0 Pre-Proposal Conference Minutes.pdf
PDF 302 KB Posted
- Solicitation number
- FA520526R0001
About this file
This document is a Pre-proposal Conference Minutes and Record of Site Visit for RFP No. FA520526R0001, issued by the 35th Contracting Squadron at Misawa Air Base, Japan. The solicitation is for an Indefinite-Delivery/Indefinite-Quantity (IDIQ) contract covering roads, pavements, and miscellaneous civil work at the installation. Five firms attended the pre-proposal conference on February 18, 2026: Baikouen-Japan Co., Ltd.; Fujimoto Kensetsu Co., Ltd.; Kamikita Kensetsu Co., Ltd.; Maeda Road Construction Co., Ltd.; and Nippo Corporation. The conference, conducted by Ms. Ozawa (Buyer), covered general requirements, price structure, contract clauses, representations and certifications, evaluation factors, and other contract requirements (B001, H002, H003, H004, H007, K002, K003, K004). Technical briefing by Mr. Hayashi addressed specifications including Project Manager and QCQ Manager qualifications and jobsite access requirements.
The contract encompasses Exhibit Line Items (ELINs) structured across multiple work categories: survey and measurement, test digging, site preparation, general construction, asphalt paving, curbs and sidewalks, pavement markings, earthwork, sanitary sewer and drainage, water lines, removal and disposal, and Military Family Housing carport areas. Estimated quantities are based on three years of planned construction work and may be underused, exceeded, or not used in any contract year. A site visit was conducted at Freedom Drive where Mr. Hayashi briefed attendees on typical pavement repair work. Written questions must be submitted by 1300 hours on February 20, 2026. The proposal submission closing date and time is 1100 hours on March 12, 2026, Japan Standard Time.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
35TH FIGHTER WING (PACAF)
MISAWA AIR BASE, JAPAN
24 Feb 26
MEMORANDUM FOR ALL PROSPECTIVE OFFERORS
FROM: 35th Contracting Squadron, Construction Flight
Bldg. 656, Misawa Air Base
Misawa-shi, Aomori-ken, Japan
SUBJECT: Pre-proposal Conference Minutes & Record of Site Visit, Request for Proposal (RFP) No.
FA520526R0001, Roads/Pavements & Misc. Civil Work Indefinite-Delivery / Indefinite-
Quantity (IDIQ) Contract, Misawa AB, Japan
1. These are the minutes of the pre-proposal conference for the subject solicitation, including record of site visit, conducted on 18 Feb 26 by the 35th Contracting Squadron IAW Attachment 1 of subject
RFP, Other Contract Requirements, para.9. L001 “Notice of Pre-bid/Pre-proposal Conference” and
FAR 52.236-27 Site Visit (Construction). The following are the names of the firms and the
Government representatives who attended the conference and site visit:
Firms (in alphabetical order) Government
Baikouen-Japan Co., Ltd. Capt Ocampo, Procuring Contracting Officer, 35 CONS/DBO
Fujimoto Kensetsu Co., Ltd. Mr. Nogawa, Chief, Construction Flight, 35 CONS/PKA
Kamikita Kensetsu Co., Ltd.
Maeda Road Construction Co., Ltd.
Nippo Corporation
Mr. Kawahara, Team Lead, 35 CONS/PKA
Ms. Ozawa, Buyer, 35 CONS/PKA
Ms. Sasaki, Buyer, 35 CONS/PKA
Ms. Ikarashi, Buyer, 35 CONS/PKA
Ms. Murakami, Buyer, 35 CONS/PKA
Ms. Miyako, Buyer, 35 CONS/PKA
Mr. Hayashi, Civil Engineer, 35 CES/CENM
2. Pre-proposal conference.
a. The conference was opened at 1300 hours by Ms. Ozawa/Buyer who explained the scope and requirements of the solicitation and provided remarks and filling instructions by presenting the
Slide Show in the attachment. All attendees were allowed to ask questions at any time during the session.
Highlights of the explanation:
• General Requirements
• Price Structure and Exhibit Line Items
• Contract Clauses and Solicitation Provisions
• Fill-Ins, Representations and Certifications
• Preparation of Price Proposal and Past Performance Information
• Evaluation Factors and Procedures
• Other Contract Requirements (B001, H002, H003, H004, H007, K002, K003 and K004)
• Historical Data
• Written Question /Proposal Submission Due Dates/Time
b. Technical briefing was made by Mr. Hayashi/Civil Engineer with regard to the specifications and exhibit line items.
Highlights of the technical briefing:
(i) Specifications.
• Requirements of Experience/Qualifications for Project Manager, QCQ Manager, and
Jobsite Foremen (Section 01 11 00, para. 1.5)
• Availability of Work Site, Working Hours and Apple Gate (Specification 01 11 00, para.
1.7)
(ii) Exhibit Line Items (ELINs)
• Structure of ELINs
• Survey and measurement (ELIN A/B/C 001 thru 004)
• Test digging (ELIN A/B/C 007)
• Test sampling and site preparation for base stabilization mixture (ELIN A/B/C 009)
• General construction and other work (ELIN A/B/C 010 thru 021)
• Asphalt paving work (ELIN A/B/C 022 thru 039)
• Curbs and sidewalk work (ELIN A/B/C 041 thru 059)
• Pavement markings, traffic safety work (ELIN A/B/C 060 thru 067)
• Earth work, sodding, planning work (ELIN A/B/C 068 thru 076)
• Sanitary sewer, drainage work (ELIN A/B/C 077 thru 097)
• Water line work (ELIN A/B/C 098 and 099)
• Removal and Disposal work (ELIN A/B/C 100 thru 127)
• Military Family Housing (MFH) Carport Area (ELIN A/B/C 128 thru 159)
(iii) The estimated quantities of ELINs are based on planned construction work over the next three years. Construction requirements and their execution timeframes may change depending on road and parking conditions, project priorities, and availability of funds. Therefore, the specified quantities may be underused, exceeded, or not used at all in each contract year.
c. Question and Answer during pre-proposal conference.
Question: Should the submittals required under K002 thru K004 of Other Contract Requirements be included in Part I, “Summary and Miscellaneous Data”?
Answer: The submittals for K002 thru K004 may be provided separately from Part I or included within Part I.
3. Site Visit. Following the pre-proposal conference ended at 1330 hours, the site visit was conducted at
Freedom Drive, Misawa AB.
a. Mr. Hayashi made on-site briefing to all attended prospective offerors on the typical pavement repair work required in the contract.
b. No particular questions were received during the site visit.
4. At the end of the site visit, Mr. Kawahara reminded all attendees that the terms of the solicitation, including all attachments, remain unchanged unless the solicitation is amended in writing. The prospective offerors’ question(s) for this solicitation, if it may arise after this pre-proposal conference and the site visit, must be submitted to 35 CONS in writing no later than 1300 hours on 20 Feb 26.
The proposal submission closing date/time is at 1100 hours of 12 Mar 26, Japan Standard Time (JST).
The site visit was adjourned at 1400 hours on 18 Feb 26.
MAYUMI OZAWA
Buyer
KAZUAKI KAWAHARA
Team Lead
Attachment:
Slide Show, 21 Slides (4 pages)
| 2026-02-24T12:37:08+0900 | |
| OZAWA.MAYUMI.1594581730 |
| 2026-02-24T11:15:58+0900 | |
| KAWAHARA.KAZUAKI.1288488637 |
File details come from the government source that posted it. Updated .