Questions and Answers 1 Feb 11.docx

DOCX document 12 KB Posted

Attached to
Repair Lighting for Ammo Area
Solicitation number
FA4809-11-R-0002
Issued by

View the file

Other files

File Type Posted
Questions and answers 8 Feb 11.docx DOCX document
Questions and answers 4 Feb 11.docx DOCX document
Revised Drawing Sheet E-1.pdf PDF
Amendment 0001.doc DOC document
Site Visit.pdf PDF
11-R-0002.doc DOC document
Cover Sheet and Instructions.doc DOC document
Attachment 1 SPECIFICATIONS VKAG 10-1042E .doc DOC document
Attachment 7 Facility Inspection Assessment Letter.pdf PDF
Attachment 5 Sheet 2 of 2 KAG 10-1042E E-1.pdf PDF
Attachment 6 Construction Cost Estimate Breakdown.pdf PDF
Attachment 3 DOR.doc DOC document
Attachment 2 Wage Determination.docx DOCX document
Attachment 4 AF66 VKAG 10-1042E.pdf PDF
Attachment 5 Sheet 1 of 2 VKAG 10-1042E G-1.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4809-11-R-0002

Repair Lighting For Ammo Area

VKAG 10-1042E

Questions & Answers 1 Feb 2011

1. QUESTION: Will the potential prime contractors in the bid for the Repair Lighting for Ammo Area (FA4809-11-R-0002) solicitation be required to have the certifications if the sub that will perform the work has them? In other words, can the prime use the certifications of their sub to meet the technical certification requirements?

ANSWER: The prime does not have to hold the certification as long as all work is installed by appropriately licensed contractor as defined in contract specifications.

2. QUESTION: Would a potential prime contractor be penalized in the evaluation if they were not able to make the site visit, but their sub was there?

ANSWER: No consideration (negative or positive) is given for attendance to the site visit.