Atch_17_-_Sample_Project_SOW.docx

DOCX document 21 KB Posted

Attached to
MACC-FOUR-POINT-OH - FA4690-15-R-0005, Solicitation
Solicitation number
FA4690-15-R-0005
Issued by

About this file

Atch 17 - Sample Project SOW

View the file

Other files

File Type Posted
FA4690-15-R-0005_Amend_0002.pdf PDF
Atch_18_-_Sample_Project_GIPR_-_19_Jan_16.docx DOCX document
Amend_2_-_Addl_Questions.docx DOCX document
Amend_1_-_Site_Visit_Minutes.pdf PDF
FA4690-15-R-0005_Amend_01_MACC-FOUR-POINT-OH.pdf PDF
Atch_18_-_Sample_Project_GIPR_-_13_Jan_16.docx DOCX document
Atch_16c_-_Wage_Determination_SD1-_Heavy-Highway_-_SD_-_9_Oct_15.docx DOCX document
Atch_15_Non-Nuclear_Intrusion_Detection_-_22_Sep_14.pdf PDF
Atch_18_-_Sample_Project_GIPR_-_1_Jun_15.docx DOCX document
Atch_20_-_Sample_Project_AF_Form_3052_-_1_Jun_15.xlsx XLSX spreadsheet
Atch_4_Sepc_Section_01000_-_20_Aug_15.doc DOC document
Atch_10__Electrical_Systems_-_15_Jan_15.pdf PDF
Atch_25_Pricing_Matrix_for_Evaluation_of_Options_-_17_Dec_15.xlsx XLSX spreadsheet
Atch_12_General_Provisions_-_10_Feb_15.doc DOC document
Atch_16e_-_Wage_Determination_SD35_-_Building_-_Penn_-_31_Jul_15.docx DOCX document
Atch_3_Submittal_Schedule_-_20_Aug_15.xls XLS spreadsheet
Atch_9_Material_Approval_Submittal_Form_3000_-_1_Sep_03.xfd —
Atch_8_Exterior_Signs_-_10_Jun_05.pdf PDF
Atch_14_Contractor_Guide_-_16_Jun_15.doc DOC document
Atch_1_Utility_Outages.doc DOC document
Atch_23_Historical_Data_-_21_Aug_2015.xls XLS spreadsheet
Atch_16a_-_Wage_Determination_SD2_-_Residential_-_Penn_-_2_Jan_15.docx DOCX document
Atch_21_1_of_3_Sample_Project_Drawing_-_1_Jun_15.pdf PDF
Atch_16d_-_Wage_Determination_SD33_-_Building_-_Mead_-_31_Jul_15.docx DOCX document
Atch_11_Ellsworth_AFB_Underground_Electrical_Rqmts_-_20_Aug_15.pdf PDF
Atch_22_Past_Performance_Questionnaire_-_25_Aug_15.doc DOC document
Atch_21_2_of_3_Sample_Project_Drawings_-_1_Jun_15.pdf PDF
Atch_21_3_of_3_Sample_Project_Drawing_-_1_Jun_15.pdf PDF
Atch_24_Determination_of_Responsibility_-_9_Dec_15.doc DOC document
Atch_17_-_Sample_Project_SOW_-_1_Jun_15.docx DOCX document
Atch_13_NAF_General_Provisions_-_21_Jan_2015.docx DOCX document
Atch_19_-_Sample_Project_Contractor_Bid_Sched_-_1_Jun_15.doc DOC document
Atch_16b_-_Wage_Determination_SD6_-_Residential_-_Mead_-_31_Jul_15.docx DOCX document
Atch_6_Design_Compatibility_Standards_-_20_Aug_15.pdf PDF
Atch_2_AF_Form_103_Work__BCE_Clearance_Request_-_1_Aug_94.xfdl XFDL file
Atch_7_Ellsworth_AFB_Fire_Protection_Standards_-_20_Aug_15.pdf PDF
Atch_21_2_of_3_Sample_Project_Drawings_-_1_Jun_15.pdf PDF
Atch_6_Design_Compatibility_Standards.pdf PDF
Atch_22_Past_Performance_Questionnaire_-_25_Aug_15.doc DOC document
Atch_24_Determination_of_Responsibility_-9_March_2012.doc DOC document
Atch_14_Contractor_Guide_-_16_Jun_15.doc DOC document
Atch_16c_-_Wage_Determination_SD1_-_Heavy_ _Highway_-_SD.docx DOCX document
Atch_16d_-_Wage_Determination_SD33_-_Building_-_Mead.docx DOCX document
Atch_2_AF_Form_103_Work__BCE_Clearance_Request.xfdl XFDL file
Atch_18_-_Sample_Project_GIPR_-_31_Jan_11.docx DOCX document
Atch_11_Ellsworth_AFB_Underground_Electrical_Rqmts.pdf PDF
Atch_21_3_of_3_Sample_Project_Drawing_-_1_Jun_15.pdf PDF
Atch_23_Historical_Data_-_21_Aug_2015.xls XLS spreadsheet
Atch_13_NAF_General_Provisions_-_21_Jan_2015.docx DOCX document
Atch_3_Submittal_Schedule.xls XLS spreadsheet
Show 40 more

Latest 50 of 65 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4690-15-R-0005

Attachment 17

SAMPLE PROJECT

Statement of Work Construct Storage & Restrooms - Facility 5025 Project # FXBM 01-1000 30 Oct 10

The contractor shall prepare a proposal to construct an addition on the east side of existing facility #5025. The addition shall be a combination storage facility and restrooms. Specific requirements are as follows:

1. 2500 square feet general, light duty storage (max 125 psf) open bay

a. Minimum 12’ clearance (headroom inside)

b. 2 - 12’ X 10’ high, insulated sectional overhead doors with electric operator (open close-stop functions mounted inside the building near the doors)

c. Overhead lighting per IES Lighting Handbook & outlets per NEC

d. Concrete floor with sealer and floor drain(s) connected to sanitary sewer.

e. Open, unfinished ceiling structure (shop prime finish).

f. Minimum, one 3’-0” X 6’-8” HM pedestrian door from exterior with closer and locking hardware.

g. L:W of floor area to be between 2:1 and 1:1

h. Driveway from existing Access Road to new OH doors (asphalt with concrete curb and gutter) for light duty truck traffic

i. No windows required

j. Unpainted CMU interior walls

2. Men’s and Women’s restrooms

a. Fixtures as required for 5 male and 3 female users

b. Heavy duty, low maintenance interior finishes (gyp board ceilings, 4’ceramic tile wainscot and painted gyp board above on walls, and ceramic tile floor)

c. Lighting per IES Lighting Handbook and outlets per NEC

d. Floor drains

e. Hardwood vanities, plastic laminate countertops, single lever faucets and vitreous china sinks.

f. Floor mounted, head rail braced , metal partitions if / where needed

3. General requirements

a. Masonry exterior to match existing facility

b. Heating system to be gas fired unit heaters for the open bay and electric base-board heaters for restrooms. Design temps to be 65 and 70 degrees respectively.

(1) Ventilation per ASHRAE Standard 62

(2) Heating calculations to include losses due to conduction, infiltration, and internal loads

c. Facility to be in compliance with ADA requirements

d. One 3’-0” X 6’-8” HM pedestrian door from existing facility into new addition with closer and locking hardware

e. Built-up-roof system to be used on new roofing

f. Fire protection / detection system per NFPA

g. Mechanical room to be accessible from building exterior only with vehicle parking nearby for repair personnel. (6'-0" X 6'-8" double access doors)

h. Fire alarm panel to be located in mechanical room (utilize Monaco BT-2 system)

i. No telephone service required

j. Utilize bar joists and metal decking roof structure

k. Install valves at water and gas service connections to mains

4. The following information is provided to assist the contractor in preparation of the proposal:

a. Roof live load shall be 30 psf. Roof design shall be in accordance with the requirements of ASCE Standard ANSI/ASCE 7-95, Section 6 (Wind Loads)

b. Assume soil bearing capacity to be 3,000 psf

c. Existing sanitary sewer (SS) is 12” diameter PVC with adequate additional capacity for the addition

d. Existing water main (W) is 6” diameter C-900 PVC with adequate additional capacity and pressure for the new requirements.

e. Existing gas line (G) is 2”PE with adequate additional capacity

f. Depth of water line is about 6’ below existing grade

g. Depth of gas line is about 3’ below existing grade

h. Existing SS manholes are 4’ diameter, pre-cast concrete with cast iron frames and lids

i. Existing electrical distribution panel has adequate additional capacity for the

addition. Panel is 280V/120V, 42 circuits with 225A main bus and 200A main
breaker. There are 20 available spaces. The panel is fed from within the supply
facility

j. Existing area between the Supply Facility and Base Road is unimproved with native grass cover

k. Water, gas, and sanitary sewer services must be connected to the existing lines in the open field. No connections within the existing supply facility are available

LOGISTICAL ISSUES

The existing facility will remain in use throughout the execution of this project and must be secure at all times when work is not taking place. As there is considerable local pedestrian traffic, the contractor must maintain safety fences and barricades as appropriate to keep the work area safe. The existing water, gas, and sewer lines cannot be isolated, therefore all connections must be made “live”. The electrical distribution panel can be shut down for a maximum of four hours, one day, to make new connections.