work_Amended 01APRIL24.pdf PDF
Pax Terminal RFIs - 2024.03.26.pdf PDF
Attachment 4 - Site Visit Instructions dated 25 Mar 2024.pdf PDF
Pax Terminal RFIs - 2024.03.25.pdf PDF
Solicitation Amendment FA524024R00050003.pdf PDF
Attachment 4 - Site Visit Instructions dated 25 Mar 2024.pdf PDF
Solicitation Amendment FA524024R00050003 SF 30.pdf PDF
Solicitation Amendment - FA524024R00050002.pdf PDF
Attachment 1 - PART A - Statement of Work_Amended 22MAR24.pdf PDF
Solicitation Amendment FA524024R00050001.pdf PDF
Attachment 1 - PART D - CAD Drawings for Renovation of B17002.zip ZIP file
Attachment 6 - Past Performance Fact Sheet.docx DOCX document
Attachment 3 - CCPWR-2021-Govs-notice.pdf PDF
Solicitation - FA524024R0005_13MAR.pdf PDF
Attachment 1 - PART A - Statement of Work.pdf PDF
Attachment 4 - Site Visit Instructions.pdf PDF
Attachment 1 - PART B - Base Bid Technical Specifications for Renovation of B17002.pdf PDF
Attachment 2 - ACBDS.pdf PDF
Attachment 5 - PIEE Proposal Manager Guide.pdf PDF
Attachment 7 - Past Performance Questionnaire (PPQ).docx DOCX document
Attachment 1 - PART C - Base Bid Final Design Submittal for Renovation of B17002.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question # Reference Question Government Response

1 SF1442

We would like to request that the bid submission date be extended to April 29, 2024. We need the additional time to secure pricing from our subcontractor and suppliers.

Proposal due date has been extended to 30 April 2024. See Amendment

FA524024R00050003.

2 Site Visit Thanks for clarifying that the site visit is on Friday, March 29. In observance of Good Friday, may we request to have this moved to Thursday, 28Mar24 or Monday, 01Apr24?

The site visit will remain as scheduled on Friday, 29 March 2024 @ 1000 HRS ChST, as the observance of Good Friday is not a Federal Holiday.

3 Site Visit Can you share any pictures or documents covering the current site conditions and other terminals if any for us to better understand the quality / standards of construction interior and exterior finishes.

Available pictures are attached in the solicitation amendment 0005 (Attachment 1 - PART F - B-17002 Site Pictures). KTRs were already allowed to take as many pictures as they wanted from inside and outside of the facility during two site visits. KTR should be responsible for researching potential design quality / standards beyond the already provided design drawings

Approval Plan and Permit Approval Process Transparency - As architectural review process and building permit approval process and eta vary from location to location, please what is the current permitting process and current eta (i.e.) are there other concurrent projects that can impact the permit issuance timelines.

Government cannot guarantee that any repair/renovation works may or may not happen at the CES Fire Station or OSS areas in the building. However, PAX Terminal project area as marked in the design will be free from any other contract works and that location will be handed over to the PAX Terminal contractor. Any construction work on the flightline side will require TACW approval that can take about 3 to 4 months. Use of cranes and other high rise equipment will require TERP approval also. Both permits can be obtained by working with 36 CES Planning section.

American Made Expectations - The current structure shown in one of attached Air Force Base’s Architectural Compatibility and Base Design Standards consists of products that may no longer be used in mainland USA like windows and shutters. Are the expectations to build the pictures shown as standards document?

For example I do not see the window/door schedule, etc

We have Andersen Base Standards and the design was made to comply with

it. Follow the design requirements shown in the design. Base standard used for the design (ACBDS) was provided by 36 CONS during solicitation.

AJJY 19-6004 Renovate Passenger Terminal B17002 And Provide Temporary Facility For Passenger Terminal Questions & Answers (Q&A)

Construction Costs - Thank you for sharing the trade costs via the Governor's letter. As the cost for construction entails more than the trade costs and Guam's GDP is primarily driven by the US Govt spending, would you be able to share any recently completed govt construction and demolition cost / sq ft studies or research ?

