PTR SF33 RFP Solicitation FA4890-11-R-0012
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until local time
X
A X B
C D
EX
X G F 104 - 115
116 - 136 X H 137 - 140
DOMINIC.ESPOSITO@LANGLEY.AF.MIL
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
1 140
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
FA4890 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 4 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and
See Section L-4.1 and 6.3.3 conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
DOMINIC ESPOSITO 757-225-7712
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 69
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
70 - 73 74 - 82
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 83 - 84 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 85 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
86 - 102
PART II - CONTRACT CLAUSES
ACC AMIC/PKC
11817 CANON BLVD, SUITE 306
NEWPORT NEWS VA 23606-4516
757-764-9154
757-764-9153FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.5. DATE ISSUED
23 Feb 2012
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
FA4890-11-R-0012
Section B - Supplies or Services and Prices
PRICING SCHEDULE B
SCHEDULE B
PRICING SCHEDULE B
At contract award, the CLINs reflected in the EXCEL spreadsheet (Atch 5) will be entered in the Procurement Desktop – Defense (PD2), the AF contract writing system. Offerors are required to complete and submit the EXCEL spreadsheet with their offer. Offerors are not required to complete the Section B Pricing schedule in pages 3 through 69 of the RFP. The EXCEL spreadsheet is for the convenience of the Government for evaluating proposals. At award, the final prices will be transferred to Section B contained in the resulting contract.
SCHEDULE B
Unit prices shall be rounded to whole dollar amounts before they are multiplied by the quantity. The price multiplied by the number of units shall equal the extended price of each CLIN. If submitted unit prices are not rounded to the nearest dollar, the Government will round the unit prices to whole dollar amounts at the time of contract award or modification. If the decimal is followed by 5, 6, 7, 8, or 9, the price will be rounded up to the nearest whole dollar. If the decimal is followed by 0, 1, 2, 3, or 4, the price will be rounded down to the nearest whole dollar. Handling rate percentages shall have no more than four decimal places (i.e. XX . XXXX%). For cost CLINs, the total estimated cost of each CLIN shall equal the Government provided cost base with the handling rate applied. All numbers shall be rounded to whole dollar amounts. (Reference L-10 and M-3.4)
COST CLINS – ADDITIONAL OPERATIONS HOURS (AOH)
The AOH CLINs are listed as NTE. The offeror shall submit fully burdened hourly rates for site operations at each location, including labor and non-labor costs, for operations outside the basic hours as described in the SOW. Rates must be provided for the base year and all option years. The offeror shall submit a breakdown of the loaded rates that includes the base rate of each labor category proposed for site operations and all detailed burden that create the fully burdened AOH rate. When AOH are approved, these rates will be used to generate the monthly invoice to bill against the appropriate CLINs. The proposed rates will be incorporated into the resulting contract as Exhibit A.
COST CLINS – EXTENDED MAINTENANCE AND SUPPORT
Overtime for the Extended Maintenance CLINs are listed as NTE. The offeror shall submit fully burdened labor rates for each site for each labor category proposed. Rates must be provided for the base year and all option years.
The offeror shall submit a breakdown of the loaded rates that includes the base rate and all detailed burden that create the fully burdened rate. If use of the Extended Maintenance CLIN is approved, these rates will be submitted in a monthly invoice to bill against the appropriate CLINs. The proposed rates will be incorporated into the resulting contract as Exhibit B.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 60 Days Transition Period
FFP
Transition Services for all sites prior to commencement IAW the SOW. Transition is from 1 Nov 12 to 31 Dec 12.
FOB: Destination
SIGNAL CODE: A
NET AMT
0002 12 Months Base Yr Program Management
FFP
Program Management for OM&S IAW SOW paragraph 1.7. Section C-1 of the SOW and not specifically priced in other CLINs of this contract. Period of Performance, 1 Jan 13 to 31 Dec 13.
0003 12 Months Base Yr PTR OM&S
FFP
Operations, Maintenance, and Support (OM&S) at Dare County Range, NC;
Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) Primary Training Ranges (PTR) for the hours listed in Table 1-2 of the SOW.
Services to be performed as specified in the informational subCLINs that delineate the FFP OM&S cost for each range. Period of Performance, 1 Jan 13 to 31 Dec 13.
0004 10 Months Base Yr PTR OM&S
FFP
Operations, Maintenance, and Support (OM&S) at Grand Bay Range, GA Primary Training Range (PTR) for the hours listed in Table 1-2 of the SOW. Services to be performed as specified in the informational subCLIN that delineates the FFP OM&S cost for the range. Period of Performance, 1 Mar 13 to 31 Dec 13.
0005 9 Months OPTION Base Yr Opt'l RCO Holloman Ranges (AETC)
FFP
Option to provide qualified RCO services to control Class A Range Operations IAW AFI13-212 and the ACC Supplement at the Holloman Ranges, NM. Period of Performance, 1 Apr 13 to 31 Dec 13.
0006 12 Months OPTION Base Yr OPT - Avon Park OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Avon Park, FL B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 13 to 31 Dec 13.
