Attachment 1 - PART B - Base Bid Technical Specifications for Renovation of B17002.pdf

PDF 5 MB Posted

Attached to
Renovate Passenger Terminal B17002 and Provide New Temporary Facility for Passenger Terminal, Andersen Air Force Base, Guam
Solicitation number
FA524024R0005
Issued by

About this file

This solicitation is for the renovation of Passenger Terminal B17002 and provision of a new temporary passenger terminal at Andersen Air Force Base in Guam. The scope of work includes demolition and construction services to renovate the existing terminal building, as well as providing a new temporary facility. The period of performance for the renovation is 720 calendar days, and 420 days for the temporary facility. The contract type is firm-fixed price. The acquisition is set aside for small businesses with a NAICS code of 236220 and size standard of $45 million. Proposals are due through PIEE by the specified date. The pre-proposal site visit will take place on March 20, 2024, and any requests for information are due by March 28, 2024.

View the file

Other files

File Type Posted
Pax Terminal RFIs - 2024.04.16.pdf PDF
Attachment 8 - Air Force Meter Data Management Plan.pdf PDF
Solicitation Amendment - FA524024R00050007.pdf PDF
Solicitation Amendment FA524024R00050007 SF 30.pdf PDF
Pax Terminal RFIs - 2024.04.12.pdf PDF
Pax Terminal RFIs - 2024.04.11.pdf PDF
Solicitation Amendment FA524024R00050006 SF 30.pdf PDF
Solicitation Amendment - FA524024R00050006.pdf PDF
Attachment 1 - PART G - B-17002 AC Ducts.pdf PDF
Solicitation Amendment FA524024R00050005 SF 30.pdf PDF
Attachment 1 - PART F - B-17002 Site Pictures.pdf PDF
Attachment 1 - PART E - Overall Floor Plan B-17002 Showing Boundaries of Other Units.pdf PDF
Pax Terminal RFIs - 2024.04.05.pdf PDF
Solicitation Amendment - FA524024R00050005.pdf PDF
Solicitation Amendment FA524024R00050004 SF 30.pdf PDF
Solicitation Amendment - FA524024R00050004.pdf PDF
Attachment 1 - PART A - Statement of Work_Amended 01APRIL24.pdf PDF
Pax Terminal RFIs - 2024.03.26.pdf PDF
Attachment 4 - Site Visit Instructions dated 25 Mar 2024.pdf PDF
Pax Terminal RFIs - 2024.03.25.pdf PDF
Solicitation Amendment FA524024R00050003.pdf PDF
Attachment 4 - Site Visit Instructions dated 25 Mar 2024.pdf PDF
Solicitation Amendment FA524024R00050003 SF 30.pdf PDF
Solicitation Amendment - FA524024R00050002.pdf PDF
Attachment 1 - PART A - Statement of Work_Amended 22MAR24.pdf PDF
Solicitation Amendment FA524024R00050001.pdf PDF
Attachment 1 - PART D - CAD Drawings for Renovation of B17002.zip ZIP file
Attachment 6 - Past Performance Fact Sheet.docx DOCX document
Attachment 3 - CCPWR-2021-Govs-notice.pdf PDF
Solicitation - FA524024R0005_13MAR.pdf PDF
Attachment 1 - PART A - Statement of Work.pdf PDF
Attachment 4 - Site Visit Instructions.pdf PDF
Attachment 2 - ACBDS.pdf PDF
Attachment 5 - PIEE Proposal Manager Guide.pdf PDF
Attachment 7 - Past Performance Questionnaire (PPQ).docx DOCX document
Attachment 1 - PART C - Base Bid Final Design Submittal for Renovation of B17002.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AJJY 19‐6004

Renovate PAX Terminal B17002

Andersen Air Force Base, Guam

Project No. AJJY 19‐6004

Specifications Final Design Submittal

12 May 2023

THIS PAGE INTENTIONALLY LEFT BLANK

Renovate PAX Terminal B17002 Project No. AJJY 19-6004 Andersen Air Force Base, Guam Final Submittal

PROJECT TABLE OF CONTENTS

DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS

00 01 15 LIST OF DRAWINGS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 20 00 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 20 QUALITY CONTROL

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19.01 30 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS (JRM ESS)

