Q and A Carpet_Asbestos_Furniture.pdf
PDF 163 KB Posted
- Attached to
- Asbestos, Carpet, and Furniture removal
- Solicitation number
- FA468625Q0006
About this file
This is a Questions and Answers (Q&A) document dated January 30, 2025 and February 3, 2025 for solicitation FA468625Q0006 regarding carpet replacement, asbestos abatement, and furniture moving services. The Q&A reveals this is a brand-new requirement with no incumbent contractor.
Key details addressed include: clarification that FAR 52.219-14 limitations on subcontracting applies only to section (c)(e)(1); confirmation that the Law office will be closed during carpet replacement and asbestos abatement work; requirement for contractors to reference PWS paragraph 2.1.1.1 for approved government sources, carpet specifications, and Tier 1 contractor list; and instructions for site visit requirements referencing Attachments 3 (Site Visit Information) and 4 (EAL Template). Floor plans are provided in Attachment 5. Question 3 regarding previous asbestos reports appears to be unanswered in the document.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS (Q&A) dated 30 January 2025
Carpet, Asbestos, Furniture Move
SOLICITATION NO. FA468625Q0006
Question 1: We would like to know if this is a brand-new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current / previous contract number?
Answer 1: Yes, this is a brand-new requirement.
Question 2: We have a question regarding the 52.219-14, Limitations on Subcontracting (Oct 2022) (15 U.S.C. 657s) clause, will this limitation be applied to Services, General construction, or Special trade construction contractors?
Answer 2: This clause applies only to FAR 52.219-14(c)(e)(1).
QUESTIONS AND ANSWERS (Q&A) dated 3 February 2025
Question 3: Could you provide previous asbestos reports.
Answer 3:
Question 4: A Floor Plan would help expedite the measuring process. Also, is the Law Office shutting down or moving operations to another Location?
Answer 4: The Law office will be closed during the carpet replacement and asbestos abatement.
Reference attachment 5 for Floor Plan.
Question 5: Can you process my request or do I need to give them my personal information?
Answer 5: Please refer to the last statement in the combo, reference Attachment 3 - Site Visit Information and complete Attachment 4 - EAL Template.
Question 6: We will need Carpet Stile, Nap not just Color. Also, are there sources available that are approved? We will need an approved Vendor or is this direct purchase from Government Sources?
Please supply the Tier 1 contacts list.
Answer 6: Yes, there are government sources that are approved, reference PWS paragraph 2.1.1.1 for ordering procedures . The Teir 1 Contractor list, Carpet style, and color is referenced in table outlined in paragraph 2.1.1.1. of the PWS.
File details come from the government source that posted it. Updated .