0007 12 Months OPTION Base Yr OPT - Belle Fourche OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Belle Fourche ESS Range in Colony, WY for the hours listed in Table 1-2 of the SOW.
Period of Performance, 1 Jan 13 to 31 Dec 13.
0008 12 Months OPTION Base Yr OPT - Poinsett ECR OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC ECR Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 13 to 31 Dec 13.
0009 12 Months OPTION Base Yr OPT - Poinsett B&G OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 13 to 31 Dec 13.
0010 12 Months OPTION Base Yr OPT - Snyder ESS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Snyder, TX ESS Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 13 to 31 Dec 13.
0011 12 Months OPTION Base Yr OPT - RIIS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at the Range Integration and Instrumentation System, NV for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 13 to 31 Dec 13.
0012 Lot Base Yr Addt'l Operations Hours (AOH)
COST
In accordance with SOW Section C-1, Paragraph 1.4, the contractor shall furnish all personnel, supervision, and other items necessary to perform Range Operations for Additional Operations Hours (AOH) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) in addition to the hours listed in Table 1-2 of the SOW. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 13 to 31 Dec 13.
ESTIMATED COST
0013 Lot OPTION Base Yr OPT - Holloman Ranges AOH (AETC)
COST
Option to provide PTR AOH services (WITH RCO) as described in CLIN 0011 at the Holloman Ranges, NM. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee.
Period of Performance, 1 Jan 13 to 31 Dec 13.
0014 Lot OPTION Base Yr OPT - Avon Park AOH
COST
Option to provide PTR AOH services (Full Ops with an RCO) as described in CLIN 0011 at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 13 to 31 Dec 13.
0015 Lot OPTION Base Yr OPT - Avon Park AOH - RCO
COST
Option to provide RCO SERVICES ONLY for PTR AOH services at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 13 to 31 Dec 13.
0016 Lot OPTION Base Yr OPT - Belle Fourche AOH
COST
Option to provide PTR AOH services as described in CLIN 0011 at the Belle Fourche ESS Range in Colony, WY. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 13 to 31 Dec 13.
0017 Lot OPTION Base Yr OPT - Poinsett ECR AOH
COST
Option to provide PTR AOH services as described in CLIN 0011 at the Poinsett ECR, SC, including services at the Bulldog MOA, Ft. Gordon, GA. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 13 to 31 Dec 13.
0018 Lot OPTION Base Yr OPT - Poinsett B&G AOH
COST
Option to provide PTR AOH services as described in CLIN 0011 at the Poinsett, SC B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 13 to 31 Dec 13.
0019 Lot OPTION Base Yr OPT - Snyder AOH
COST
Option to provide PTR AOH services as described in CLIN 0011 at the Snyder ESS Range, TX. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 13 to 31 Dec 13.
0020 Lot OPTION Base Yr OPT - RIIS AOH
COST
Option to provide PTR AOH services as described in CLIN 0011 at the Range Integration and Instrumentation System, NV. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 13 to 31 Dec 13.
0021 Lot Base Yr Supplies, Parts, & Services
COST
Supplies, Parts, and Services. Cost will be on a REIMBURSABLE basis IAW the requirements, thresholds, and approvals stated in SOW Section C-2, Paragraph
2.11 and Table 2.1. Parts and Services provided IAW SOW Section C-2, Paragraph 2.12 and Computer Software and LAN System service agreements provided IAW SOW Section C-4, Chapter 2, Paragraph 4.1.10. NTE $520,000.00.
Burdened Handling Rate ______%. Period of Performance, 1 Jan 13 to 31 Dec 13.
0022 Lot Base Yr Fuel
COST
Purchase of petroleum, oil, lubricants (POL) fuels required to perform PTR OM&S under CLINs 0003-0011 and AOH services under CLIN 0012-0020 IAW SOW Section C-2, Paragraph 2.13. Costs are REIMBURSABLE. NTE $400,000.00. Period of Performance, 1 Jan 13 to 31 Dec 13.
0023 Lot Base Yr Travel
COST
Cost reimbursable travel, government directed and approved in support of PTR.
The Government will only reimburse allowable costs IAW FAR Part 31.205-46, Travel Costs. NTE $40,000.00. Burdened Handling Rate ______%. Period of Performance, 1 Jan 13 to 31 Dec 13.
0024 Lot Base Yr Ext'd Maintenance & Support
COST
In accordance with SOW Section C-1, Paragraph 1.7.7 - Government directed extended maintenance and support for activities within the general scope of the contract to meet SOW requirements, but above the basic work under the contract.
Contractor requires Program Manager approval before incurring costs. Cost will be on a REIMBURSABLE basis, exclusive of additional fee other than already included in the fully burdened labor rates. NTE $40,000.00. Period of Performance, 1 Jan 13 to 31 Dec 13.
1001 12 Months OPTION Opt Yr 1 Program Management
FFP
Program Management for OM&S IAW SOW paragraph 1.7. Section C-1 of the SOW and not specifically priced in other CLINs of this contract. Period of Performance, 1 Jan 14 to 31 Dec 14.
1002 12 Months OPTION Opt Yr 1 PTR OM&S
FFP
Operations, Maintenance, and Support (OM&S) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) Primary Training Ranges (PTR) for the hours listed in Table 1- 2 of the SOW. Services to be performed as specified in the informational subCLINs that delineate the FFP OM&S cost for each range. Period of Performance, 1 Jan 14 to 31 Dec 14.
1003 12 Months OPTION Opt Yr 1 Opt'l RCO Holloman Ranges(AETC)
FFP
Option to provide qualified RCO services to control Class A Range Operations IAW AFI13-212 and the ACC Supplement at the Holloman Ranges, NM. Period of Performance, 1 Jan 14 to 31 Dec 14.
1004 12 Months OPTION Opt Yr 1 OPT - Avon Park OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Avon Park, FL B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 14 to 31 Dec 14.
1005 12 Months OPTION Opt Yr 1 OPT - Belle Fourche OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Belle Fourche ESS Range in Colony, WY for the hours listed in Table 1-2 of the SOW.
Period of Performance, 1 Jan 14 to 31 Dec 14.
1006 12 Months OPTION Opt Yr 1 OPT - Poinsett ECR OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC ECR Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 14 to 31 Dec 14.
1007 12 Months OPTION Opt Yr 1 OPT - Poinsett B&G OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 14 to 31 Dec 14.
1008 12 Months OPTION Opt Yr 1 OPT - Snyder ESS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Snyder, TX ESS Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 14 to 31 Dec 14.
1009 12 Months OPTION Opt Yr 1 OPT - RIIS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at the Range Integration and Instrumentation System, NV for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 14 to 31 Dec 14.
1010 Lot OPTION Opt Yr 1 Addt'l Operations Hours (AOH)
COST
In accordance with SOW Section C-1, Paragraph 1.4, the contractor shall furnish all personnel, supervision, and other items necessary to perform Range Operations for Additional Operations Hours (AOH) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) in addition to the hours listed in Table 1-2 of the SOW. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 14 to 31 Dec 14.
1011 Lot OPTION Opt Yr 1 OPT-Holloman Ranges AOH (AETC)
COST
Option to provide PTR AOH services (WITH RCO) as described in CLIN 1010 at the Holloman Ranges, NM. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee.
Period of Performance, 1 Jan 14 to 31 Dec 14.
1012 Lot OPTION Opt Yr 1 OPT - Avon Park AOH
COST
Option to provide PTR AOH services as described in CLIN 1010 at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 14 to 31 Dec 14.
1013 Lot OPTION Opt Yr 1 OPT - Avon Park AOH - RCO
COST
Option to provide RCO SERVICES ONLY for PTR AOH services at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 14 to 31 Dec 14.
1014 Lot OPTION Opt Yr 1 OPT - Belle Fourche AOH
COST
Option to provide PTR AOH services as described in CLIN 1010 at the Belle Fourche ESS Range in Colony, WY. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 14 to 31 Dec 14.
1015 Lot OPTION Opt Yr 1 OPT - Poinsett ECR AOH
COST
Option to provide PTR AOH services as described in CLIN 1010 at the Poinsett ECR, SC, including services at the Bulldog MOA, Ft. Gordon, GA. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 14 to 31 Dec 14.
1016 Lot OPTION Opt Yr 1 OPT - Poinsett B&G AOH
COST
Option to provide PTR AOH services as described in CLIN 1010 at the Poinsett, SC B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 14 to 31 Dec 14.
1017 Lot OPTION Opt Yr 1 OPT - Snyder AOH
COST
Option to provide PTR AOH services as described in CLIN 1010 at the Snyder ESS Range, TX. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 14 to 31 Dec 14.
1018 Lot OPTION Opt Yr 1 OPT - RIIS AOH
COST
Option to provide PTR AOH services as described in CLIN 1010 at the Range Integration and Instrumentation System, NV. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 14 to 31 Dec 14.
1019 Lot OPTION Opt Yr 1 Supplies, Parts, and Services
COST
Supplies, Parts, and Services. Cost will be on a REIMBURSABLE basis IAW the requirements, thresholds, and approvals stated in SOW Section C-2, Paragraph
2.11 and Table 2.1. Parts and Services provided IAW SOW Section C-2, Paragraph 2.12 and Computer Software and LAN System service agreements provided IAW SOW Section C-4, Chapter 2, Paragraph 4.1.10. NTE $520,000.00. Burdened Handling Rate ______%. Period of Performance, 1 Jan 14 to 31 Dec 14.
1020 Lot OPTION Opt Yr 1 Fuel
COST
Purchase of petroleum, oil, lubricants (POL) fuels required to perform PTR OM&S under CLINs 1002-1009 and AOH services under CLINs 1010-1018 IAW SOW Section C-2, Paragraph 2.13. NTE $400,000.00. Period of Performance, 1 Jan 14 to 31 Dec 14.
1021 Lot OPTION Opt Yr 1 Travel
COST
Cost reimbursable travel, government directed and approved in support of PTR.
The Government will only reimburse allowable costs IAW FAR Part 31.205-46, Travel Costs. NTE $40,000.00. Burdened Handling Rate ______%. Period of Performance, 1 Jan 14 to 31 Dec 14.
1022 Lot OPTION Opt Yr 1 Extended Maintenance & Support
COST
In accordance with SOW Section C-1, Paragraph 1.7.7 - Government directed extended maintenance and support for activities within the general scope of the contract to meet SOW requirements, but above the basic work under the contract.
Contractor requires Program Manager approval before incurring costs. Cost will be on a REIMBURSABLE basis, exclusive of additional fee other than already included in the fully burdened labor rates. NTE $40,000.00. Period of Performance, 1 Jan 14 to 31 Dec 14.
2001 12 Months OPTION Opt Yr 2 Program Management
FFP
Program Management for OM&S IAW SOW paragraph 1.7. Section C-1 of the SOW and not specifically priced in other CLINs of this contract. Period of Performance, 1 Jan 15 to 31 Dec 15.
2002 12 Months OPTION Opt Yr 2 PTR OM&S
FFP
Operations, Maintenance, and Support (OM&S) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) Primary Training Ranges (PTR) for the hours listed in Table 1- 2 of the SOW. Services to be performed as specified in the informational subCLINs that delineate the FFP OM&S cost for each range. Period of Performance, 1 Jan 15 to 31 Dec 15.
2003 12 Months OPTION Opt Yr 2 Opt'l RCO Holloman Ranges(AETC)
FFP
Option to provide qualified RCO services to control Class A Range Operations IAW AFI13-212 and the ACC Supplement at the Holloman Ranges, NM. Period of Performance, 1 Jan 15 to 31 Dec 15.
2004 12 Months OPTION Opt Yr 2 OPT - Avon Park OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Avon Park, FL B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 15 to 31 Dec 15.
2005 12 Months OPTION Opt Yr 2 OPT - Belle Fourche OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Belle Fourche ESS Range in Colony, WY for the hours listed in Table 1-2 of the SOW.
Period of Performance, 1 Jan 15 to 31 Dec 15.
2006 12 Months OPTION Opt Yr 2 OPT - Poinsett ECR OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC ECR Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 15 to 31 Dec 15.
2007 12 Months OPTION Opt Yr 2 OPT - Poinsett B&G OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 15 to 31 Dec 15.
2008 12 Months OPTION Opt Yr 2 OPT - Snyder ESS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Snyder, TX ESS Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 15 to 31 Dec 15.
2009 12 Months OPTION Opt Yr 2 OPT - RIIS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at the Range Integration and Instrumentation System, NV for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 15 to 31 Dec 15.
2010 Lot OPTION Opt Yr 2 Addt'l Operations Hours (AOH)
COST
In accordance with SOW Section C-1, Paragraph 1.4, the contractor shall furnish all personnel, supervision, and other items necessary to perform Range Operations for Additional Operations Hours (AOH) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) in addition to the hours listed in Table 1-2 of the SOW. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 15 to 31 Dec 15.
2011 Lot OPTION Opt Yr 2 OPT-Holloman Ranges AOH (AETC)
COST
Option to provide PTR AOH services (WITH RCO) as described in CLIN 2010 at the Holloman Ranges, NM. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee.
Period of Performance, 1 Jan 15 to 31 Dec 15.
2012 Lot OPTION Opt Yr 2 OPT - Avon Park AOH
COST
Option to provide PTR AOH services as described in CLIN 2010 at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 15 to 31 Dec 15.
2013 Lot OPTION Opt Yr 2 OPT - Avon Park AOH - RCO
COST
Option to provide RCO SERVICES ONLY for PTR AOH services at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 15 to 31 Dec 15.
2014 Lot OPTION Opt Yr 2 OPT - Belle Fourche AOH
COST
Option to provide PTR AOH services as described in CLIN 2010 at the Belle Fourche ESS Range in Colony, WY. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 15 to 31 Dec 15.
2015 Lot OPTION Opt Yr 2 OPT - Poinsett ECR AOH
COST
Option to provide PTR AOH services as described in CLIN 2010 at the Poinsett ECR, SC, including services at the Bulldog MOA, Ft. Gordon, GA. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 15 to 31 Dec 15.
2016 Lot OPTION Opt Yr 2 OPT - Poinsett B&G AOH
COST
Option to provide PTR AOH services as described in CLIN 2010 at the Poinsett, SC B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 15 to 31 Dec 15.
2017 Lot OPTION Opt Yr 2 OPT - Snyder AOH
COST
Option to provide PTR AOH services as described in CLIN 2010 at the Snyder ESS Range, TX. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 15 to 31 Dec 15.
2018 Lot OPTION Opt Yr 2 OPT - RIIS AOH
COST
Option to provide PTR AOH services as described in CLIN 2010 at the Range Integration and Instrumentation System, NV. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 15 to 31 Dec 15.
2019 Lot OPTION Opt Yr 2 Supplies, Parts, and Services
COST
Supplies, Parts, and Services. Cost will be on a REIMBURSABLE basis IAW the requirements, thresholds, and approvals stated in SOW Section C-2, Paragraph
2.11 and Table 2.1. Parts and Services provided IAW SOW Section C-2, Paragraph 2.12 and Computer Software and LAN System service agreements provided IAW SOW Section C-4, Chapter 2, Paragraph 4.1.10. NTE $520,000.00. Burdened Handling Rate ______%. Period of Performance, 1 Jan 15 to 31 Dec 15.
2020 Lot OPTION Opt Yr 2 Fuel
COST
Purchase of petroleum, oil, lubricants (POL) fuels required to perform PTR OM&S under CLINs 2002-2009 and AOH services under CLINs 2010-2018 IAW SOW Section C-2, Paragraph 2.13. NTE $400,000.00. Period of Performance, 1 Jan 15 to 31 Dec 15.
2021 Lot OPTION Opt Yr 2 Travel
COST
Cost reimbursable travel, government directed and approved in support of PTR.
The Government will only reimburse allowable costs IAW FAR Part 31.205-46, Travel Costs. NTE $40,000.00. Burdened Handling Rate ______%. Period of Performance, 1 Jan 15 to 31 Dec 15.
2022 Lot OPTION Opt Yr 2 Extended Maintenance & Support
COST
In accordance with SOW Section C-1, Paragraph 1.7.7 - Government directed extended maintenance and support for activities within the general scope of the contract to meet SOW requirements, but above the basic work under the contract.
Contractor requires Program Manager approval before incurring costs. Cost will be on a REIMBURSABLE basis, exclusive of additional fee other than already included in the fully burdened labor rates. NTE $40,000.00. Period of Performance, 1 Jan 15 to 31 Dec 15.
3001 12 Months OPTION Opt Yr 3 Program Management
FFP
Program Management for OM&S IAW SOW paragraph 1.7. Section C-1 of the SOW and not specifically priced in other CLINs of this contract. Period of Performance, 1 Jan 16 to 31 Dec 16.
3002 12 Months OPTION Opt Yr 3 PTR OM&S
FFP
Operations, Maintenance, and Support (OM&S) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) Primary Training Ranges (PTR) for the hours listed in Table 1- 2 of the SOW. Services to be performed as specified in the informational subCLINs that delineate the FFP OM&S cost for each range. Period of Performance, 1 Jan 16 to 31 Dec 16.
3003 12 Months OPTION Opt Yr 3 Opt'l RCO Holloman Ranges(AETC)
FFP
Option to provide qualified RCO services to control Class A Range Operations IAW AFI13-212 and the ACC Supplement at the Holloman Ranges, NM. Period of Performance, 1 Jan 16 to 31 Dec 16.
3004 12 Months OPTION Opt Yr 3 OPT - Avon Park OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Avon Park, FL B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 16 to 31 Dec 16.
3005 12 Months OPTION Opt Yr 3 OPT - Belle Fourche OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Belle Fourche ESS Range in Colony, WY for the hours listed in Table 1-2 of the SOW.
Period of Performance, 1 Jan 16 to 31 Dec 16.
3006 12 Months OPTION Opt Yr 3 OPT - Poinsett ECR OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC ECR Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 16 to 31 Dec 16.
3007 12 Months OPTION Opt Yr 3 OPT - Poinsett B&G OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 16 to 31 Dec 16.
3008 12 Months OPTION Opt Yr 3 OPT - Snyder ESS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Snyder, TX ESS Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 16 to 31 Dec 16.
3009 12 Months OPTION Opt Yr 3 OPT - RIIS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at the Range Integration and Instrumentation System, NV for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 16 to 31 Dec 16.
3010 Lot OPTION Opt Yr 3 Addt'l Operations Hours (AOH)
COST
In accordance with SOW Section C-1, Paragraph 1.4, the contractor shall furnish all personnel, supervision, and other items necessary to perform Range Operations for Additional Operations Hours (AOH) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) in addition to the hours listed in Table 1-2 of the SOW. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 16 to 31 Dec 16.
3011 Lot OPTION Opt Yr 3 OPT-Holloman Ranges AOH (AETC)
COST
Option to provide PTR AOH services (WITH RCO) as described in CLIN 3010 at the Holloman Ranges, NM. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee.
Period of Performance, 1 Jan 16 to 31 Dec 16.
3012 Lot OPTION Opt Yr 3 OPT - Avon Park AOH
COST
Option to provide PTR AOH services as described in CLIN 3010 at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 16 to 31 Dec 16.
3013 Lot OPTION Opt Yr 3 OPT - Avon Park AOH - RCO
COST
Option to provide RCO SERVICES ONLY for PTR AOH services at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 16 to 31 Dec 16.
3014 Lot OPTION Opt Yr 3 OPT - Belle Fourche AOH
COST
Option to provide PTR AOH services as described in CLIN 3010 at the Belle Fourche ESS Range in Colony, WY. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 16 to 31 Dec 16.
