Atch_16c_-_Wage_Determination_SD1-_Heavy-Highway_-_SD_-_9_Oct_15.docx

DOCX document 28 KB Posted

Attached to
MACC-FOUR-POINT-OH - FA4690-15-R-0005, Solicitation
Solicitation number
FA4690-15-R-0005
Issued by

About this file

Atch 16c - Wage Determination SD1- Heavy-Highway - SD - 9 Oct 15

View the file

Other files

File Type Posted
FA4690-15-R-0005_Amend_0002.pdf PDF
Atch_18_-_Sample_Project_GIPR_-_19_Jan_16.docx DOCX document
Amend_2_-_Addl_Questions.docx DOCX document
Amend_1_-_Site_Visit_Minutes.pdf PDF
FA4690-15-R-0005_Amend_01_MACC-FOUR-POINT-OH.pdf PDF
Atch_18_-_Sample_Project_GIPR_-_13_Jan_16.docx DOCX document
Atch_15_Non-Nuclear_Intrusion_Detection_-_22_Sep_14.pdf PDF
Atch_18_-_Sample_Project_GIPR_-_1_Jun_15.docx DOCX document
Atch_20_-_Sample_Project_AF_Form_3052_-_1_Jun_15.xlsx XLSX spreadsheet
Atch_4_Sepc_Section_01000_-_20_Aug_15.doc DOC document
Atch_10__Electrical_Systems_-_15_Jan_15.pdf PDF
Atch_25_Pricing_Matrix_for_Evaluation_of_Options_-_17_Dec_15.xlsx XLSX spreadsheet
Atch_12_General_Provisions_-_10_Feb_15.doc DOC document
Atch_16e_-_Wage_Determination_SD35_-_Building_-_Penn_-_31_Jul_15.docx DOCX document
Atch_3_Submittal_Schedule_-_20_Aug_15.xls XLS spreadsheet
Atch_9_Material_Approval_Submittal_Form_3000_-_1_Sep_03.xfd —
Atch_8_Exterior_Signs_-_10_Jun_05.pdf PDF
Atch_14_Contractor_Guide_-_16_Jun_15.doc DOC document
Atch_1_Utility_Outages.doc DOC document
Atch_23_Historical_Data_-_21_Aug_2015.xls XLS spreadsheet
Atch_16a_-_Wage_Determination_SD2_-_Residential_-_Penn_-_2_Jan_15.docx DOCX document
Atch_21_1_of_3_Sample_Project_Drawing_-_1_Jun_15.pdf PDF
Atch_16d_-_Wage_Determination_SD33_-_Building_-_Mead_-_31_Jul_15.docx DOCX document
Atch_11_Ellsworth_AFB_Underground_Electrical_Rqmts_-_20_Aug_15.pdf PDF
Atch_22_Past_Performance_Questionnaire_-_25_Aug_15.doc DOC document
Atch_21_2_of_3_Sample_Project_Drawings_-_1_Jun_15.pdf PDF
Atch_21_3_of_3_Sample_Project_Drawing_-_1_Jun_15.pdf PDF
Atch_24_Determination_of_Responsibility_-_9_Dec_15.doc DOC document
Atch_17_-_Sample_Project_SOW_-_1_Jun_15.docx DOCX document
Atch_13_NAF_General_Provisions_-_21_Jan_2015.docx DOCX document
Atch_19_-_Sample_Project_Contractor_Bid_Sched_-_1_Jun_15.doc DOC document
Atch_16b_-_Wage_Determination_SD6_-_Residential_-_Mead_-_31_Jul_15.docx DOCX document
Atch_6_Design_Compatibility_Standards_-_20_Aug_15.pdf PDF
Atch_2_AF_Form_103_Work__BCE_Clearance_Request_-_1_Aug_94.xfdl XFDL file
Atch_7_Ellsworth_AFB_Fire_Protection_Standards_-_20_Aug_15.pdf PDF
Atch_21_2_of_3_Sample_Project_Drawings_-_1_Jun_15.pdf PDF
Atch_6_Design_Compatibility_Standards.pdf PDF
Atch_22_Past_Performance_Questionnaire_-_25_Aug_15.doc DOC document
Atch_24_Determination_of_Responsibility_-9_March_2012.doc DOC document
Atch_14_Contractor_Guide_-_16_Jun_15.doc DOC document
Atch_16c_-_Wage_Determination_SD1_-_Heavy_ _Highway_-_SD.docx DOCX document
Atch_16d_-_Wage_Determination_SD33_-_Building_-_Mead.docx DOCX document
Atch_2_AF_Form_103_Work__BCE_Clearance_Request.xfdl XFDL file
Atch_18_-_Sample_Project_GIPR_-_31_Jan_11.docx DOCX document
Atch_11_Ellsworth_AFB_Underground_Electrical_Rqmts.pdf PDF
Atch_21_3_of_3_Sample_Project_Drawing_-_1_Jun_15.pdf PDF
Atch_23_Historical_Data_-_21_Aug_2015.xls XLS spreadsheet
Atch_17_-_Sample_Project_SOW.docx DOCX document
Atch_13_NAF_General_Provisions_-_21_Jan_2015.docx DOCX document
Atch_3_Submittal_Schedule.xls XLS spreadsheet
Show 40 more