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 00.15 10 TOTAL BUILDING COMMISSIONING

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 DEMOLITION

DI VI SI ON 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DI VI SI ON 04 - MASONRY

04 20 00 UNIT MASONRY

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 61 16 SOLID SURFACING FABRICATIONS

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 21 16 MINERAL FIBER BLANKET INSULATION

07 41 13 METAL ROOF PANELS

07 56 00 FLUID-APPLIED ROOFING SYSTEM

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DI VI SI ON 08 - OPENI NGS

08 11 13 STEEL DOORS AND FRAMES

08 11 16 ALUMINUM DOORS AND FRAMES

PROJECT TABLE OF CONTENTS Page 1 dtd - 12 MAY 2023

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 33 23 OVERHEAD COILING DOORS

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

DI VI SI ON 09 - FI NI SHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 24 23 CEMENT PLASTER

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 67 23.14 RESINOUS SEAMLESS FLOORING SYSTEM

09 84 20 ACOUSTICAL WALL PANELS

09 90 00 PAINTS AND COATINGS

09 96 00 HIGH-PERFORMANCE COATINGS

DI VI SI ON 10 - SPECI ALTI ES

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 26 00 WALL PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

10 51 13 METAL LOCKERS

10 71 13.13 STORM SHUTTERS

DI VI SI ON 12 - FURNI SHI NGS

12 32 00 MANUFACTURED WOOD CASEWORK

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 13 13.00 20 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DI VI SI ON 22 - PLUMBI NG

22 00 00 PLUMBING, GENERAL PURPOSE

22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL

22 07 19.00 40 PLUMBING PIPING INSULATION

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 COMMON PIPING FOR HVAC

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 48.19 SEISMIC BRACING FOR HVAC

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL

PROJECT TABLE OF CONTENTS Page 2

23 23 00 REFRIGERANT PIPING

23 30 00 HVAC AIR DISTRIBUTION

23 31 13.00 40 METAL DUCTS

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLES

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS

23 82 19.00 40 FAN COIL UNITS

DI VI SI ON 26 - ELECTRI CAL

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 05 13.43 TELEVISION DISTRIBUTION SYSTEM

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

31 23 00.00 20 EXCAVATION AND FILL

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 11 20 BASE COURSE

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

DI VI SI ON 33 - UTI LI TI ES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERS

DI VI SI ON 34 - TRANSPORTATI ON

34 77 39 BAGGAGE HANDLING SYSTEMS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 3

THIS PAGE INTENTIONALLY LEFT BLANK

PROJECT TABLE OF CONTENTS Page 4

DOCUMENT 00 01 15

LIST OF DRAWINGS

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

SHEET

NO.

DRAWING

NO.

