Attachment 1 - SOW 20 May 2026.pdf
PDF 105 KB Posted
- Attached to
- RH - Base Course - AVON Park
- Solicitation number
- FA481426Q0010
About this file
This is a Statement of Work for the delivery and placement of Graded Crushed Aggregate Base Course (GCA) composed of crushed concrete at Avon Park Air Force Range in Florida.
The contractor must provide and deliver 16,410 tons of GCA as the base requirement (CLIN 0001), with an optional additional purchase of up to 1,000 tons (CLIN 0002). The material will be used for taxiway Hotel and the C-17 Assault strip, which must support Modified Heavy Aircraft operations. Deliveries must begin within 15 days after receipt of order and be completed no later than July 10, 2026, to 45 South Boulevard, Avon Park, FL 33825. The contractor must submit two items with its offer: Material Specifications Sheets with certified laboratory test results (LA Abrasion per ASTM C131/C121M, Gradation per ASTM C117, Compaction per ASTM D1557 Method C, Atterberg Limits per ASTM D4318, Clay Lumps per ASTM C142, and Flat/Elongated Particles per ASTM D4791) and a Logistics Plan confirming delivery by July 10, 2026. Pricing shall be provided on a per-ton basis for both CLINs.
Material must conform to UFGS 32.11.23 and consist of clean, sound, durable crushed stone or angular sand, free of silt and clay per ASTM D2487. Recycled Concrete Aggregate (RCA) is permitted if previously handled portland cement concrete with no reinforcing steel, bituminous surfacing, or foreign materials. The GCA must meet strict gradation limits with zero tolerance (1 inch: 100%, ½ inch: 40–70%, No. 4: 20–50%, No. 10: 15–40%, No. 40: 5–25%, No. 200: 0–8%), maximum Liquid Limit of 25 and Plasticity Index of 5 for material passing No. 40 sieve. The contractor is solely responsible for quality control testing every 2,500 tons delivered, with results submitted to the Contracting Officer and Contracting Officer's Representative within 24 hours. Field placement tolerances include grade within +¼ inch to -½ inch, smoothness within ±3/8 inches, total thickness within ±½ inches, average job thickness within ±¼ inches, and minimum 100% compaction of laboratory maximum density. Non-compliant materials will be rejected at no cost to the Government, and the contractor must remove and replace deficient material at its own expense. Additional performance requirements include submitting a Safety Plan, producing minimum 500-ton sub-lots in eight-hour periods, providing delivery/weight tickets and certified weight receipts for each vehicle, employing properly licensed English-speaking drivers with military installation access, and cleaning all debris or spills same-day. Final payment is processed upon Government acceptance of all tonnage, reconciliation of delivery tickets, and satisfactory work completion.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work: Graded Crushed Aggregate Base Course (Crushed Concrete)
Dated 20 May, 2026
Definitions
Term Definition
GCA Graded Crushed Aggregate Base Course (Crushed Concrete)
UFGS Uniform Guide Specifications
UFC Unified Facilities Criteria
AVPAFR Avon Park Air Force Range
CO Contracting Officer
COR Contracting Officer's Representative
ASTM American Society for Testing and Materials
RCA Recycled Concrete Aggregate
ARO After Receipt of Order
Referenced Documents
This section lists all documents referenced within this SOW. The contractor is responsible for obtaining and adhering to the latest versions of these documents.
• UFGS 32.11.23 - Graded Crushed Aggregate Base Course
• UFC 3-206-02 - Pavement Design for Airfields
• Avon Park Air Force Range (AVPAFR) Design Standards
• ASTM C131/C121M - Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine
• ASTM C117 - Standard Test Method for Materials Finer than 75-μm (No. 200) Sieve in Mineral Aggregates by Washing
• ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort
• ASTM D4318 - Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
• ASTM C142 - Standard Test Method for Clay Lumps and Friable Particles in Aggregates
• ASTM D4791 - Standard Test Method for Flat Particles, Elongated Particles, or Flat and Elongated Particles in Coarse Aggregate
• ASTM D2487 - Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
One (1) Design & Material Composition
The Contractor shall provide all plant, labor, material, design, and supervision to provide and deliver a base quantity of 16,410 tons of Graded Crushed Aggregate Base Course (GCA) (Crushed Concrete), with an optional quantity for up to 1,000 additional tons. The GCA will be used for taxiway Hotel and the C-17 Assault strip at Avon Park Florida Air Force Range, Avon Park, Florida. The Taxiway is Type A traffic area and will be required to support C-17 Operations. The C-17 Assault strip must support a Modified Heavy Aircraft as per UFC 3-206-02. The Contractor shall not commence work without prior coordination with the Contracting Officer, Project Inspector and Using Agency. GCA will conform to the Uniform Guide Specifications (UFGS) 32.11.23.
Material Composition Specifications:
• Base Composition: The material must consist of clean, sound, durable particles of crushed stone, angular sand, or other such approved materials.
• Silt/Clay Limit: The aggregate stock must be free of silt and clay as defined by ASTM D2487.
• Recycled Concrete Aggregate (RCA): Crushed Recycled Concrete Aggregate (RCA) is permitted for use.
• RCA must consist of previously handled portland cement concrete or other concrete containing pozzolanic binder material.
• RCA must be consistent with all gradation requirements defined in this
SOW.
• RCA must be completely free of all reinforcing steel, bituminous concrete surfacing (asphalt), and any other foreign or deleterious materials.
General Design Notes:
• Design shall be in strict accordance with Unified Facilities Criteria (UFC) and the Avon Park Air Force Range Design Standards. The information provided in this SOW and the requirements of the AVPAFR Design Standards shall be determined to be the minimum standards required in this project. Where the information provided and/or AVPAFR Design Standards conflict, then the most stringent shall be used.
• The Contractor shall notify the Contracting Officer in writing of any identified conflicts between design standards for resolution.
Two (2) Submittals Required with Offers
Offerors must submit the following information with their offers. Failure to provide this information may result in the offer being rejected:
1. Material Specifications Sheet(s): The submitted material specifications document must confirm and prove that the offered material is in accordance with (IAW) all specifications designated in this Statement of Work (SOW) utilizing Crushed Concrete/RCA. This includes, but is not limited to, certified laboratory test results confirming the GCA stock meets the following standards:
• L.A Abrasion Test: ASTM C131/C121M
• Gradation Analysis: ASTM C117
• Degree of Compaction: ASTM D1557 (Method C)
• Liquid Limit and Plasticity Index: ASTM D4318
• Clay Lumps and Friable Particles: ASTM C142
• Flat and Elongated Particles: ASTM D4791
2. Logistics Plan: A plan that confirms all materials can be delivered to the work site on or before 10 July, 2026.
Three (3) Work Requirements
The Contractor shall provide all plant, labor, material, design and supervision to provide and deliver GCA (Crushed Concrete).
3.1 Base Requirement (CLIN 0001)
The contractor shall provide a firm-fixed quantity of 16,410 Tons of GCA (Crushed Concrete) conforming to UFGS 32.11.23.
3.2 Optional Requirement (CLIN 0002)
The Government holds the option to purchase additional GCA (Crushed Concrete) up to a maximum of 1,000 additional tons. The exercise of this option is governed by FAR 52.217-7.
3.3 Delivery
• Schedule: Deliveries will start within 15 days After Receipt of Order (ARO) and must be completed No Later Than (NLT) 10 July, 2026.
• Execution: The Contractor shall deliver all GCA specified under CLIN 0001 and any quantities ordered under CLIN 0002 in pre-coordinated intervals, ensuring all materials are delivered on or before the 10 July deadline. Deliveries shall be made to 45 South BLVD, Avon Park, FL 33825.
• Documentation: A physical Delivery/Weight Ticket shall be provided with each delivery vehicle to the project inspector upon arrival.
3.4 Quality Control, Testing, and Compliance Thresholds
The Contractor is solely responsible for performing and securing quality control testing during the execution of this contract according to the following mandatory criteria:
• Mandatory Quality Control Tests: Gradation (ASTM C117), LA Abrasion (ASTM C131/C121M), and Atterberg Limits (ASTM D4318).
• Frequency of Testing: Every 2,500 tons delivered.
• Submission Method: All certified laboratory test results and reports shall be submitted directly to both the CO and COR via email within 24 hours of test completion.
• Atterberg Limits Limits: The maximum Liquid Limit (LL) of material passing through the No. 40 sieve is 25. The maximum Plasticity Index (PI) of material passing through the No. 40 sieve is 5.
Table 1: Mandatory Material Gradation Specifications (Pass/Fail)
The GCA material delivered to the site must strictly conform to the following gradation limits by weight. There is zero tolerance for deviation outside of these ranges:
Sieve Size Required Cumulative % Passing (By Weight)
1 inch 100%
½ inch 40% – 70%
No. 4 20% – 50%
No. 10 15% – 40%
No. 40 5% – 25%
No. 200 0% – 8%
Table 2: Mandatory Placement Compliance and Field Tolerances
Field placement, installation, and compaction of GCA on taxiway Hotel and the C-17 Assault strip must comply with the exact tolerances defined below.
• Non-Compliance and Remediation: Non-conforming materials will be rejected at no cost to the Government. If any material or finished surface is found to be non-compliant with the tolerances in Table 2, the Contractor shall, at their own expense, immediately remove the non-compliant material and replace it with fully compliant material to meet the requirements of this specification.
Property / Measurement
Mandatory Specification Limit
Allowable Field Tolerance
Grade Design Profile Grade +1/4 inch to -1/2 inch
Smoothness Design Surface Plane ±3/8 inches (Individual Test)
Total Thickness Nominal Design Thickness ±1/2 inches (Individual Core/Pit)
Average Job Thickness Total Job Surface Average ±1/4 inches
Compaction Laboratory Maximum Density
Minimum 100% (No negative tolerance)
3.5 Pricing Instructions
Offerors shall provide pricing on a per-unit (per ton) basis for both CLIN 0001 and CLIN 0002.
Four (4) Performance
• Payment & Reconciliation: Final payment processed upon Government acceptance of all 16,410 tons, reconciliation of all delivery/weight tickets, and satisfactory completion of work.
• Ticket Submission: Contractors will provide waybills and certified weight receipts for every vehicle moving GCA to the jobsite.
• Production: Contractor shall be able to produce a minimum sub-lot of 500 tons in an eight-hour period.
• Safety: Prior to work, the Contractor shall submit a comprehensive Safety Plan for review and approval.
• Drivers: Must be properly licensed, English-speaking, and legally allowed to enter a military installation with proper ID at all times.
• Site Maintenance: All debris or spills caused by the contractor must be cleaned off the same day.