Answers_to_Questions.pdf

PDF 261 KB Posted

Attached to
Ellsworth Air Force Base- SABER
Solicitation number
FA4690-16-R-0007
Issued by

About this file

Answers to Questions

View the file

Other files

File Type Posted
FA4690-16-R-0007_SABER_Amend_0002.pdf PDF
Pre-Proposal_Conference_Minutes.pdf PDF
FA4690-16-R-0007_SABER_Amend_0001.pdf PDF
Attach_6_-__AFI_32-1062_Electrical_Systems _Power_Plants_and_Generators.pdf PDF
Attach_8_-_Material_Approval_Submittal.pdf PDF
Attach_22_-_Ellsworth_General_Contract_Administrative_Provisions_-_Jul_15.pdf PDF
Attach_20-_PPQ.pdf PDF
Attach_14_WD_-_SD35_-_Building-PENN_16_Sep_16.pdf PDF
Attach_18_-_Bid_Schedule.xlsx XLSX spreadsheet
Attach_3_-_Spec_Section_01800_Environmental_Provisions.pdf PDF
Attach_7_-_Ellsworth_AFB_Fire_Protection_Standards.pdf PDF
Attach_21-_Example_Sample_Project_Proposal_Redacted.pdf PDF
Attach_17_WD_-_SD6_-_Residential-MEADE_5_Aug_16.pdf PDF
FA4690-16-R-0007_Saber_Solicitation.pdf PDF
Attach_19-_Sample_Project_SOW.pdf PDF
Attach_4_-_EAFB_Design_Compatability_Standards.pdf PDF
Attach_11_-_Utility_Outages.pdf PDF
Attach_13_WD_-_SD33_-_Building-MEAD_16_Sep_16.pdf PDF
Attach_16_WD_-_SD2_-_Residential-PENN_8_Jan_16.pdf PDF
Attach_2_-_Spec_Section_01000_Ellsworth_AFB_Special_Provisions.pdf PDF
Attach_23_Determination_of_Resp.pdf PDF
Attach_12_-_Schedule_of_Materials_Submittal.xls XLS spreadsheet
Attach_9_-_EAFB_Exterior_Signs.pdf PDF
Attach_15_WD_-_SD1_-_Heavy_ _Highway-STATEWIDE_8_Jan_16.pdf PDF
Attach_1-_SABER_IDIQ_SOW.pdf PDF
Attach_5_-_Ellsworth_AFB_Underground_Electrical_Requirements.pdf PDF
Attach_10_-_AF_Form_103_Work__BCE_Clearance_Request.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

28TH CONTRACTING SQUADRON (AFGSC)

ELLSWORTH AIR FORCE BASE, SOUTH DAKOTA

Deter…Assure…Strike!

19 December 2016

Question 1: Will the sample project be awarded?

Answer 1: No. The sample project is intended to create a baseline of work. This project was already completed at another base. We have not purchased the software yet because we have given the Contractor the opportunity to determine the software they would like to utilze for this Contract.

Question 2: Does the Government want design services & costs included for the sample project?

Answer 2: Yes. The intent behind the project is to replicate the exact procedures to ensure everyone knows what the SABER contract will entail.

Question 3: The sample project SOW, Section 5: Drawings, requests that the drawings shall not exceed minimum design of 35% but also states the drawings shall conform to the standard specified in the SOW and EAFB design compatibility standards.

Minimum design would be exceeded if a typical general construction contractor would need to hire additional expertise in order to accomplish the design. Is the contractor able to provide a one line pdf drawing for the sample project to aid in the Government’s evaluation of the contractor’s proposal or will AutoCAD drawings be required?

Answer 3: Yes, a single line PDF, shop drawings, and standard designs available from internet sources would be adequate for the design. Please note that this can vary throughout the contract. There might be often situations where the government provides the designs or more detailed designs will be required from the contractor

(but not exceeding 35%).

Question 4: If AutoCAD is required can you provide both the AutoCAD and PDF’s as builds for the sample project?

Answer 4: It is not necessary for this sample project. However, if another project is more detailed, we would provide AutoCAD and PDF’s for the project.

DEPARTMENT OF THE AIR FORCE

28TH CONTRACTING SQUADRON (AFGSC)

ELLSWORTH AIR FORCE BASE, SOUTH DAKOTA

Deter…Assure…Strike!

Question 5: Will the contractor be responsible for the classroom setup, projector, whiteboard and computers for the onsite training or with the Government have this available for use?

Answer 5: No. The contractor will just have to coordinate with the SABER Chief or any CE

SABER representatives to ensure the classroom setup, projector, whiteboard and computers for the onsite training.

Question 6: SOW, 3.4.2, states that “The QCM under this contract cannot provide and execute the services of the CM or Project Superintendent.” Due to the duration and smaller scope of this SABER contract can the CM or Superintendent act as the

QCM?

Answer 6: Upon further review, we agree that the duration and smaller scope of this SABER contract does not require the QCM to be a different person. The CM or Project

Superintendent can act as the QCM.