DESCRIPTION

01 GENERAL

1 G- 001 TITLE/COVER SHEET AND GENERAL NOTES

2 G- 002 REFERENCE SYMBOLS, ABBREVIATIONS & MATERIAL SYMBOLS

3 G- 003 INDEX OF DRAWINGS

4 G- 004 BUILDING CODE AND LIFE SAFETY ANALYSIS

5 G- 005 OCCUPANCY CLASSIFICATION / LOAD TABLE

6 G- 006 BUILDING CODE SITE PLAN

7 G- 007 LIFE SAFETY PLAN

02 TOPOGRAPHI C SURVEY

8 V- 101 TOPOGRAPHIC SURVEY

03 CI VI L

9 C- 001 GENERAL NOTES

10 CD 101 SITE DEMOLITION / REMOVAL PLAN

11 CS 101 CIVIL SITE PLAN

12 CU 101 SITE UTILITY PLAN

13 CG 101 GRADING AND DRAINAGE PLAN

14 CG 102 ENLARGED CROSSWALK PLAN & SECTION PROFILE/ SECTIONS

15 CG 103 PROFILE / SECTIONS

16 CG 104 CROSS SECTIONS

17 C- 501 MISCELLANEOUS DETAILS

18 C- 502 MISCELLANEOUS DETAILS

19 C- 503 WATERLINE MISCELLANEOUS DETAILS

20 C- 504 MISCELLANEOUS DETAILS

21 C- 505 MISCELLANEOUS DETAILS

04 ARCHI TECTURAL

22 AS 101 SITE PLAN

23 AD 101 EXISTING / DEMOLITION FLOOR PLAN

DOCUMENT 00 01 15 Page 1

24 AD 102 EXISTING / DEMOLITION CEILING PLAN

25 AD 103 EXISTING / DEMOLITION ROOF PLAN

26 A- 101 OVERALL FLOOR PLAN

27 A- 101A ENLARGED FLOOR PLAN

28 A- 101B ENLARGED FLOOR PLAN

29 A- 102 FLOOR FINISH PLAN

30 A- 103 REFLECTED CEILING PLAN

31 A- 104 ROOF PLAN

32 A- 105 ROOF PLAN

33 A- 201 BUILDING ELEVATIONS

34 A- 301 BUILDING SECTIONS

35 A- 302 BUILDING SECTION

36 A- 401 CENTRAL LOBBY TOILETS - ENLARGED PLAN & INTERIOR ELEVATIONS

37 A- 402 GATE 1 & 3 TOILETS - ENLARGED PLAN & INTERIOR ELEVATIONS

38 A- 403 AMS & OSS TOILETS - ENLARGED PLAN & INTERIOR ELEVATIONS

39 A- 404 ENLARGED PLAN & INTERIOR ELEVATIONS

40 A- 405 PAX SERVICE & CHECK-IN COUNTER - ENLARGED PLAN & INTERIOR

ELEVATIONS

41 A- 406 DECORATIVE WALL - ENLARGED PLAN, ELEVATION & DETAILS

42 A- 407 ENLARGED CONVEYOR PLANS (INBOUND & OUTBOUND AREAS)

43 A- 408 EXTERIOR STAIR - ENLARGED PLAN, ELEVATION, SECTION & DETAILS

44 A- 501 WALL TYPES

45 A- 502 WALL SECTIONS

46 A- 503 WALL SECTIONS

47 A- 601 ROOM FINISH SCHEDULE

48 A- 602 DOOR & WINDOW SCHEDULE

49 A- 603 DOOR & WINDOW TYPES

50 A- 604 MOUNTING HEIGHT SCHEDULE

51 A- 605 SIGNAGE SCHEDULE

52 A- 606 SIGNAGE TYPES & MOUNTING HEIGHT

53 A- 701 MISCELLANEOUS DETAILS

54 A- 702 MISCELLANEOUS DETAILS

55 A- 703 MISCELLANEOUS DETAILS

56 A- 704 MISCELLANEOUS DETAILS

57 A- 705 MISCELLANEOUS DETAILS

58 A- 706 MISCELLANEOUS DETAILS

05 I NTERI OR DESI GN

59 ID 101 OVERALL FURNITURE PLAN

60 ID 102 ENLARGED FURNITURE PLAN

61 ID 103 ENLARGED FURNITURE PLAN

62 ID 104 FF&E SCHEDULE

06 STRUCTURAL

63 S- 001 STRUCTURAL NOTES

DOCUMENT 00 01 15 Page 2

64 S- 002 TYPICAL STRUCTURAL DETAILS

65 SD 101 STRUCTURAL DEMOLITION PLAN

66 S- 101 FOUNDATION PLAN / STRUCTURAL PLAN

67 S- 102 ROOF FRAMING PLAN

68 S- 301 BUILDING SECTIONS

69 S- 401 ENLARGED ROOF FRAMING PLANS, FIRE RISER ENCLOSURE

70 S- 501 TYPICAL COLUMN-FOOTING DETAIL, SCHEDULE OF COLUMN, WALL, &

FOOTINGS, L-SHAPED FOOTINGS, GRADE BEAMS, SLAB-ON-GRADE DETAILS

71 S- 502 TYPICAL BEAM ELEV/SECTION, TYPICAL COLUMN/BEAM JOINTS, DETAILS,

AND SECTIONS

72 S- 503 RETROFITTED EXIST CONCRETE BEAM, ENCLOSURE WALL FOR FIRE RISER

73 S- 504 MISCELLANEOUS DETAILS

07 FI RE PROTECTI ON

74 F- 001 FIRE PROTECTION GENERAL NOTES, LEGEND AND ABBREVIATIONS

75 FD 101 FIRE SPRINKLER DEMOLITION PLAN

76 FD 102 FAMNS DEMOLITION PLAN

77 FX 101 NEW FIRE SPRINKLER PLAN

78 FA 101 NEW FAMNS PLAN

79 F- 501 MISCELLANEOUS DETAILS

80 F- 502 MISCELLANEOUS DETAILS

81 FA 601 FIRE ALARM RISER DIAGRAM

82 FA 602 FAMNS MATRIX AND SEQUENCE OF OPERATIONS