3015 Lot OPTION Opt Yr 3 OPT - Poinsett ECR AOH
COST
Option to provide PTR AOH services as described in CLIN 3010 at the Poinsett ECR, SC, including services at the Bulldog MOA, Ft. Gordon, GA. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 16 to 31 Dec 16.
3016 Lot OPTION Opt Yr 3 OPT - Poinsett B&G AOH
COST
Option to provide PTR AOH services as described in CLIN 3010 at the Poinsett, SC B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 16 to 31 Dec 16.
3017 Lot OPTION Opt Yr 3 OPT - Snyder AOH
COST
Option to provide PTR AOH services as described in CLIN 3010 at the Snyder ESS Range, TX. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 16 to 31 Dec 16.
3018 Lot OPTION Opt Yr 3 OPT - RIIS AOH
COST
Option to provide PTR AOH services as described in CLIN 3010 at the Range Integration and Instrumentation System, NV. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 16 to 31 Dec 16.
3019 Lot OPTION Opt Yr 3 Supplies, Parts, and Services
COST
Supplies, Parts, and Services. Cost will be on a REIMBURSABLE basis IAW the requirements, thresholds, and approvals stated in SOW Section C-2, Paragraph
2.11 and Table 2.1. Parts and Services provided IAW SOW Section C-2, Paragraph 2.12 and Computer Software and LAN System service agreements provided IAW SOW Section C-4, Chapter 2, Paragraph 4.1.10. NTE $520,000.00. Burdened Handling Rate ______%. Period of Performance, 1 Jan 16 to 31 Dec 16.
3020 Lot OPTION Opt Yr 3 Fuel
COST
Purchase of petroleum, oil, lubricants (POL) fuels required to perform PTR OM&S under CLINs 3002-3009 and AOH services under CLINs 3010-3018 IAW SOW Section C-2, Paragraph 2.13. NTE $400,000.00. Period of Performance, 1 Jan 16 to 31 Dec 16.
3021 Lot OPTION Opt Yr 3 Travel
COST
Cost reimbursable travel, government directed and approved in support of PTR.
The Government will only reimburse allowable costs IAW FAR Part 31.205-46, Travel Costs. NTE $40,000.00. Burdened Handling Rate ______%. Period of Performance, 1 Jan 16 to 31 Dec 16.
3022 Lot OPTION Opt Yr 3 Extended Maintenance & Support
COST
In accordance with SOW Section C-1, Paragraph 1.7.7 - Government directed extended maintenance and support for activities within the general scope of the contract to meet SOW requirements, but above the basic work under the contract.
Contractor requires Program Manager approval before incurring costs. Cost will be on a REIMBURSABLE basis, exclusive of additional fee other than already included in the fully burdened labor rates. NTE $40,000.00. Period of Performance, 1 Jan 16 to 31 Dec 16.
4001 12 Months OPTION Opt Yr 4 Program Management
FFP
Program Management for OM&S IAW SOW paragraph 1.7. Section C-1 of the SOW and not specifically priced in other CLINs of this contract. Period of Performance, 1 Jan 17 to 31 Dec 17.
4002 12 Months OPTION Opt Yr 4 PTR OM&S
FFP
Operations, Maintenance, and Support (OM&S) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) Primary Training Ranges (PTR) for the hours listed in Table 1- 2 of the SOW. Services to be performed as specified in the informational subCLINs that delineate the FFP OM&S cost for each range. Period of Performance, 1 Jan 17 to 31 Dec 17.
4003 12 Months OPTION Opt Yr 4 Opt'l RCO Holloman Ranges(AETC)
FFP
Option to provide qualified RCO services to control Class A Range Operations IAW AFI13-212 and the ACC Supplement at the Holloman Ranges, NM. Period of Performance, 1 Jan 17 to 31 Dec 17.
4004 12 Months OPTION Opt Yr 4 OPT - Avon Park OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Avon Park, FL B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 17 to 31 Dec 17.
4005 12 Months OPTION Opt Yr 4 OPT - Belle Fourche OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Belle Fourche ESS Range in Colony, WY for the hours listed in Table 1-2 of the SOW.
Period of Performance, 1 Jan 17 to 31 Dec 17.
4006 12 Months OPTION Opt Yr 4 OPT - Poinsett ECR OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC ECR Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 17 to 31 Dec 17.
4007 12 Months OPTION Opt Yr 4 OPT - Poinsett B&G OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 17 to 31 Dec 17.
4008 12 Months OPTION Opt Yr 4 OPT - Snyder ESS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at Snyder, TX ESS Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 17 to 31 Dec 17.
4009 12 Months OPTION Opt Yr 4 OPT - RIIS OM&S
FFP
Option to provide Operations, Maintenance, and Support (OM&S) at the Range Integration and Instrumentation System, NV for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 17 to 31 Dec 17.
4010 Lot OPTION Opt Yr 4 Addt'l Operations Hours (AOH)
COST
In accordance with SOW Section C-1, Paragraph 1.4, the contractor shall furnish all personnel, supervision, and other items necessary to perform Range Operations for Additional Operations Hours (AOH) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) in addition to the hours listed in Table 1-2 of the SOW. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 17 to 31 Dec 17.