Additional information is not available. Offerors are responsible for providing their most accurate pricing based on currently available information.

Financing - As this is catered to small business and is relatively a bigger spend when compared to a traditional small business financial capability is there any govt support to material, and other costs vs. contractor have to pay and govt pays after the contractor gets to the site?

The Government does not anticipate providing financial support under this requirement.

Are we allowed to speak with the Architect (John Setadi) or Engineer of record to expedite the bid submission process?

It is not Government's call and no comments.

Attachment 1 - Part C - Base Bid

Final Design

Submittal

Attachment 1 – Part C - Base Bid Final Design Submittal for Renovation of B17002 – Sheet M-601. The equipment schedule for the Horizontal Split Dehumidification Indoor Unit (chilled water), electrical characteristics, 40 HP.

Kindly confirm if this capacity is the total for both DOAS and AHU (20 HP each) or is it 40 HP for DOAS and 40 HP for AHU.

40 HPs each for DOAS and AHU

Attachment 1 - Part C - Base Bid

Final Design

Submittal

Attachment 1 – Part C - Base Bid Final Design Submittal for Renovation of B17002 – Sheet M-601. The equipment schedule for the Horizontal Split Dehumidification Indoor Unit (chilled water), Remarks. The remarks call for variable air volume units with heat pipe (passive reheat coil), the equipment supplier is asking for the required specification for the heat pipe (passive reheat coil) to provide us with a proper proposal for the equipment.

No special specification is available for the passive reheat coil. All the coils for DOAS and AHU shall be copper/copper.

Attachment 1 – Part C - Base Bid

Final Design

Submittal

Attachment 1 – Part C - Base Bid Final Design Submittal for Renovation of B17002 – Sheet MD-101 – Demolition notes #5. Contractor shall conduct pre-tab to verify the existing SA & RA airflow in non-AMS areas.

-Can you provide the limits or location for the AMS and non-AMS area. Please provide the non-AMS ducts to be pre-tab prior to demolition.

Complete floor plan of B-17002 showing the boundaries of Fire Dept. and OSS/FSS areas is attached in the solicitation amendment 0005 (Attachment 1 - PART E - Overall Floor Plan B-17002 Showing Boundaries of Other Units).

Attachment 1 – Part C - Base Bid

Final Design

Submittal

Attachment 1 – Part C - Base Bid Final Design Submittal for Renovation of B17002 – Sheet MD-101 – Demolition notes #8. Provide temporary air conditioning units in areas affected by works.

-Can the government verify the location where temporary AC is needed? What type of temporary cooling does the Government need, i.e, split AC, package cooling unit, portable AC, etc. What is the capacity needed for the temporary AC.

The locations of other Commands in B-17002 are shown in the complete floor plan of B-17002. Both Fire department and OSS/FSS areas require AC, power and other utilities always as they work 24/7. Contractor can provide options to keep up AC, power and other utilities during all outages for the areas mentioned. Some renovation works on the OSS/FSS area are included in the SOW, refer to designed floor plan.

Solicitation Amendment

FA524024R

00050003

Solicitation Amendment FA524024R00050003 – Section B – Supplies or Services & Prices or Cost – Item 0002, page 4 of 63 states “Provide temporary facility for PAX Terminal operations… and removal/demolition of temporary facilities upon completion of renovation of B17002.

-Kindly advise if the removed/demolished temporary facilities need to be turned over to the Government. If to be turned over to the Government, kindly advise where to deliver the removed temporary facilities. Do we also need to turn over the baggage conveyor?

The cost for demo of temporary facilities including baggage roller conveyors shall be included in the cost proposal. The baggage roller conveyors shall be returned to the customer.

Attachment 1 – Part C - Base Bid

Final Design

Submittal

Attachment 1 – Part C - Base Bid Final Design Submittal for Renovation of B17002 – Sheet ID 104 – Legend: States that, “Separate funding contractor furnished/contractor installed by planned modification of contract.”

