Attachment 1 - AJJY 23-1026A Revised SOW dated 17AUG23.pdf
PDF 2 MB Posted
- Attached to
- AJJY 23-1026A Repair Booster Pump Station #3 B680, B681, B682A, B683 and B686, Andersen Air Force Base, Guam
- Solicitation number
- FA524023R0030
About this file
This statement of work describes a design-build project to repair Booster Pump Station #3 at Andersen Air Force Base in Guam. The project involves renovations to five buildings that make up the station, replacement of circuit breakers and wiring, replacement of the water treatment system, installation of new piping and pumps, and upgrades to the SCADA system. The work will be conducted in phases with submissions of 35%, 65%, and 100% design documents. The performance period is 550 calendar days.
The repair and construction work involves demolishing and replacing components in the five buildings, including doors, louvers, pumps, HVAC equipment, electrical systems, and coatings. New requirements include installation of hoists, flow meters, a water treatment system, and a Rockwell Automation SCADA system. The contractor must meet all applicable standards and codes for construction, sustainability, commissioning, and cybersecurity. Hazardous material abatement will be covered under bid option items.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023
36TH CIVIL ENGINEER SQUADRON
REPAIR BOOSTER PUMP STATION #3
B680, B681, B682A, B683 AND B6856
ANDERSEN AIR FORCE BASE, GUAM
DESIGN-BUILD PROJECT
PROJECT NO.: AJJY 23-1026A
06 JULY 2023 revised 17 AUGUST 2023
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023
36TH CIVIL ENGINEER SQUADRON
TABLE OF CONTENTS
PART 1 STATEMENT OF WORK / PROJECT PROGRAM
PART 2 ATTACHMENTS
Attachment 1: Location & Site Map
Attachment 2: Concept Reference Drawings
(Notional & Reference Only)
36TH CIVIL ENGINEER SQUADRON
PART 1
STATEMENT OF WORK / PROJECT PROGRAM
Table of Contents
CHAPTERS
1. PROJECT DESCRIPTION
2. PROJECT OBJECTIVES
3. SITE ANALYSIS
4. BUILDING/FACILITY REQUIREMENTS
5. ROOM REQUIREMENTS
6. ENGINEERING SYSTEM REQUIREMENTS
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023
36TH CIVIL ENGINEER SQUADRON
1. PROJECT DESCRIPTION
1.1 OVERVIEW:
This is a “Design-Build” project to repair Booster 3 Station (Bldg-680, Bldg-681, and Bldg-682A), Generator House (Bldg-683) and Water Treatment Station (Bldg-6856). Work will include renovations to Buildings 680, 681, 682A and 6856, replacement of circuit breaker and wires at Bldg-683, replacement of water treatment system at B6856, installation of new piping system, booster pumps, variable frequency drives and SCADA system, new painting and coating for walls, roof, and floor, installation of manual hoist system for each building, new aluminum door and rollup doors, provide new wires, conduit, and lighting fixtures.
1.2 EXISTING OPERATIONS:
The construction work activities will be coordinated with the facility manager and building occupants.
Contractor shall coordinate all interruption of utility services. All other actions not involving interruption of services can be conducted during regular working hours. In the event work/project activities other than what is indicated in this project program occur simultaneously, the contractor shall verify, coordinate, and may be required to phase such work/project activities.
1.3 LOCATION OF WORK:
The project is located at Booster 3 Station (Bldg-680, Bldg-681 and Bldg-682A), Generator House (Bldg-683) and Water Treatment Facility (Bldg-6856), Andersen Air Force Base (AFB) Guam. See attached site map.
2. PROJECT OBJECTIVES:
2.1 SCOPE OF WORK:
The contractor shall provide all labor, materials, equipment, permit and clearances, architectural and engineering services, transportation, supervision, and other incidental work required for the project. Other incidental work required includes all items and considerations necessary to ensure a complete and usable final product, including, but not limited to, the necessary design and construction considerations not specifically stated elsewhere in this statement of work. Complete and usable final product means that the completed final product is finished throughout and can be used to fully satisfy the requirements and the intended purpose of the project.
Perform all work according to all local and Federal safety and health regulations. Comply with the current Occupational Safety and Health Administration (OSHA) regulatory requirements.
All unforeseen utilities and appurtenances affected by the construction shall be protected. Damage to existing utilities and appurtenances shall be restored to its original condition at no additional cost to the Government.
The attached notional sketch/drawing with dimensions shown may not be accurate and is only to be used as reference for location and layout purposes. All drawings and shop drawings shall be based on actual measurements, conditions and shall be developed to provide the least demolition and removal work possible.
Contractor shall be responsible for field verification to verify on site all dimensions, elevations, utilities, power
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023 source, archive data, and all other requirements necessary for the successful completion, and satisfactory construction of the project. The contractor shall visit the project site; consult GEOBASE drawing archives to collect all available data on the existing infrastructure and to verify actual existing conditions.
During construction, booster station and water treatment station shall never be shut down for more than 16 hours per day. A temporary by-pass connection, temporary pump and temporary water treatment system shall be installed during construction as required.
2.2 WORK PHASING AND RELOCATION WORK:
The work shall be phased and must provide a work phasing plan/schedule as required to effect efficient completion of the repair/replacement work. Relocation activities shall be coordinated and scheduled with Facility Manager.