08 PLUMBI NG

83 P- 001 PLUMBING GENERAL NOTES, LEGEND AND ABBREVIATIONS

84 PD 101 PLUMBING DEMOLITION PLAN

85 P- 101 NEW PLUMBING PLAN

86 P- 102 NEW PLUMBING ROOF PLAN

87 P- 401 ENLARGED PLUMBING PLAN

88 P- 402 ENLARGED PLUMBING PLAN

89 P- 501 MISCELLANEOUS DETAILS

90 P- 502 MISCELLANEOUS DETAILS

91 P- 601 PLUMBING FIXTURES AND EQUIPMENT SCHEDULE

92 P- 901 ISOMETRIC PIPING DIAGRAM

93 P- 902 ISOMETRIC PIPING DIAGRAM

94 P- 903 ISOMETRIC PIPING DIAGRAM

95 P- 904 ISOMETRIC PIPING DIAGRAM

09 MECHANI CAL

96 M- 001 MECHANICAL NOTES, LEGEND AND ABBREVIATIONS

97 MD 101 MECHANICAL DEMOLITION PLAN

98 MD 102 MECHANICAL DEMOLITION ROOF PLAN

99 M- 101A PARTIAL NEW MECHANICAL PLAN

100 M- 101B PARTIAL NEW MECHANICAL PLAN

101 M- 102 NEW MECHANICAL ROOF PLAN

DOCUMENT 00 01 15 Page 3

102 M- 103 MECHANICAL CONTROL PLAN

103 M- 301 MECHANICAL SECTION

104 M- 401 ENLARGED MECHANICAL PLAN

105 M- 501 MISCELLANEOUS DETAILS

106 M- 502 MISCELLANEOUS DETAILS

107 M- 601 MECHANICAL EQUIPMENT SCHEDULE

108 M- 602 MECHANICAL EQUIPMENT SCHEDULE

109 M- 701 SCHEMATIC DIAGRAM AND DDC POINT LIST

110 M- 702 SEQUENCE OF OPERATIONS

10 ELECTRI CAL

111 E- 001 SYMBOL LIST, ABBREVIATIONS, MOUNTING HEIGHT SCHEDULE AND

GENERAL NOTES

112 ES 101 NEW ELECTRICAL SITE PLAN

113 ED 101 EXISTING / DEMOLITION ELECTRICAL PLAN

114 ED 102 EXISTING / DEMOLITION ELECTRICAL ROOF PLAN

115 ED 103 ELECTRICAL SITE REMOVAL PLAN

116 E- 101 ELECTRICAL DISTRIBUTION PLAN

117 EL 101 PARTIAL LIGHTING PLAN - A

118 EL 102 PARTIAL LIGHTING PLAN - B

119 EP 101 PARTIAL POWER PLAN - A

120 EP 102 PARTIAL POWER PLAN - B

121 E- 401 ENLARGED PLANS 1

122 E- 402 ENLARGED PLANS 2

123 E- 403 ENLARGED PLANS 3

124 E- 404 ENLARGED PLANS 4

125 E- 501 MISCELLANEOUS DETAILS 1

126 E- 502 MISCELLANEOUS DETAILS 2

127 E- 601 ONE-LINE DIAGRAM - EXISTING

128 E- 602 ONE-LINE DIAGRAM - NEW

129 E- 603 MISCELLANEOUS DIAGRAMS 1

130 E- 604 MISCELLANEOUS DIAGRAMS 2

131 E- 605 PANEL SCHEDULES 1

132 E- 606 PANEL SCHEDULES 2

133 E- 607 LIGHT FIXTURE SCHEDULE 1 OF 2

134 E- 608 LIGHT FIXTURE SCHEDULE 2 OF 2

11 TELECOMMUNI CATI ON

135 T- 001 GENERAL NOTES, SYMBOL LIST, ABBREVIATIONS AND MOUNTING HEIGHT

SCHEDULE

136 TD 101 EXISTING / DEMOLITION TELECOMMUNICATIONS PLAN

137 TD 102 EXISTING / DEMOLITION TELECOMMUNICATIONS ROOF PLAN

138 T- 101 TELECOMMUNICATIONS PLAN

139 T- 102 SECURITY SYSTEM PROVISIONS PLAN

140 T- 103 PUBLIC ADDRESS / INTERCOM SYSTEM PROVISIONS PLAN

DOCUMENT 00 01 15 Page 4

141 T- 104 WIRELESS ACCESS POINT PLAN

142 T- 401 ENLARGED PLANS 1

143 T- 402 ENLARGED PLANS 2

144 T- 501 MISCELLANEOUS DETAILS 1

145 T- 502 MISCELLANEOUS DETAILS 2

146 T- 503 MISCELLANEOUS DETAILS 3

147 T- 504 MISCELLANEOUS DETAILS 4

148 T- 505 MISCELLANEOUS DETAILS 5

149 T- 506 MISCELLANEOUS DETAILS 6

150 T- 507 MISCELLANEOUS DETAILS 7

151 T- 601 MISCELLANEOUS DIAGRAMS 1

152 T- 602 MISCELLANEOUS DIAGRAMS 2

153 T- 603 TELECOMMUNICATIONS EQUIPMENT ELEVATION

-- End of Document --

DOCUMENT 00 01 15 Page 5

THIS PAGE INTENTIONALLY LEFT BLANK

DOCUMENT 00 01 15 Page 6

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes renovation of existing Passenger Terminal Building B17002 and incidental related work.

1.2.2 Location

The work is located at the Andersen Air Force Base, Guam. The exact location will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 48 hours prior to

SECTION 01 11 00 Page 1 excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.5.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

1.6 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

Pursuant to Contract Clause FAR 52.245-1 Government Property, the Government will furnish the following materials and equipment for installation by the Contractor:

DESIGNATION NO. DESCRIPTION QUANTITY

Refer to Sheet

ID104 FF&E

Schedule

Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified, and the various quantities will be adjusted when necessary.

Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Provide any additional quantities that are required.

1.6.1 Delivery Schedule

Notify the Contracting Officer in writing at least 30 calendar days in advance of the date on which the materials and equipment are required.

Coordinate a date and time for contractor to pick-up the item and transport it to the contractor's job site or shop for storage or additional fabrication or preparation.

1.6.2 Delivery Location

The materials and equipment will be delivered to 734AMS facility to hold until it can be delivered to the job site.

1.7 GOVERNMENT-INSTALLED WORK

Refer to Sheet ID104 FF&E Schedule.

SECTION 01 11 00 Page 2

1.8 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area.

Provide a Salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 11 00 Page 4

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)

ANSI/AHRI 210/240 (2008; Add 1 2011; Add 2 2012) Performance Rating of Unitary Air-Conditioning & Air-Source Heat Pump Equipment

AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)

ASCE 7-16 (2017; Errata 2018; Supp 1 2018) Minimum Design Loads and Associated Criteria for Buildings and Other Structures

INTERNATIONAL CODE COUNCIL (ICC)

ICC IBC (2018) International Building Code

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA

20-1; TIA 20-2; TIA 20-3; TIA 20-4)

National Electrical Code

NFPA 90A (2018) Standard for the Installation of Air Conditioning and Ventilating Systems

NFPA 101 (2018; ERTA 18-1; ERTA 18-2; ERTA 18-3;

ERTA 18-4; TIA 18-1; TIA 18-2; TIA 18-3;

TIA 18-4) Life Safety Code

U.S. Code (USC)

8 USC 1101 Definitions

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-301-01 (2019) Structural Engineering

U.S. DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT (HUD)

24 CFR 3280 (2019) Manufactured Home Construction and Safety Standards

SECTION 01 14 00 Page 1

1.2 DEFINITIONS

1.2.1 State

"State" when used in reference to states of the United States also includes the Territory of Guam.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

Personnel List

1.4 SPECIAL SCHEDULING REQUIREMENTS

a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. Specific items of work to which this requirement applies include:

b. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

1.5 CONTRACTOR ACCESS AND USE OF PREMISES

1.5.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.5.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.5.1.2 Installation Access

Obtain access to Andersen Air Force Base, Guam through participation in the Defense Biometrics Identification System (DBIDS). A background check will be conducted prior to being issued a one year DBIDs ID. If any derogatory or unfavorable information concerning the caregiver is disclosed, the unfavorable information will need to be resolved through the appropriate law enforcement office prior to being issued a DBIDS Credential. No fees are associated with obtaining a DBIDS credential.

SECTION 01 14 00 Page 2

Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.

1.5.1.2.1 Registration for DBIDS

Registration for DBIDS is available at https://www.andersen.af.mil/Contact-Us/Visitor-Center/. Procedure includes:

a. Present an approved and signed Base pass request - Contractor memo from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.

b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.

c. Provide completed USAF Affidavit Form and Triple (III) Log Information to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.andersen.af.mil/Contact-Us/Visitor-Center/.

d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.

e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.

1.5.1.2.2 DBIDS Eligibility Requirements

Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.

An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.

The Government is the final authority.

1.5.1.2.3 DBIDS Notification Requirements

a. Immediately report instances of lost or stolen badges to the Contracting Officer.

b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:

(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.

(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the

SECTION 01 14 00 Page 3 safety or security of the Installation or anyone therein.

1.5.1.2.4 One-Day Passes

Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.

1.5.1.3 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.5.2 Working Hours

Regular working hours will consist of an 8 1/2 hour period between 7 a.m.

and 4:30 p.m., Monday through Friday, excluding Government holidays.

1.5.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.

1.5.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to four hours. This time limit includes time for deactivation and reactivation.

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

SECTION 01 14 00 Page 4

1.6 SECURITY REQUIREMENTS

1.6.1 Employment Restrictions For Guam

he Contractor must not employ any person, for any work required by this contract, who: (1)is a non-immigrant as described in section 101(a)(15)(H)(ii) of the Immigration and Nationality Act (8 U.S.C.

1101(a)(15)(H)(ii), (2) is an alien having a residence in a foreign country which he has no intention of abandoning and who is coming to the United States to perform temporary services or labor.

1.6.2 Personnel List

Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:

a. Name

b. Date and place of birth

c. Citizenship

d. Home address

e. Social security number

f. Current pass expiration date

g. Naturalization or Alien Registration number

h. Passport number, place of issue, and expiration date

i. Guam Police clearance report for last six months

The request for personnel passes must be accompanied with the following certification:

"I hereby certify that all personnel on this list are either born U.S.

citizens, naturalized U.S. citizens with the naturalization number shown, or legal aliens with the alien registration number indicated."

Signature/Firm Name

1.6.3 Citizenship Requirements

Aliens will not be admitted to the work site without approval.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 14 00 Page 5

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 14 00 Page 6

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A615/A615M (2020) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Schedule of Prices; G

1.3 SCHEDULE OF PRICES

1.3.1 Data Required

Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction Contract) as directed by the Contracting Officer. Schedule of Prices must have cost summarized and totals provided for each construction category. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices. Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.

1.3.2 Payment Schedule Instructions

Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer.

Additionally, the Schedule of Prices must be separated as follows:

a. Primary Facilities Cost Breakdown:

SECTION 01 20 00 Page 1

Defined as work on the primary facilities out to the 5 foot line.

Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 foot line.

b. Supporting Facilities Cost Breakdown:

Defined as site work, including incidental work, outside the 5 foot line.

1.3.3 Schedule Requirements for HVAC TAB

The field work requirements in Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC must be broken down in the Schedule of Prices and in the Construction Progress Documentation by separate line items which reflect measurable deliverables. The value for each pay item listed below will be established on a case by case basis for each Contract. The line items are as follows:

a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. Submit the resulting findings to the Government to allow correction of the design. The progress payment will not be issued until the report is reviewed and approved.

b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report must contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.

c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data must be collected for one seasonal condition (either summer or winter depending on project timing).

d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government. The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.

e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously submitted Season I report.

f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. Compile this data into a report and submit to the Government. On completion of submittal review to ensure compliance with the pre-field engineering report

SECTION 01 20 00 Page 2 scope, progress payment is issued. Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.

1.4 CONTRACT MODIFICATIONS

In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the

EP 1110-1-8 .

1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.5.1 Content of Invoice

Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment shall include the documents listed below.

a. The Contractor's invoice, on 36CES Forms furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Forms must include certification by Quality Control (QC) Manager as required by the Contract.

b. The Estimate for Voucher/ Contract Performance Statement on 36CES Forms furnished by the Government. Use 36CES Forms, unless otherwise directed by the Contracting Officer, on 36CES Contracts when a Monthly Estimate for Voucher is required.

c. Contractor's Monthly Estimate for Voucher and Contractors Certification on 36 CES Forms with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.

d. Monthly Work-hour report.

e. Updated Construction Progress Schedule and tabular reports required by the contract.

f. Contractor Safety Self Evaluation Checklist.

g. Updated submittal register.

h. Solid Waste Disposal Report.

i. Certified payrolls.

j. Updated testing logs.

k. Other supporting documents as requested.

SECTION 01 20 00 Page 3

1.5.2 Submission of Invoices

If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.

Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.

1.5.3 Final Invoice

a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.

b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.

c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.

1.6 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

1.6.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR 32.503-6 Suspension or Reduction of Payments:

a. Reasonable deductions due to defects in material or workmanship;

b. Claims which the Government may have against the Contractor under or in connection with this Contract;

SECTION 01 20 00 Page 4

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and

d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.

1.6.2 Payment for Onsite and Offsite Materials

Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:

a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.

b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this Contract.

Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.

d. Materials are adequately insured and protected from theft and exposure.

e. Provide a written consent from the surety company with each payment request for offsite materials.

f. Materials to be considered for progress payments prior to installation must be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.

g. Materials in transit to the job site or storage site are not acceptable for payment.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00 Page 5

-- End of Section --

SECTION 01 20 00 Page 6

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

15 CFR 772 Definition of Terms

15 CFR 773 Special Licensing Procedures

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

SD-04 Samples

Color Boards; G

1.3 COLOR BOARDS FOR AIR FORCE PROJECTS

Submit five sets of color boards within 90 calendar days after Contract Award. Each set of boards must include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Present the samples on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Design modules to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, submit samples not less than 12 inches square with the board.

If more space is needed, more than one board per set may be submitted.

Certify that the color samples have been reviewed in detail, and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples does not relieve the Contractor of the responsibility to submit samples required elsewhere herein.

SECTION 01 30 00 Page 1

1.4 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.5 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

1.6 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by law.

1.7 SUPERVISION

1.7.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

For projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 20 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.

1.7.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

SECTION 01 30 00 Page 2

1.7.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.7.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.8 PRECONSTRUCTION MEETING

Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.8.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.9 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.

Include the following in the facility Turnover effort:

1.9.1 Red Zone Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project

SECTION 01 30 00 Page 3 and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

1.9.2 Meetings

a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.

At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.

c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.

e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.

Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

1.10 EXPORT LICENSES FOR OVERSEAS PROJECTS

Obtain individual export licenses and project export licenses required by the Department of Commerce regulations ( 15 CFR 772 and 15 CFR 773 ) so that no delays are experienced in shipping from the United States of America to a foreign country. For additional information, the Contractor may contact one of the U.S. and Foreign Commercial Service District Offices of the Department of Commerce which are located in almost every State.

1.11 WAIVER FOR WORKER'S COMPENSATION

In addition to FAR 52.228-4 Workers' Compensation and War-Hazard Insurance Overseas, the Secretary of Labor has granted a waiver. The waiver does not apply to employees who are hired in the United States, or who are residents, or citizens of the United States.

1.12 PARTNERING

Contractor shall host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, 36CES Design and Construction team, Subject Matter Experts, the Installation, Contractor, key subcontractors, and the Designer of Record are required to participate in the Partnering process.

SECTION 01 30 00 Page 4

1.12.1 Facilitated (Formal) Partnering

a. Provide and host a Formal Partnering session with key personnel from the project team including both Contractor and Government personnel.

All costs associated with the Partnering session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the Contractor.

b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees. Participants will bear their own costs for meals, lodging and transportation associated with Partnering .

c. The Initial Partnering Session must be a duration of one day and be held at a location off base as agreed to by…