4011 Lot OPTION Opt Yr 4 OPT-Holloman Ranges AOH (AETC)
COST
Option to provide PTR AOH services (WITH RCO) as described in CLIN 4010 at the Holloman Ranges, NM. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee.
Period of Performance, 1 Jan 17 to 31 Dec 17.
4012 Lot OPTION Opt Yr 4 OPT - Avon Park AOH
COST
Option to provide PTR AOH services as described in CLIN 4010 at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 17 to 31 Dec 17.
4013 Lot OPTION Opt Yr 4 OPT - Avon Park AOH - RCO
COST
Option to provide RCO SERVICES ONLY for PTR AOH services at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 17 to 31 Dec 17.
4014 Lot OPTION Opt Yr 4 OPT - Belle Fourche AOH
COST
Option to provide PTR AOH services as described in CLIN 4010 at the Belle Fourche ESS Range in Colony, WY. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 17 to 31 Dec 17.
4015 Lot OPTION Opt Yr 4 OPT - Poinsett ECR AOH
COST
Option to provide PTR AOH services as described in CLIN 4010 at the Poinsett ECR, SC, including services at the Bulldog MOA, Ft. Gordon, GA. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 17 to 31 Dec 17.
4016 Lot OPTION Opt Yr 4 OPT - Poinsett B&G AOH
COST
Option to provide PTR AOH services as described in CLIN 4010 at the Poinsett, SC B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 17 to 31 Dec 17.
4017 Lot OPTION Opt Yr 4 OPT - Snyder AOH
COST
Option to provide PTR AOH services as described in CLIN 4010 at the Snyder ESS Range, TX. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 17 to 31 Dec 17.
4018 Lot OPTION Opt Yr 4 OPT - RIIS AOH
COST
Option to provide PTR AOH services as described in CLIN 4010 at the Range Integration and Instrumentation System, NV. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 17 to 31 Dec 17.
4019 Lot OPTION Opt Yr 4 Supplies, Parts, and Services
COST
Supplies, Parts, and Services. Cost will be on a REIMBURSABLE basis IAW the requirements, thresholds, and approvals stated in SOW Section C-2, Paragraph
2.11 and Table 2.1. Parts and Services provided IAW SOW Section C-2, Paragraph 2.12 and Computer Software and LAN System service agreements provided IAW SOW Section C-4, Chapter 2, Paragraph 4.1.10. NTE $520,000.00. Burdened Handling Rate ______%. Period of Performance, 1 Jan 17 to 31 Dec 17.
4020 Lot OPTION Opt Yr 4 Fuel
COST
Purchase of petroleum, oil, lubricants (POL) fuels required to perform PTR OM&S under CLINs 4002-4009 and AOH services under CLINs 4010-4018 IAW SOW Section C-2, Paragraph 2.13. NTE $400,000.00. Period of Performance, 1 Jan 17 to 31 Dec 17.
4021 Lot OPTION Opt Yr 4 Travel
COST
Cost reimbursable travel, government directed and approved in support of PTR.
The Government will only reimburse allowable costs IAW FAR Part 31.205-46, Travel Costs. NTE $40,000.00. Burdened Handling Rate ______%. Period of Performance, 1 Jan 17 to 31 Dec 17.
4022 Lot OPTION Opt Yr 4 Extended Maintenance & Support
COST
In accordance with SOW Section C-1, Paragraph 1.7.7 - Government directed extended maintenance and support for activities within the general scope of the contract to meet SOW requirements, but above the basic work under the contract.
Contractor requires Program Manager approval before incurring costs. Cost will be on a REIMBURSABLE basis, exclusive of additional fee other than already included in the fully burdened labor rates. NTE $40,000.00. Period of Performance, 1 Jan 17 to 31 Dec 17.
5001 6 Months OPTION 6 Mo. Ext. Program Management
FFP
Option to Extend Services IAW FAR 52.217-8 to provide Program Management for OM&S IAW SOW paragraph 1.7. Section C-1 of the SOW and not specifically priced in other CLINs of this contract. Period of Performance, 1 Jan 18 to 30 Jun 18.
5002 6 Months OPTION 6 Mo. Ext. PTR OM&S
FFP
Option to Extend Services IAW FAR 52.217-8 to provide Operations, Maintenance, and Support (OM&S) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) Primary Training Ranges (PTR) for the hours listed in Table 1-2 of the SOW.
Services to be performed as specified in the informational subCLINs that delineate the FFP OM&S cost for each range. Period of Performance, 1 Jan 18 to 30 Jun 18.
5003 6 Months OPTION 6 Mo. Ext. OPT RCO Holloman Ranges(AETC)
FFP
Option to Extend Services IAW FAR 52.217-8 to provide qualified RCO services to control Class A Range Operations IAW AFI13-212 and the ACC Supplement at the Holloman Ranges, NM. Period of Performance, 1 Jan 18 to 30 Jun 18.