2.3 DEMOLITION AND REMOVAL:
BLDG-680, Booster Pump#1
Architectural
a. Coordinate with Facility Manager for all items that will remain.
b. Demolish and dispose of existing rollup door, frame, and accessories.
c. Demolish and dispose of existing louvers, frames, and accessories.
d. Demolish and dispose of existing single swing door, frame, and accessories.
e. Remove and dispose of existing eye bolts in the ceiling.
f. Remove existing roof coating and prepare surface to receive new roof coating.
g. Remove existing interior and exterior paint. Clean surface of dirt, grease, oil, loose particles, efflorescent, existing coating, etc. and prepare surface to receive new paint.
h. Remove existing interior floor finish.
Mechanical
a. Coordinate with Facility Manager for all items that will remain or materials to be salvaged. Any existing materials not accepted by the Government shall be disposed of by the contractor.
b. Remove and dispose of existing booster pump#1, accessories, components, pipes, fittings, support, and valves.
c. Remove and dispose of existing wall mounted ductless split a/c unit.
Electrical
a. Coordinate with Facility Manager for all items that will remain or materials to be salvaged. Any existing materials not accepted by the Government shall be disposed of by the contractor.
b. Remove and dispose of existing disconnect switches, transformer, electrical panel, conduits, clamps, and wires.
c. Remove and dispose of existing interior and exterior electrical lighting, switches, receptacles, conduits, clamps, and wires.
d. Remove and dispose of existing VFD, control system, components, conduits, clamps, and wires.
e. Remove existing remote terminal unit system, components, conduits, clamps, and wires.
f. Remove and dispose of existing circuit breaker for Bldg-680 (Booster Pump#1) located at Bldg-
683 (Generator House).
BLDG-681, Booster Pump#2
b. Demolish and dispose of existing louvers, frame, and accessories.
c. Demolish and dispose of existing single swing door, frame, and accessories.
d. Remove and dispose of existing eye bolts in the ceiling.
e. Remove existing roof coating and prepare surface to receive new roof coating.
f. Remove existing interior and exterior paint. Clean surface of dirt, grease, oil, loose particles, efflorescent, existing coating, etc. and prepare surface to receive new paint.
g. Remove existing interior floor finish.
Mechanical
a. Coordinate with Facility Manager for all items that will remain or materials to be salvaged. Any existing materials not accepted by the Government shall be disposed of by the contractor.
b. Remove and dispose of existing booster pump#2, accessories, components, pipes, fittings, support and valves.
c. Remove and dispose of existing wall mounted ductless split a/c unit.
Electrical
a. Coordinate with Facility Manager for all items that will remain or materials to be salvaged. Any existing materials not accepted by the Government shall be disposed by the contractor.
b. Remove and dispose of existing disconnect switches, transformer, electrical panel, conduits, clamps, and wires.
c. Remove and dispose of existing interior and exterior electrical lighting, switches, receptacles, conduits, clamps, and wires.
d. Remove and dispose of existing VFD, control system, components, conduits, clamps, and wires.
e. Remove existing remote terminal unit system, components, conduits, clamps, and wires.
g. Remove and dispose of existing circuit breaker for Bldg-681 (Booster Pump#2) located at Bldg-
683 (Generator House).
BLDG-682A, Booster Pump #3
Architectural
a. Coordinate with Facility Manager for all items that will remain.
b. Demolish and dispose of existing louvers, frame, and accessories.
c. Demolish and dispose of all existing double swing doors, frame, and accessories.
d. Remove and dispose of existing eye bolts in the ceiling.
e. Remove existing roof coating and prepare surface to receive new roof coating.
f. Remove existing interior and exterior paint. Clean surface of dirt, grease, oil, loose particles, efflorescent, existing coating, etc. and prepare surface to receive new paint.
g. Remove existing interior floor finish.
Mechanical
a. Coordinate with Facility Manager for all items that will remain or materials to be salvaged. Any existing materials not accepted by the Government shall be disposed of by the contractor.
b. Remove and dispose of existing booster pump #3, accessories, components, pipes, fittings, support, and valves.
c. Remove and dispose of existing wall mounted ductless split a/c unit.
Electrical
a. Coordinate with Facility Manager for all items that will remain or materials that will be salvaged.
Any existing materials not accepted by the Government shall be disposed of by the contractor.
b. Remove and dispose of existing disconnect switches, transformer, electrical panel, conduits, clamps, and wires.
c. Remove and dispose of existing interior and exterior electrical lighting, switches, receptacles, conduits, clamps, and wires.
d. Remove and dispose of existing VFD, control system, components, conduits, clamps, and wires.
e. Remove existing remote terminal unit system, components, conduits, clamps, and wires.
f. Remove and dispose existing circuit breaker for Bldg-682A (Booster Pump #3) located at Bldg-683
(Generator House).
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023
By-Pass Pit, East of BLDG-682A
a. Coordinate with Facility Manager for all items that will remain or materials that will be salvaged.
Any existing materials not accepted by the Government shall be disposed of by the contractor.
b. Remove and dispose of existing by-pass piping, water meters, accessories, components, supports, fittings, and valves.
BLDG-6856, Water Treatment Facility
b. Demolish and dispose of existing all rollup doors, frame, and accessories.
c. Demolish and dispose of all existing swing door, frame, and accessories.
d. Remove and dispose of existing eye wash and shower station.
e. Remove and dispose of existing eye bolts in the ceiling.
f. Remove existing roof coating and prepare surface to receive new roof coating.
g. Remove existing interior and exterior paint. Clean surface of dirt, grease, oil, loose particles, efflorescent, existing coating, etc. and prepare surface to receive new paint.
h. Remove existing interior floor finish.
a. Coordinate with Facility Manager for all items that will remain or materials that will be salvaged.