- Is the FF&E for both Base bid and temporary facility to be ordered under GSA contract? If so, kindly advise what will be the budget for the FF&E for the contractor to provide pricing for the Handling and Administration Rate (HAR).

Furniture plan is for coordination purpose only. The current SOW does not include any cost for FF&E.

Attachment 1 – Part A – Statement of Work_Ame nded 22Mar24

Attachment 1 – Part A – Statement of Work_Amended 22Mar24 – Page 4 of 44 – Amendment 1: Exclude all cost and labor for purchasing, shipping, and installing the BHE. However, all utility connections for the BHE as shown in design shall be included in base bid.

- Kindly confirm if this also includes the BHE cost for the temporary facility.

Amendment 1 is to remove all the cost for the BHE for B-17002 only. The temporary facility requires baggage conveyor systems as mentioned in the SOW and all the cost and labor for this shall be included in the proposal.

We would like to request for the overall ducting layout for the whole building to include the Fire Department and OSS/FSS. This will determine the overall duct length of the Pre-Tab before the demolition for our TAB subcontractor to provide a proper proposal. Thiswill also help to determine what kind of temporary cooling the contractor will provide during the demolition.

Available map of AC duct work is attached in the solicitation amendment 0006. KTR shall verify the site for accuracy.

Question

#13

Follow up question to item number 13 of attachment Pax+Terminal+RFIs+- +2024.04.05.

How about the demolished temporary facilities and materials inside the temporary facilities, i.e., AC, plumbing fixtures, windows, doors, fire alarm devices, etc. Do these materials need to be turned over to the Government too or is to be disposed of by the contractor.

Any equipment/material provided by KTR would be included as part of demo/disposal. Any equipment/material that is Gov't furnished will return to the Gov't.

RFP Due

Date

Would the government please extend the bid deadline by a minimum of 14 calendar days to allot more time for contractors to obtain the most competitive pricing and incorporate into the bid?

The proposal submission date remains 30 April 2024.

19 SF1442 Does this project require a mandatory site visit prior to submi «ng a bid proposal?

Site visits were scheduled on conducted on 20 March 2024 and 29 March 2024. The government does not intend to hold any additional site visits.

Attendance at a site visit is not a requirement for bid submission.

20 SF1442

Do you anticipate any time extensions for submitting bid proposals (which I understand closes on April 30)?

The proposal submission date remains 30 April 2024.

Please provide hardware sets (08 71 00 - Door Hardware) for the following doors:

PT-125E Baggage Build-up B08A Mission Planning B08B Mission Planning

Provide hardware for PT-125E to match PT-125A per Spec. 08 71 00.

Provide full mortise hinge, cipher locks, door closure and gasketing for Mission planning B08A & B08B. The hardware schedule is included in Solicitation Attachment 1 - PART B - Base Bid Technical Specifications for Renovation of B17002.

Detail D3/S-

Detail D3/S-502: How do we compute the length of T2 rebar? What does the abbreviation “OR” mean? Confirm T1 length is L1 / 3.

Details are clearly shown in D3/S-502. T2 is 2*L1/3. T1 is full length top bar as shown in the same drawing.

CAD

Drawings Can we get the X-Refs of the A-Cad drawings? We did not find any X-Ref files. X-Ref files are not required for pre-bid cost estimating and is not provided.

Detail A3/S-

Detail A3/S-504, the wall on the right side of the double door, Can we get the full dimensions of wall along Grid FF, between Grid 13A and 14B?

The dimensions can be obtained from the CAD drawings of overall floor plan.

Room PL 105 Lactation room, what detail in drawing page A704, A705, applies for the cabinet in this room? Is this a base cabinet or just a countertop?

Base cabinet with countertop. As per A-101A, C1/A404;

this counter/cabinet would be similar as A5 & C5 on A704 as requires the sink and an undermount min fridge

*** NO FURTHER ENTRIES ***