5004 6 Months OPTION 6 Mo. Ext. - Avon Park OM&S
FFP
Option to Extend Services IAW FAR 52.217-8 to provide Operations, Maintenance, and Support (OM&S) at Avon Park, FL B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 18 to 30 Jun 18.
5005 6 Months OPTION 6 Mo. Ext. - Belle Fourche OM&S
FFP
Option to Extend Services IAW FAR 52.217-8 to provide Operations, Maintenance, and Support (OM&S) at Belle Fourche ESS Range in Colony, WY for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 18 to 30 Jun 18.
5006 6 Months OPTION 6 Mo. Ext. - Poinsett ECR OM&S
FFP
Option to Extend Services IAW FAR 52.217-8 to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC ECR Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 18 to 30 Jun 18.
5007 6 Months OPTION 6 Mo. Ext. - Poinsett B&G OM&S
FFP
Option to Extend Services IAW FAR 52.217-8 to provide Operations, Maintenance, and Support (OM&S) at Poinsett, SC B&G Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 18 to 30 Jun 18.
5008 6 Months OPTION 6 Mo. Ext. - Snyder ESS OM&S
FFP
Option to Extend Services IAW FAR 52.217-8 to provide Operations, Maintenance, and Support (OM&S) at Snyder, TX ESS Range for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 18 to 30 Jun 18.
5009 6 Months OPTION 6 Mo. Ext. - RIIS OM&S
FFP
Option to Extend Services IAW FAR 52.217-8 to provide Operations, Maintenance, and Support (OM&S) at the Range Integration and Instrumentation System, NV for the hours listed in Table 1-2 of the SOW. Period of Performance, 1 Jan 18 to 30 Jun 18.
5010 Lot OPTION 6 Mo. Ext Addt'l Operations Hours (AOH)
COST
Option to Extend Services IAW FAR 52.217-8. In accordance with SOW Section C-1, Paragraph 1.4, the contractor shall furnish all personnel, supervision, and other items necessary to perform Range Operations for Additional Operations Hours (AOH) at Grand Bay Range, GA; Dare County Range, NC; Mountain Home Ranges, ID; and Holloman Ranges, NM (WITHOUT RCO) in addition to the hours listed in Table 1-2 of the SOW. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 18 to 30 Jun 18.
5011 Lot OPTION 6 Mo. Ext. - Holloman Ranges AOH (AETC)
COST
Option to Extend Services IAW FAR 52.217-8 to provide PTR AOH services (WITH RCO) as described in CLIN 5010 at the Holloman Ranges, NM. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 18 to 30 Jun 18.
5012 Lot OPTION 6 Mo. Ext. - Avon Park AOH
COST
Option to Extend Services IAW FAR 52.217-8 to provide PTR AOH services as described in CLIN 5010 at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 18 to 30 Jun 18.
5013 Lot OPTION 6 Mo. Ext. - Avon Park AOH - RCO
COST
Option to Extend Services IAW FAR 52.217-8 to provide RCO SERVICES ONLY for PTR AOH services at the Avon Park, FL B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 18 to 30 Jun 18.
5014 Lot OPTION 6 Mo. Ext. - Belle Fourche AOH
COST
Option to Extend Services IAW FAR 52.217-8 to provide PTR AOH services as described in CLIN 5010 at the Belle Fourche ESS Range in Colony, WY. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 18 to 30 Jun 18.
5015 Lot OPTION 6 Mo. Ext. - Poinsett ECR AOH
COST
Option to Extend Services IAW FAR 52.217-8 to provide PTR AOH services as described in CLIN 5010 at the Poinsett ECR, SC, including services at the Bulldog MOA, Ft. Gordon, GA. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 18 to 30 Jun 18.
5016 Lot OPTION 6 Mo. Ext. - Poinsett B&G AOH
COST
Option to Extend Services IAW FAR 52.217-8 to provide PTR AOH services as described in CLIN 5010 at the Poinsett, SC B&G Range. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 18 to 30 Jun 18.
5017 Lot OPTION 6 Mo. Ext. - Snyder AOH
COST
Option to Extend Services IAW FAR 52.217-8 to provide PTR AOH services as described in CLIN 5010 at the Snyder ESS Range, TX. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 18 to 30 Jun 18.
5018 Lot OPTION 6 Mo. Ext. - RIIS AOH
COST
Option to Extend Services IAW FAR 52.217-8 to provide PTR AOH services as described in CLIN 5010 at the Range Integration and Instrumentation System, NV. Costs are REIMBURSABLE at the fully burdened hourly rate as negotiated for site operations, exclusive of any other additional fee. Period of Performance, 1 Jan 18 to 30 Jun 18.
5019 Lot OPTION 6 Mo. Ext. Supplies, Parts, and Services
COST
Option to Extend Services IAW FAR 52.217-8 to provide Supplies, Parts, and Services. Cost will be on a REIMBURSABLE basis IAW the requirements, thresholds, and approvals stated in SOW Section C-2, Paragraph 2.11 and Table
2.1. Parts and Services provided IAW SOW Section C-2, Paragraph 2.12 and Computer Software and LAN System service agreements provided IAW SOW Section C-4, Chapter 2,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .