Attachment 13_March BOS Phase Out Plan 20181130-DC.pdf
PDF 332 KB Posted
- Attached to
- Base Operations Support Services March ARB Federal contract opportunity
- Solicitation number
- FA4664-20-R-9999
About this file
This document contains a phase out plan and related federal contract opportunity. The phase out plan outlines Onvoi Global Services' (OGS) approach for transitioning base operations and support services at March Air Reserve Base in California to a successor contractor over a proposed 30-day period. Key details include transitioning personnel, conducting inventories of government furnished equipment, providing training and briefings to the new contractor, and fully transferring responsibility for services by January 31st.
The related federal contract opportunity is a short-term sole source solicitation for interim base operations support services at March Air Reserve Base from January 1st to December 31st, 2020. The fixed-price contract with some cost-reimbursable line items is sought through a limited competition among five incumbent contractors due to an urgent need. Services required include general base operations and support functions.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Operations and Support Services (BOS) at March ARB, CA
Contract # FA4664-19-C-0001
Phase Out Plan
1931 US Highway 90 West
DeFuniak Springs, FL 32433
POC: Darryl Centanni
Darryl.centanni@ogsvc.com
Cell: 805-312-3274 mailto:Darryl.centanni@ogsvc.com
November 2018 i
Table of Contents Introduction
Background
Authority
Scope
Phase Out Objective
Phase Out Plan Guidance
OGS Management Phase Out Responsibilities
30 Day Phase Out plan
Phase Out Plan Roles and Responsibilities
Phase Out Meetings
Summary
Appendix 1
Table of Figures
1) 30 Day Phase Out Plan
2) Phase Out Plan Roles and Responsibilities
November 2018 1
INTRODUCTION
ONVOI Global Services (OGS) provides consistently successful performance that is on-cost, on-time, and defect free. OGS works as a close-knit team using analytical tools, techniques, and processes that enable predictable, repeatable performance. The internal structure of team work, processes, and procedures are very well-defined and visible, allowing for continuous internal process improvement. Quality is an essential element of all work assignments for OGS and will be maintained throughout any contract phase-out/transitional period.
Our Phase Out Plan ensures continuity of high-quality services and low risk to our customers by providing a structured, methodical process to transfer contract requirements from OGS to a successor contractor.
OGS has determined at a minimum a 30-day Phase Out Period is required to accomplish a successful, disruption free transition of contract responsibility to a successor contract team
BACKGROUND
March ARB Base Operations and Support PWS requires the contractor to develop and submit to the Government a Phase Out Plan. This plan details the overall approach to maintaining quality performance throughout the duration of contract performance from OGS to a successor contractor.
This plan documents how the OGS intends to transition service delivery requirements in a timely, responsible manner that will preclude disruption of services to the customer. This plan is a communication vehicle for the entire March BOS Team (Contract/Project Manager, Supervisors, Workforce).
AUTHORITY
This is a dynamic document to be used by the employees of OGS supporting this contract and updated as required. This document shall be reviewed by OGS Management at least annually.
SCOPE
This plan includes processes and procedures to follow for identifying areas to be addressed during the phase-out period. Included in our plan is a robust list of key items that will be thoroughly addressed with the successor contractor and guidance for our employees and any applicable subcontractors to follow. The key elements of this plan include:
• Management responsibilities
• Inventories and inspections
• Deficiency identification and reporting
• Record keeping systems
• Periodic reports
PHASE OUT OBJECTIVE
The objective of our Phase Out Plan is to provide a seamless transition of contract responsibilities from OGS to a successor contractor and to eliminate service disruption during the transition period.
Our goal is to fully comply with and exceed the quality requirements of the PWS during the transition period. To accomplish this objective, we will ensure that we continue to measure the performance of our employees to verify that we are meeting PWS requirements while we simultaneously indoctrinate, train and transition the new contracting firm. We pledge to communicate to all of our personnel the meaning of the objectives and how each person helps to
November 2018 2 achieve them. We will evaluate the need for changes to our Phase Out Plan as the situation requires.
OGS will designate an on-site Phase Out Plan Coordinator who will direct our Phase-Out effort.
Our Phase-Out Plan coordinator will be supported by OGS’ VP of operations.
PHASE OUT PLAN GUIDANCE
This Phase Out Plan provides guidance on the transition of BOS services from OGS to a successor contractor:
Award
Notification
Phase Out
Team
Assembly
Phase Out
Plan Review and Update if
Necessary
Brief
Government and
Incorporate
Changes
Brief
Successor
Commence
Transition of
Services
OGS MANAGEMENT PHASE OUT RESPONSIBILITIES
OGS management will monitor, track and assist if required during Phase Out Plan execution.
When each Tab area turnover objectives, appendix 1, have been completed they will be checked off the master Phase-Out check list and signed by the OGS Phase-Out Coordinator, On-site Project
Manager and successor contractor representative to signify that the new contract holder acknowledges they are ready to assume responsibility for that Tab’s functions on the agreed upon contract start date.
30 DAY PHASE OUT PLAN
30 Day Phase Out Plan Task Responsibility Status
Contract Award Notification 12/15/2019 Gov
Start Transition 3-Jan
Exec Management
Form Transition Out Team 16-Dec
Exec Management
Daily Phase-Out team mtg 3-Jan PMO
Review/Revise Phase-Out Plan 17-Dec PMO
Attend Pre-performance mtg if requested TBD Exec
Management
Provide incumbent employee personnel list 17-Dec HR
Meet with successor contractor leadership 15 Jan Exec
Management
Provide personnel resumes if requested N/A HR
Post notice with new contractor contact info 5-Jan HR
Brief Phase Out Plan to Tab Managers 18-Dec PMO
Meet with COR's to Brief Phase Out Plan 18-Dec PMO
Incorporate Phase Out Plan changes 18-Dec PMO
Initiate GFE Inventory with Gov 15-Jan PMO
November 2018 3
Prepare termination notices 18-Jan HR
Attend/Assist with Environmental Site Survey 18-Jan PMO
Provide list of vacant positions 18-Jan HR
Supply Personnel brief/tour/GFE inventory 19-Jan PMO
Airfield Mgmt Personnel brief/tour/GFE inventory N/A PMO
VOM Personnel brief/tour/GFE inventory 20-Jan PMO
RPM Personnel brief/tour/GFE inventory 22-Jan PMO
Fuels Personnel brief/tour/GFE inventory 24-Jan PMO
TMO Personnel brief/tour/GFE inventory 26-Jan PMO
Receive copy of complete inventory turnover signed by GOV 27-Jan PMO
Meet with Union Leadership 27-Jan PMO
Meet with Union Stewards 27-Jan PMO
Complete Transition of Incumbent Personnel 27-Jan HR
Release cleared peronnel in JPAS 27-Jan FSO
Assist with Coordinating CAC Issuance/collection 3-Jan FSO
Transfer property 31-Jan PMO/GOV
Transfer keys 31-Jan PMO/GOV
Transfer Training Records/Certs/License/Qualification info 31-Jan PMO
Transfer work order processing responsibility 15-Jan PMO
Sell OGS property no longer needed 15-Jan PMO
Ship retainable OGS property to desired location 16-Jan PMO
Prepare employee final pay 31-Jan Accounting
Submit final invoices to Gov 31-Jan Accounting
Submit final payment to Union 31-Jan Accounting
Terminate insurances 31-Jan Accounting
Terminate agreements 31-Jan Exec
Management
1) 30 Day Phase Out Plan
PHASE OUT PLAN ROLES AND RESPONSIBILITIES
Roles and Responsibilities of Personnel for Phase out Plan
Phase Out Plan Coordinator Reports to: OGS Senior Management
• Provide corporate level oversight for the Phase Out Plan
• Report to OGS senior management regarding Customer Satisfaction
• Report to OGS senior management regarding status
• Provide advice and assistance, as requested, regarding Phase Out Plan
November 2018 4
Roles and Responsibilities of Personnel for Phase out Plan
• Submit changes to the Phase Out Plan to the Contracting Officer for review and approval
• Develop and execute Phase Out Plan on predetermined timeline
• Verifies completion of Phase Out Plan milestones
Phase Out Team Reports to: Phase Out Plan Coordinator
• Establish and maintain a quality driven Phase Out Plan
• Monitors Phase Out status on a daily basis
• Discusses Phase out status with Phase Out Coordinator
• Responsibility for maintaining Customer Satisfaction during Phase Out
• Report Phase Out status to Phase Out Coordinator
• Ensure Phase Out Plan maintains Schedule of Events
• Prepare changes to The Phase Out Plan if necessary
• Maintains and files QC documentation and reports
• Verify that corrective actions have been implemented and documented
• Review the results of all QC inspections or audits performed
• Perform site trend analysis for non-conforming work
• Provide quality recommendations to the Quality Manager
• Participate in audits, inspections, surveillance activities to document performance
Workforce Personnel Reports to: Contract Manager/QCI
• Perform work in accordance with contract specifications and technical directives
• Participate in audits, inspections, surveillance activities to document performance in accordance with the entire PWS
• Provide detailed information/indoctrination and training to new contractor on job/function requirements
2) Phase Out Plan Roles and Responsibilities
PHASE OUT MEETINGS
The Phase Out Coordinator will meet daily with the phase out team to update transition status and address/resolve any questions or concerns. This meeting will be used to update the master schedule and brief OGS Executive Leadership on transition progress.
SUMMARY
This Phase Out Plan is a dynamic document that sets the basic standards to ensure an orderly, disruption free transition of services from OGS to a successor contractor within a prescribed time period. OGS’s Transition Team, Tab Managers, Supervisors, and workforce at March ARB will work diligently with all Government and successor contractor personnel to ensure full compliance
November 2018 5 and continuity of all contract requirements is maintained during the contract transition period. This
Phase Out Plan will be revised as needed.
APPENDIX 1
November 2018 1
Date:
To: Tab ___ COR
Subj: Tab ___ transition/turnover acknowledgement
IAW Onvoi Phase Out Plan I have completed the below items for Tab ___
1. Tab Manager Brief ___________ (date completed)
2. Tour of all Tab spaces and machinery items___________ (date completed)
3. Completed inventory of all Tab ___ GFE ___________ (date completed)
4. Reviewed applicable Tab Service Delivery Summary Items ___________ (date completed)
5. Indoctrinated on all required reports ___________ (date completed)
Successor Contractor
OGS Tab Manager
OGS Phase Out Coordinator