Any existing materials not accepted by the Government shall be disposed of by the contractor.
b. Remove and dispose of existing water treatment system, pipes, fittings, accessories, and components inside the building.
c. Remove and dispose of all exhaust fans, accessories, components, and duct.
d. Remove and dispose of existing chorine and fluoride analyzer.
Electrical
a. Coordinate with Facility Manager for all items that will remain or materials that will be salvaged.
Any existing materials not accepted by the Government shall be disposed of by the contractor.
b. Remove and dispose of all abandoned control system, accessories, components, clamps, conduits, and wires.
c. Remove and dispose of all abandoned disconnect switches, j-box, clamps, conduits, and wires.
d. Remove and dispose of existing electrical panel, transformer, clamps, conduits, and wires.
e. Remove existing remote terminal unit system, components, conduits, clamps, and wires.
f. Remove and dispose of existing lighting fixtures, accessories, components, clamps, conduits, and wires.
g. Remove and dispose of existing circuit breaker for Bldg-685 (Water Treatment Facility) located at
Bldg-683 (Generator House).
By-Pass Manifold, West of Bldg-6856
a. Coordinate with Facility Manager for all items that will remain or materials that will be salvaged.
Any existing materials not accepted by the Government shall be disposed of by the contractor.
b. Remove and dispose of existing by-pass piping, water meters, accessories, components, supports, fittings, and valves.
Additional Requirements
Hazardous Materials
a. Remove and dispose of any remaining raw water treatment chemicals.
b. Remove all raw water treatment materials and equipment from the building.
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023
c. Remove any hazardous materials that may be disturbed during construction. Perform Asbestos Containing Material (ACM) and Lead Base Paint (LBP) test on existing building prior to demolition and removal. Possible locations with ACM include, but are not limited to, pipes, floors, walls, and ceiling. Abatement and remediation shall be performed by Certified Industrial Hygienist and Industrial Hygienist. All asbestos and lead base paint removal will be done through Bid Option 1.
Historical, Archaeological and Cultural A historic building survey/assessment (Section 106 consultation with GovGuam SHPO) will be required to determine if the buildings are eligible to be included in the National Register. If the study determines they are indeed eligible, additional architectural study called HABS will be needed.
2.4 REPAIR AND CONSTRUCTION WORK:
BLDG-680, Booster Pump #1
Civil/Structural
a. Concrete seal opening of rollup door and louvers.
b. Repair any damage or cracks on the wall, roof, and flooring.
c. Provide manual overhead lifting hoist system for pump-motor maintenance that have capability to extend outside of access door. Hoist system working load maximized for pump-motor assembly.
a. Provide and apply mold and mildew resistant paint for entire building exterior and interior areas, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low-VOC content.
b. Provide fluid applied single component, air-dry silicone rubber coating with minimum 60 mils DFT, with a 10-year warranty. Color shall be white and provide for a high level of solar ultraviolet reflectivity. Coating must be formulated to resist algae and fungi growth and must not oxidize or discolor in hot and humid climates.
c. Provide new slip resistant flooring, 2-component, 100% solids, and moisture-tolerant epoxy resin.
d. Replace exterior single door with aluminum double door. Provide door shoe with rain drip and bottom gasket, overhead rain drip, and overlapping astragal (for double doors). All new door hardware finishes shall conform to ACBDS exterior door standards and installed as complete and functional. Ensure that newly installed door hardware & accessories will have maximum infiltration of 0.25 cubic feet/min./square foot in accordance with ASTM E 283-04, complete and functional to prevent water intrusion. Door threshold shall be specified and designed based on the existing floor and door profiles. Coordinate paint color with 36CES/OPS.
a. Provide and install new one (1) each 100HP, 1,250 GPM, minimum of 260 TDH booster pump split case including accessories, components, pipes, valves, fittings, and bracket.
b. Modify existing concrete pedestal and footing of existing pump to fit new pedestal requirement of pump. Coordinate requirements from manufacturer's recommendation.
c. Pipe materials shall be ductile iron conforming AWWA C151, Class 52 (min.). Pipe and fittings shall have a cement-mortar lining conforming to AWWA C104, standard thickness. Provide ductile iron flange type with stainless steel 316 type bolt and nuts.
d. Provide and apply mold and mildew resistant paint for new pipes, valves, and appurtenance, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low- VOC content.
e. Provide and install new one (1) each wall mounted ductless split a/c unit.
f. HVAC/R outdoor unit bracket, bolt and wedge anchors should be stainless steel.
g. HVAC/R outdoor unit condenser coil should be coated with 10,000HRS salt spray.
h. HVAC/R outdoor unit cabinet casing should be coated with extremely durable, polyurethane coating specially developed to provide comprehensive corrosion protection for the inner and outer
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023 casing of any HVAC/R unit.
i. HVAC/R electronic board should be coated with corrosion protection and water-resistant.
a. Replace/upgrade existing circuit breaker for Bldg-680 located at Bldg-683.
b. Replace/upgrade existing underground power line from Bldg-680 to Bldg-683.
c. Provide and install new electrical panel, receptacles, conduit, wires, brackets, and clamps.
d. Provide new 460V/120V transformer, disconnect switch, conduit, wires, brackets, and clamps.
e. Provide variable frequency drive with soft-starter bypass controller and disconnect switch. Soft-start bypass shall be used in the event of VFD failure. Provide a UL approved stainless steel enclosure for the pump controllers. Connect pump controllers & accessories to the SCADA system. The new system shall incorporate and allow for the pump controllers to have a Hand- Off-Auto (H-O-A) switch which can be used for both automatic and manual operation of the pumps without the SCADA system. Dry contacts shall be provided to the new SCADA system for control and monitoring functions. H-O-A selector switch shall be rotary heavy-duty type with extra contacts for input to PLC.
f. Provide and install new NEMA 4X stainless steel 316 type disconnect switch for new wall mount ductless split a/c unit.
g. Provide and install new Light Emitting Diode (LED) lighting fixtures with complete branch circuit conduits, wirings & light switches and plate covers for interior and exterior of Bldg-680.
BLDG-681, Booster Pump#2
a. Concrete seal opening of louvers.
b. Repair any damage or cracks on the wall, roof, and flooring.
c. Provide and install new manual lifting hoist system for pump-motor maintenance that have capability to extend outside of double door.
a. Provide and apply mold and mildew resistant paint for entire building exterior and interior areas, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low-VOC content.
b. Provide fluid applied single component, air-dry silicone rubber coating with minimum 60 mils DFT, with a 10-year warranty. Color shall be white and provide for a high level of solar ultraviolet reflectivity. Coating must be formulated to resist algae and fungi growth and must not oxidize or discolor in hot and humid climates.
c. Provide new slip resistant flooring, 2-component, 100% solids, and moisture-tolerant epoxy resin.
d. Replace exterior single door with aluminum double door. Provide door shoe with rain drip and bottom gasket, overhead rain drip, and overlapping astragal (for double doors). All new door hardware finishes shall conform to ACBDS exterior door standards and installed as complete and functional. Ensure that newly installed door hardware & accessories will have maximum infiltration of 0.25 cubic feet/min./square foot in accordance with ASTM E 283-04, complete and functional to prevent water intrusion. Door threshold shall be specified and designed based on the existing floor and door profiles. Coordinate paint color with 36CES/OPS.
a. Provide and install new one (1) each 100HP, 1,250 GPM, minimum of 260 TDH booster pump split case including accessories, components, pipes, valves, fittings, and bracket.
b. Modify existing concrete pedestal and footing of existing pump to fit new pedestal requirement of pump. Coordinate requirements from manufacturer's recommendation.
c. Provide and install new above-ground propeller type water flow meter rated for outdoor with digital totalizer register (US GPM). The new propeller type flowmeter with straightening vanes should have a flowrate and volumetric output and must comply with industry standard of 4- 20mA signal. The flowmeter should have a dial for manual reading. The new system shall be connected to the SCADA for monitoring, trending and other report in accordance with UFC 3- 230-01 requirements and NFM Public Works Utilities Criteria for Electric, Sewer and Water.
Provide isolation valve before the flowmeter.
d. New bypass line shall be provided to isolate the new flow meter for maintenance purposes.
e. Pipe materials shall be ductile iron conforming AWWA C151, Class 52 (min.). Pipe and fittings shall have a cement-mortar lining conforming to AWWA C104, standard thickness. Provide ductile iron flange type with stainless steel 316 type bolt and nuts.
f. Provide and apply mold and mildew resistant paint for new pipes, valves, appurtenance, and support, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low-VOC content.
g. Provide and install new one (1) each wall mounted ductless split a/c unit.
h. HVAC/R outdoor unit bracket, bolt and wedge anchors should be stainless steel.
i. HVAC/R outdoor unit condenser coil should be coated with 10,000HRS salt spray.
j. HVAC/R outdoor unit cabinet casing should be coated with extremely durable, polyurethane coating specially developed to provide comprehensive corrosion protection for the inner and outer casing of any HVAC/R unit.
k. HVAC/R electronic board and voltage monitor should be coated with corrosion protection and water-resistant.
Electrical
a. Replace/upgrade existing circuit breaker for Bldg-681 located at Bldg-683.
b. Replace/upgrade existing underground power line from Bldg-681 to Bldg-683.
c. Provide and install new electrical panel, receptacles, conduit, wires, brackets, and clamps.
d. Provide and install new 460V/120V transformer, disconnect switch, conduit, wires, brackets, and clamps.
e. Provide and install new variable frequency drive with soft-starter bypass controller and disconnect switch. Soft-start bypass shall be used in the event of VFD failure. Provide a UL approved stainless steel enclosure for the pump controllers. Connect pump controllers & accessories to the SCADA system. The new system shall incorporate and allow for the pump controllers to have a Hand-Off-Auto (H-O-A) switch which can be used for both automatic and manual operation of the pumps without the SCADA system. Dry contacts shall be provided to the new SCADA system for control and monitoring functions. H-O-A selector switch shall be rotary heavy-duty type with extra contacts for input to PLC.
f. Provide and install new NEMA 4X stainless steel 316 type disconnect switch for new wall mount ductless split a/c unit.
g. Provide and install new Light Emitting Diode (LED) lighting fixtures with complete branch circuit conduits, wirings & light switches and plate covers for interior and exterior.
BLDG-682A, Booster Pump #3
Civil/Structural
a. Concrete seal opening of louvers.
b. Repair any damage or cracks on the wall, roof, and flooring.
c. Provide and install new manual lifting hoist system for pump-motor maintenance that have capability to extend outside of double door.
Architectural
a. Provide and apply mold and mildew resistant paint for entire building exterior and interior areas, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low-VOC content.
b. Provide fluid applied single component, air-dry silicone rubber coating with minimum 60 mils DFT, warrantied for 10 years. Color shall be white and provide for a high level of solar ultraviolet reflectivity. Coating must be formulated to resist algae and fungi growth and must not oxidize or discolor in hot and humid climates.
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023
c. Provide new slip resistant flooring, 2-component, 100% solids, and moisture-tolerant epoxy resin.
d. Replace exterior double doors with aluminum double door for both sides. Provide door shoe with rain drip and bottom gasket, overhead rain drip, and overlapping astragal (for double doors). All new door hardware finishes shall conform to ACBDS exterior door standards and installed as complete and functional. Ensure that newly installed door hardware & accessories will have maximum infiltration of 0.25 cubic feet/min./square foot in accordance with ASTM E 283-04, complete and functional to prevent water intrusion. Door threshold shall be specified and designed based on the existing floor & door profiles. Coordinate paint color with 36CES/OPS.
a. Provide and install new one (1) each 150HP, 2,500 GPM, minimum of 260 TDH booster pump split case including accessories, components, pipes, valves, fittings, and bracket.
b. Modify existing concrete pedestal and footing of existing pump to fit new pedestal requirement of pump. Coordinate requirements from manufacturer's recommendation.
c. Pipe materials shall be ductile iron conforming AWWA C151, Class 52 (min.). Pipe and fittings shall have a cement-mortar lining conforming to AWWA C104, standard thickness. Provide ductile iron flange type with stainless steel 316 type bolt and nuts.
d. Provide and apply mold and mildew resistant paint for new pipes, valves, appurtenance, and support, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low-VOC content.
e. Provide and install new one (1) each wall mounted ductless split a/c unit.
f. HVAC/R outdoor unit bracket, bolt and wedge anchors should be stainless steel.
g. HVAC/R outdoor unit condenser coil should be coated with 10,000HRS salt spray.
h. HVAC/R outdoor unit cabinet casing should be coated with extremely durable, polyurethane coating specially developed to provide comprehensive corrosion protection for the inner and outer casing of any HVAC/R unit.
i. HVAC/R electronic board and voltage monitor should be coated with corrosion protection and water-resistant.
a. Replace/upgrade existing circuit breaker for Bldg-682A located at Bldg-683.
b. Replace/upgrade existing underground power line from Bldg-682A to Bldg-683.
c. Provide and install new electrical panel, receptacles, conduit, wires, brackets, and clamps.
d. Provide and install new 460V/120V transformer, disconnect switch, conduit, wires, brackets, and clamps.
e. Provide and install new variable frequency drive with soft-starter bypass controller and disconnect switch. Soft-start bypass shall be used in the event of VFD failure. Provide a UL approved stainless steel enclosure for the pump controllers. Connect pump controllers & accessories to the SCADA system. The new system shall incorporate and allow for the pump controllers to have a Hand-Off-Auto (H-O-A) switch which can be used for both automatic and manual operation of the pumps without the SCADA system. Dry contacts shall be provided to the new SCADA system for control and monitoring functions. H-O-A selector switch shall be rotary heavy-duty type with extra contacts for input to PLC.
f. Provide and install new NEMA 4X stainless steel 316 type disconnect switch for new wall mount ductless split a/c unit.
g. Provide and install new Light Emitting Diode (LED) lighting fixtures with complete branch circuit conduits, wirings & light switches and plate covers for interior and exterior.
By-Pass Pit, East of BLDG-682A
a. Provide pit backfill materials and compact as per Geotechnical/Soil Report recommendation as per Andersen AFB requirements.
a. Provide and install new aboveground 12-in ductile iron waterline with concrete pedestal and footing. New bypass line shall be provided to isolate the new flow meter for maintenance purposes.
b. Provide and install a new 12-in above-ground propeller type water flow meter rated for outdoor with digital totalizer register (US GPM). The new propeller type flowmeter with straightening vanes should have a flowrate and volumetric output and must comply with industry standard of 4-20mA signal. The flowmeter should have a dial for manual reading. The new system shall be connected to the SCADA for monitoring, trending, and other report in accordance with UFC 3-230-01 requirements and NFM Public Works Utilities Criteria for Electric, Sewer and Water. Provide isolation valve before and after the flowmeter.
c. Pipe materials shall be ductile iron conforming AWWA C151, Class 52 (min.). Pipe and fittings shall have a cement-mortar lining conforming to AWWA C104, standard thickness. Provide ductile iron flange type with stainless steel 316 type bolt and nuts.
d. Provide and apply mold and mildew resistant paint for new pipes, valves, appurtenance, and support, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low-VOC content.
BLDG-683, Generator House
Electrical
a. Provide monitoring points to SCADA for the existing emergency generator operation status in accordance with NFPA 110 using dry contacts and wiring from existing generator control panel to new SCADA panel.
b. As necessary; due to the upgrade of pumps and other additional loads, provide upgrade on the existing electrical equipment found to be deficient but not limited to the following: pad-mounted transformer, stand-by generator and ATS, switchboard, conduits, cables, and other associated electrical equipment to accommodate the new loads. Any upgrade needed will be done through Bid Option 2.
BLDG-6856, Water Treatment Facility
Civil/Structural
a. Repair any damage or cracks on the wall, roof, and flooring.
b. Provide and install new manual lifting hoist system for chemical 55gal drum that have capability to extend outside of rollup doors with chemical/corrosion resistant coating.
