Primary Training Ranges OM&S Government Responses to Industry Questions for RFP
ID Reference Question/Comment Response
SOW Para. 3.6.1 /MHAFB Wildland Management
Plan (WFMP) Pg. 14
Request the Government reconcile and clarify the GFE equipment provided against that required by the MHAFB WFMP specifically pertaining to the requirement to have two motor graders at Saylor Creek, one 2.5 ton pumper truck with 1200 gallon tank at Saylor Creek and two 1-ton trucks with 250-gallon and 350-gallon slip-on tanks at Saylor Creek. The GFE listing at TE-5 shows that one 2.5 ton truck located at Juniper Butte, 2 F-450 Pickups with slip-on tanks located at Juniper Butte and only one motor grader located at
Saylor Creek
SOW has been updated to remove all reference to the Wildland Fire
Management Plan. Will be updated in an Amendment to the RFP at a later date.
39 SOW B&G Services Summary
PO05 Range Target Maintenance & Construction lists an MPP of 25% for Avon Park. Is the Government's intention to have the PTR contractor perform this function at Avon Park versus the BOS contractor?
No. The Workload estimate shows strafe pits are maintained by this contract. Please note clarification of strafe targets on North
Conventional Range. Will be updated in an Amendment to the RFP at a later date.
40 SOW B&G Services Summary
B&G Services Summary PO07 Roads, Grounds, and Firebreak:
Maintain improved/unimproved roads, firebreaks, fences, and grounds. (C-2.1, 2.4, 3.5). The MPP is listed as 12% for Avon Park.
Is it the Government's intention that the PTR contractor perform this maintenance effort versus the current Avon Park BOS contractor?
No. The Workload estimate shows ground maintenance to be accomplished at Avon Park.
SOW EC Services Summary and Poinsett EC
Workload estimate
EC Services Summary PO016 Maintain assigned range equipment
(AN/MSR-T4) TRAINS shows an MPP for PE of 11% and an MPP for PT of 0%. Page 111 of the Services Summary lists the abbreviation for
Poinsett ECR as PT. The MPP for PO016 is apparently in agreement with the Poinsett Workload estimate. Will the Government please clarify what the MPP for PE at 11% represents?
PE Removed. Will be updated in an Amendment to the RFP at a later date.
42 SOW EC Services Summary
PO015 Maintain assigned range equipment (AN/MST-T1A) MUTES.
This item has an MPP listed for PE of 18% and PT of 14%. Page 111 of the EC Service Summary lists the abbreviation for Poinsett ECR as PT and there is no abbreviation of PE listed.
Will the Government please clarify the abbreviation PE and clarify exactly what MPP percentage pertains to MUTES at Poinsett ECR?
PE Removed. Will be updated in an Amendment to the RFP at a later date.
43 SOW EC Services Summary
PO01 Site Operations. (Qualified Manpower requirements)
The MPP for Poinsett for this item does not contain any percentage.
Will the Government please clarify the MPP for this item?
It is 4%. Will be updated in an Amendment to the RFP at a later date.
44 SOW EC Service Summary PO24
PO24 MPP lists GP at 4%.
Assuming GP means Granite Peak, will the Government please update the EC Services Summary to remove all reference to GP?
Removed. Will be updated in an Amendment to the RFP at a later date.
FA4890-11-R-0012 Page 1 of 2 3/13/2012
Primary Training Ranges OM&S Government Responses to Industry Questions for RFP
ID Reference Question/Comment Response
45 SOW Section C-1, Table 1-2
The mentioned table lists Avon Park, Belle Fourche ESS, Poinsett EC and B&G, RIIS, and Snyder ESS as optional sites.
Will the Government please explain the rationale for listing these as optional and provide some assurance that if a site in not exercised during one contract option year, that it will not be exercised in any subsequent year? Due to the nature of the equipment maintained on these sites, bringing a site back on-line after closing it down presents a nearly insurmountable risk to the contractor. Once the trained/qualified workforce is dispersed, it will be very difficult to reconstitute a trained/qualified workforce within any reasonable timeframe. Can the Government assure bidders that the situation described above will not occur?
These sites are listed as optional due to uncertainty of funding during the current debate on DoD funding. If an option is not exercised, the government does not intend to exercise an out year option. If the decision is made to reopen a site in later years it will have to be separately negotiated due to the pre-existing conditions changing.
Does Avon Park, which is a Class B/C range, utilize a remotely located RCO?
A Class B/C range by definition does not have a RCO. Scoring systems for the south conventional range are located in the former RCO tower.
47 Collective Bargaining Agreements
Previous CBAs included an employee seniority listing which included original hire date. This is important for new offerors in order to know who much non-productive labor to build into their pricing. Can seniority listings for each location be provided?
IAW FAR 52.222-41(n) Seniority list. Not less than 10 days prior to completion of any contract being performed at a Federal facility where service employees may be retained in the performance of the succeeding contract and subject to a wage determination which contains vacation or other benefit provisions based upon length of service with a
Contractor (predecessor) or successor (29 CFR 4.173), the incumbent
Prime Contractor shall furnish the Contracting Officer a certified list of the names of all service employees on the Contractor’s or subcontractor’s payroll during the last month of contract performance.
Such list shall also contain anniversary dates of employment on the contract either with the current or predecessor Contractors of each such service employee. The Contracting Officer shall turn over such list to the successor Contractor at the commencement of the succeeding contract.
FA4890-11-R-0012 Page 2 of 2 3/13/2012