Q and A Carpet_Asbestos_ Furniture 1 - 11 Feb 25.pdf
PDF 112 KB Posted
- Attached to
- Asbestos, Carpet, and Furniture removal
- Solicitation number
- FA468625Q0006
About this file
This is a Questions and Answers (Q&A) document dated February 11, 2025, for solicitation FA468625Q0006 regarding carpet, asbestos, and furniture moving services.
The document contains a single question and answer exchange where a contractor inquires about the permissibility of using a phased approach to furniture moving during carpet removal and installation. The contractor proposes moving furniture to one side of the building while completing work on the other side, then switching, rather than requiring external storage. The government confirms this phased approach is permissible, allowing contractors to avoid the need for off-site storage while maintaining project progress.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS (Q&A) dated 11 February 2025
Carpet, Asbestos, Furniture Move
SOLICITATION NO. FA468625Q0006
Question 1: I would like to clarify whether it would be acceptable to move furniture to one side of the building, complete the carpet removal and installation on that section, and then move the furniture back while completing the second half. This phased approach would eliminate the need for external storage while ensuring continued progress on the project.
Can you confirm whether this method is permissible, or is full removal and off-site storage required before any work begins?
Answer 1: Yes, this method is permissible.