Architectural
a. Provide and apply mold and mildew resistant paint for entire building exterior and interior areas, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low-VOC content.
b. Provide fluid applied single component, air-dry silicone rubber coating with minimum 60 mils DFT, with a 10-year warranty. Color shall be white and provide for a high level of solar ultraviolet reflectivity. Coating must be formulated to resist algae and fungi growth and must not oxidize or discolor in hot and humid climates.
c. Provide and install new slip resistant flooring, 2-component, 100% solids, and moisture-tolerant epoxy resin.
d. Replace exterior singe doors with aluminum single doors. Provide door shoe with rain drip and bottom gasket, overhead rain drip, and overlapping astragal (for double doors). All new door hardware finishes shall conform to ACBDS exterior door standards and installed as complete and functional. Ensure that newly installed door hardware & accessories will have maximum infiltration of 0.25 cubic feet/min./square foot in accordance with ASTM E 283-04, complete and functional to prevent water intrusion. Door threshold shall be specified and designed based on the existing floor & door profiles. Coordinate paint color with 36CES/OPS.
e. Replace existing rollup doors, frames, and accessories with chemical/corrosion resistant coating.
Coordinate paint color with 36CES/OPS.
f. Provide new electrical/SCADA control room to isolate from chemical treatment room.
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023
a. Provide and install new water treatment system. Provide all piping and valves for the water treatment system.
b. Provide and install new primary chlorine gas system and analyzer system. Size the treatment system as needed. The system must include interface units/controller’s unit that will have a built-in data logger with the capacity to store data on fifteen (15) minutes intervals for up to six (6) months.
The interface must include a chlorine analyzer both Amperometric and Colorometric installed as part of the system. Amperometric analyzers shall continuously monitor hypochlorous acid (HOIC), temperature and pH. Measurement technology shall be amperometric/membrane which includes electrode, membrane, and electrolyte. Accuracy shall be less than 2% or +/- 10 ppb of the measured value, whichever is greater. Response time shall be approximately 90 seconds. Analyzer shall also employ NN-diethyl-p-phenylenediamine (DPD) colometric method of measurement using DPD indicator and buffer solution. Analyzer shall be capable of measuring the free or total residual chlorine. Measurement shall be recorded every 2.5 minutes. Interface units/controllers shall be connected to the SCADA system and shall incorporate an excel spreadsheet summarizing data and information for submission at any given time.
c. Provide and install new parallel secondary treatment system. Secondary treatment should be a skid mounted package using calcium hypochlorite complete with tank, pumps, and other accessories as a complete stand-alone treatment package. Size the treatment system as needed.
Coordinate requirements for system’s sequence of operation and connection to the SCADA system.
d. Provide and install new fluoridation system and analyzer system, size & suitable for the treatment system complete with leak detection. Coordinate requirements for system’s sequence of operation and connection to the SCADA system.
e. All mechanical components, accessories, piping, fittings, and support should be chemical/corrosion resistant inside the chemical treatment room.
f. Provide and install new eye wash and shower station.
g. Provide exhaust system to each water treatment system rated for chemical/corrosion resistant.
Size the exhaust system as needed.
h. Provide and install new one (1) each wall mounted ductless split a/c unit in the new proposed electrical/SCADA control room.
i. HVAC/R outdoor unit bracket, bolt and wedge anchors should be stainless steel.
j. HVAC/R outdoor unit condenser coil should be coated with 10,000HRS salt spray.
k. HVAC/R outdoor unit cabinet casing should be coated with extremely durable, polyurethane coating specially developed to provide comprehensive corrosion protection for the inner and outer casing of any HVAC/R unit.
l. HVAC/R electronic board and voltage monitor should be coated with corrosion protection and water-resistant.
a. Replace/upgrade existing circuit breaker for Bldg-6856 located at Bldg-683.
b. Replace/upgrade existing underground power line from Bldg-6856 to Bldg-683.
c. Provide and install new electrical room or enclose existing location of electrical panel and transformer.
d. Provide and install new electrical panel, receptacles, conduit, wires, brackets, and clamps with corrosion/chemical resistant coating (PVC Coated) located on new proposed electrical room.
e. Provide and install new 460V/120V transformer, disconnect switch, conduit, wires, brackets, and clamps with corrosion/chemical resistant coating (PVC Coated).
f. Provide and install new NEMA 4X stainless steel 316 type disconnect switch for new wall mount ductless split a/c unit.
g. Provide and install new Light Emitting Diode (LED) lighting fixtures with complete branch circuit conduits, wirings & light switches and plate covers for interior and exterior of with corrosion/chemical resistant coating.
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023
By-Pass Manifold, West of BLDG-6856
a. Provide and install new aboveground 12-in ductile iron waterline with concrete pedestal and footing. New bypass line shall be provided to isolate the new flow meter for maintenance purposes.
b. Provide and install a new 12-in above-ground propeller type water flow meter rated for outdoor with digital totalizer register (US GPM). The new propeller type flowmeter with straightening vanes should have a flowrate and volumetric output and must comply with industry standard of 4-20mA signal. The flowmeter should have a dial for manual reading. The new system shall be connected to the SCADA for monitoring, trending, and other report in accordance with UFC 3-230-01 requirements. Provide isolation valve before the flowmeter.
c. Provide and install new injection, sampling points for chorine and fluoride.
d. Pipe materials shall be ductile iron conforming AWWA C151, Class 52 (min.). Pipe and fittings shall have a cement-mortar lining conforming to AWWA C104, standard thickness. Provide ductile iron flange type with stainless steel 316 type bolt and nuts.
e. Provide and apply mold and mildew resistant paint for new pipes, valves, appurtenance, and support, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low-VOC content.
Inter-tie Vault, West of Bldg-6856
a. The trench excavation for new underground by-pass line will be managed as High probability encountering MEC/UXO. Therefore, the contractor will be required to adhere to Munitions Response Explosive Safety Submission (MRESS), current amendment series.
b. Provide and install new underground inter-tie concrete vault with personnel access door between MW1-3 piping and MW5-9 piping.
a. Provide and install new underground ductile iron waterline inter-tie for potable and non-potable water with backflow prevention device.
b. Pipe materials shall be ductile iron conforming AWWA C151, Class 52 (min.). Pipe and fittings shall have a cement-mortar lining conforming to AWWA C104, standard thickness. Provide ductile iron flange type with stainless steel 316 type bolt and nuts.
c. Provide and apply mold and mildew resistant paint for new pipes, valves, appurtenance, and support, complete. Coordinate paint color with 36CES/OPS. Paints and coatings shall be zero or low-VOC content.
Additional Requirements
a. Restore other areas affected by the new work to original condition or better.
b. Provide hydro- seeding on sodded areas affected by the new work.
c. Restore road AC/concrete pavement, concrete sidewalk and curb affected by new work to original condition or better. Thickness of AC/concrete, friction course, base course, and sub- base shall be in accordance with thickness required by Andersen AFB or match the existing thickness on pavement areas affected by the new work, whichever is greater.
a. Perform the required hydrostatic /pressure/leak testing and line deflection at the new water line in accordance with UFC.
b. Perform the required disinfection of the new waterline in accordance with American Water Works Association (AWWA) C651 (Standard for Disinfecting Water mains).
c. The contractor shall request water outages via the 36 CES Base Utility via the Contracting Officer’s representative, thirty (30) days prior to the desired date of the outage. The contractor shall ensure
REPAIR BOOSTER PUMP STATION #3 B680, B681, B682A, B683 AJJY 23-1026A
AND B6856 ANDERSEN AIR FORCE BASE, GUAM Version: 06 JULY 2023 17 AUGUST 2023 that approval has been obtained for the outage prior to performing work.
d. Provide fire alarm and fire suppression system. Shop drawing submittals of the Fire Protection
System shall be reviewed and approved by the Fire Protection Engineer. Preliminary and final test shall be certified by a U.S. Registered Fire Protection Engineer.
e. Employ independent Commissioning Firm to test the newly installed system.
f. Perform complete system start up and functional testing of the new equipment’s by an authorized manufacturer’s representative and witnessed by 36th CES/CEOIH, Air Force Civil Engineer Center Field Support and Civil Engineer Maintenance, Inspection and Repair Team representative.
g. Test and balance the system and air distribution as defined in Division 01 Submittals and Special testing requirements. AABC or NEBB certification is required for units installed. Submit balancing report to the PM for verification and approval.
h. Provide minimum 8-hour training for user and other government maintenance personnel prior to turnover.
i. Miscellaneous repair, restoration and finishing work not specifically included under Items identified above, but required to deliver a completed, functional, and Code-Compliant, Energy Efficient system.
j. Provide coordination drawing to ensure new installation will not be in conflict to existing utilities.
k. Provide drawings approved by a Professional (Mechanical) Engineer for the pumps, water treatment etc. mounting, transition and other related appurtenances prior to work execution.
a. Provide new Rockwell Automation SCADA system complete with control and monitoring functions for the booster pump station, treatment system and the tank. The system will use an Allen- Bradley Programmable Logic Controller (PLC) as the major component in the SCADA system. The PLC shall be compatible to the existing system at Andersen AFB SCADA system.
PLC’s must provide control and monitoring functions with necessary logic and timing functions, memory, software, input/output points and communication capabilities required to meet all the requirements and objectives of the project including all accessories and logic programs for a computer and ready for use. The system shall accommodate the replacement of assemblies without having to disconnect field wiring. Removable connectors shall be used to connect field wiring to the individual circuit board. Control strategies and alarms shall be incorporated in the SCADA system. SCADA cabinet enclosure shall be NEMA 4X with dead front door and cooling fans for ventilation suitable for outside use and corrosive environment.
b. Provide two (2) each 15-inch touch screen Human Machine Interface (HMI) one in front of SCADA panel at Bldg-682A (Booster Pump #3) and another one at Bldg-6856 (Water Treatment Facility) to allow for operator interface with the SCADA system. Information shall be seen on screen at any given real time. HMI should be computer-based with the latest NFM CIO approved operating system compatible with the existing system used by the Andersen AFB SCADA system.
c. Provide power to the SCADA panel complete with conduit, wiring and all the necessary accessories as a complete and usable system. Connect newly installed Variable Frequency Drives (VFD) controllers & accessories to the new SCADA system. Coordinate with the VFD manufacturer for connection to the SCADA system.
d. New SCADA system will be standalone and ready for connection to on-going B18001 Central SCADA system project.
e. Provide surge protective device (SPD) for power supply and communication. SPD shall also function as lighting protection. Provide SPD at downstream of VFD and SCADA.
f. Replace remote terminal units.
g. Install new underground 2in conduit for communication line for B680, B681, B682A, B683 and
B6856.
h. Employ independent Commissioning Firm to test the newly installed system.
i. Provide coordination drawing to ensure new installation will not be in conflict to existing utilities.
j. Provide shop drawings approved by a Professional (Electrical) Engineer for all electrical installation.
2.5 ANTITERRORISM:
Comply with UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings for Antiterrorism requirements.
2.6 SEISMIC REHABILITATION: NOT USED.
2.7 BID OPTION ITEMS:
Bid Option 1: Provide unit cost for Hazardous material abatement and remediation as required to perform the scope of work for the building. Any HAZMAT found during the project will be remediated by using the Option 1-unit prices to adjust the contract. See Bid Schedule for Quantities.
Bid Option 2: Provide unit cost for B683 Electrical Upgrade.
2.8 HAZARDOUS MATERIAL ASSESSMENT:
Hazardous material assessments are required at all areas to be affected by the new work. Contractor shall perform hazardous material assessment and testing prior to start of repair work including demolition work and submit final report to the government with recommendations for abatement and remediation if needed. Areas containing hazardous materials that will not be affected by the new work must be left in place, undisturbed and encapsulated if directly exposed to personnel. No abatement cost or work will be included in the Base Bid. All abatement work would be performed using the Bid Option 1 unit pricing.
2.9 HAZARDOUS MATERIAL ABATEMENT:
Where hazardous materials are found, aside from the water treatment chemicals stated above, abatement and remediation shall be done as part of Bid Option 1. Abate the hazardous materials in accordance with all local and federal guidelines for safe removal and disposal prior to start of repair work. Hazardous Materials shall be removed, stored, and disposed of in accordance with the applicable Federal and Local government requirements. Comply with all Federal and Local government safety and disposal requirements for remediation work. After proper abatement of the hazardous materials, patch and prepare the impacted areas to receive new finish. Coordinate abatement work with Contracting Officer well in advance to ensure proper notification to all occupants and the Command.
Environmental Requirements: Contractor shall ensure that all required permits are obtained before construction begins. Contractor must abide by Occupational Safety and Health Act (ACM abatement, lead- based paint abatement, noise, confined space, etc.) or others as applicable. Coordinate with Contracting Officer with regard to consultations with Environmental group regarding environmental requirements.
Comply with the following requirements:
a. Coordinate with the installation Asbestos Program Manager (APM) and Region Asbestos Program Coordinator (APC) for any previous asbestos and lead based paint surveys.
b. Coordination must be established with APM and APC for tenant notification of abatement or sampling and work schedule which may impact the tenants.
c. Provide copies of all AHERA certifications: (asbestos worker, contractor supervisor, asbestos monitor, asbestos project designer).
d. Provide copies and proof of medical surveillance monitoring.
e. Provide copies of abatement plans, hazard communication plan for APM and APC approval.
f. All asbestos samples must be taken by a certified and current AHERA asbestos inspector.
g. All asbestos samples shall be analyzed by an accredited NVLAP lab.
h. NESHAP notification shall be provided to GEPA and copy to the Installation APM and Region's APC.
i. Waste shipment records (WSR) shall be provided to GEPA and copy to installation APMs and Region's APC.
j. Waste manifests with receipt signatures from permitted disposal facility must be provided to the APMs and
APC.
2.10 SUBMITTALS:
The following submittals are required.
Submittal Requirements (After Award and Before Start of Construction):
1. Activity Hazard Analysis (AHA)
2. Health and Safety Plan (HSP)
3. Design Quality Control Plan (DQC)
4. Contractor’s Quality Control Plan (CQC)
5. Construction Schedule
6. Hazardous Material Assessment
7. Munition Response Explosive Safety Submission (MRESS) – Munition and Explosives of Concern
(MEC) Intrusive Investigation Work Plan (MEC field work will not be allowed to start without Government approved MEC Plan)
8. Water line disinfection plan and procedure
9. Water line leak test procedure
10. Temporary water treatment and bypass plan procedure
11. Design Construction Documents: Prepare, organize, and present Design Construction Documents.
Contractor will not be allowed to start construction without the Government approved documents listed below.
Construction Submittals (As required by specifications)
Provide mix design calculations in accordance with the requirements included in specification section 01 33 00 Submittal Procedures.
Design Drawings: Prepare using AutoCAD 2016 formatted for ANSI D (22” x 34”) sheets. The Ready for Construction submission shall be stamped and signed by the Designer of Record (DOR).
Submit all CAD files for the final drawings on CD-ROM or DVD disks in AutoCAD 2016 format. Drawing files must be full files, uncompressed and unzipped.
Basis of Design: Each submission shall include a basis of design with all proposed materials including Design Analyses and Calculations to substantiate the design meets the RFP and all applicable codes.
Specifications: Shall be Unified Facilities Guide specifications submitted in Construction Specification Institute (CSI) 2010 format edit with SpecIntact software in accordance with UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard.
Contractor shall submit the number of copies as requested as defined under each required submission identified below. The basis of design, design drawings and specifications shall be included on a CD-ROM in addition to the required hard copy for each submission. Each submission shall be submitted to the Contracting Officer or their representative for Government review and concurrence.
The Contractor shall submit a copy of the Government’s review comments from each prior submission with each subsequent submission. This document shall indicate the corrective action taken for each comment and/or other proposed solution. Incomplete submissions will be returned to the Contractor with no additional time added to the performance period.
Electronically seal and sign all Acrobat PDF drawings, specifications, and other documents. The electronic signatures shall be printable and viewable in Adobe Acrobat Reader with no additional software.
Provide the following Design Submittal Packages:
a. 35% Concept Design Documents Submittal: 30 calendar days following the construction award date of delivery order.