Latest 50 of 65 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4690-15-R-0005

Attachment 16c

General Decision Number: SD150001 10/09/2015 SD1

State: South Dakota

Construction Types: Heavy and Highway

Counties: South Dakota Statewide.

HEAVY AND HIGHWAY CONSTRUCTION PROJECTS

Note: Executive Order (EO) 13658 establishes an hourly minimum wage of $10.10 for 2015 that applies to all contracts subject to the Davis-Bacon Act for which the solicitation is issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.10 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 09/25/2015 1 10/09/2015

* SUSD2015-001 08/16/2015

Rates Fringes

CARPENTER........................$ 22.77 0.00

CONCRETE FINISHER................$ 21.41 0.00

ELECTRICIAN......................$ 22.79 0.00

LABORER

Group 1.....................$ 15.74 0.00 Group 2.....................$ 17.51 0.00 Group 3.....................$ 18.95 0.00 Group 5.....................$ 22.77 0.00 Group 6.....................$ 21.41 0.00

LABORER CLASSIFICATIONS:

GROUP 1: Air Tool Operator; Common Laborer; Landscape Worker, Flagger, Pilot Car Driver; Trucks under 26,000 GVW; Blue-top Checker, Materials Checker.

GROUP 2: Mechanic Tender; Pipe Layer (except culvert); Form Builder Tender; Special Surface Finish Applicator; Striping.

GROUP 3: Asphalt Plant Tender; Pile Driver Leadsman; Form Setter, Oiler/Greaser.

GROUP 5: Form Builder

GROUP 6: Grade Checker

PAINTER..........................$ 21.41 0.00

POWER EQUIPMENT OPERATOR:

Group 1.....................$ 16.85 0.00 Group 2.....................$ 18.13 0.00 Group 3.....................$ 19.89 0.00 Group 4.....................$ 20.30 0.00 Group 5.....................$ 22.75 0.00

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1: Concrete Paving Cure Machine; Concrete Paving Joint Sealer; Conveyor; Tractor (farm type with attachments); Self- Propelled Broom; Concrete Routing Machine; Paver Feeder;

Pugmill; Skid Steer.

GROUP 2: Bull Dozer 80 HP or less; Front End Loader 1.25 CY or less; Self-Propelled Roller (except Hot Mix); Sheepsfoot/50 Ton Pneumatic Roller; Pneumatic Tire Tractor or Crawler (includes Water Wagon and Power Spray Units); Wagon Drill; Air Trac; Truck Type Auger; Concrete Paving Saw.

GROUP 3: Asphalt Distributor; Bull Dozer over 80 HP; Concrete Paving Finishing Machine; Backhoes/Excavators 20 tons or less;

Crusher (may include internal screening plant); Front End Loader over 1.25 CY; Rough Motor Grader; Self-Propelled Hot Mix Roller; Push Tractor; Euclid or Dumpster; Material Spreader; Rumble Strip Machine.

GROUP 4:Asphalt Paving Machine Screed; Asphalt Paving Machine;

Cranes/Derricks/Draglines/Pile Drivers/Shovels 30 to 50 tons;

Backhoes/Excavators 21 to 40 tons; Maintenance Mechanic;

Scrapers; Concrete Pump Truck.

GROUP 5:Asphalt Plant; Concrete Batch Plant;

Backhoes/Excavators over 40 tons;

Cranes/Derricks/Draglines/Pile Drivers/Shovels over 50 tons;

Heavy Duty Mechanic; Finish Motor Grader; Automatic Fine Grader; Milling Machine; Bridge Welder.

TRUCK DRIVER

Group 1.....................$ 16.57 0.00 Group 2.....................$ 18.82 0.00

TRUCK DRIVERS CLASSIFICATIONS

GROUP 1: Tandem Truck without trailer or pup; Single Axle Truck over 26,000 GVW with trailer.

GROUP 2: Semi-Tractor and Trailer; Tandem Truck with Pup.

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION