This final request for proposal is for a multiple award construction contract indefinite delivery indefinite quantity contract at Dyess Air Force Base. Offerors must prepare and submit proposals in accordance with the instructions in the solicitation. Proposals will be evaluated based on technical factors, past performance, and price. The government will provide existing as-built drawings upon award. Interested parties must review amendments and the statement of work for any changes. Proposals are due on May 5, 2020. The government will conduct an optional site visit on April 17 and registration is due by April 9. Questions asked during the pre-solicitation period are attached. The air force reserves the right to cancel the solicitation before or after closing.

View the file

Other files

File Type Posted
Amendment FA466120R00010005 SF 30.pdf PDF
6 Pricing Worksheet (SOW att G).xlsx XLSX spreadsheet
2 MACC solicitation sections L and M.docx DOCX document
SOW Addendum One - 6030 MACC 13-0068.pdf PDF
1 MACC solicitation sections F-H.docx DOCX document
4 Seed Project SOW Bldg 6030 v5.pdf PDF
Amendment FA466120R00010005 SF 30.pdf PDF
0 Solicitation FA466120R0001.pdf PDF
Amendment FA466120R00010004 SF 30.pdf PDF
FA4661-20-R-0001-0004 Attachment 1 Site Visit MFR.pdf PDF
FA466120R00010003 Attachment 1 (Site Visit MFR).pdf PDF
Amendment FA466120R00010003 SF 30.pdf PDF
Amendment FA466120R00010002 SF 30.pdf PDF
12 Question Submission Form v3.doc DOC document
Amendment FA466120R00010001 SF 30.pdf PDF
4 Seed Project SOW Bldg 6030 v4.pdf PDF
12 Question Submission Form v2.doc DOC document
10 Subcontractor Consent Form.doc DOC document
Pre-Solicitation notice - Questions and Answers.pdf PDF
6 Pricing Worksheet (SOW att G).xlsx XLSX spreadsheet
8 PPQ.pdf PDF
11 Site Visit Registration Form.doc DOC document
2 MACC solicitation sections L and M.docx DOCX document
4 Seed Project SOW Bldg 6030 v3.pdf PDF
9 Financial Reference Sheet.docx DOCX document
3 MACC Blanket Special Conditions.pdf PDF
7 FACTS Sheet.docx DOCX document
12 Question Submission Form.doc DOC document
0 Solicitation - FA466120R0001.pdf PDF
5 Wage Determination 1 Apr.pdf PDF
1 MACC solicitation sections F-H.docx DOCX document
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

7TH CONTRACTING SQUADRON (AFGSC)

DYESS AIR FORCE BASE TEXAS

DEATH FROM ABOVE

15 May 2020

MEMORANDUM FOR RECORD

FROM: 7 CONS/PKA

SUBJECT: Questions and Answers – beta.SAM.gov Solicitation Notice FA4661-20-R-0001 Dyess AFB Multiple Award Construction Contract (MACC)

The purpose of this memorandum for record is to answer the questions received in response to the posting of the solicitation documents and site visit (In-person and Virtual) for the Dyess AFB MACC. Interested parties were allowed to submit questions or suggestions until May 1, 2020.

The following questions were received:

Question #1 (Section L – Para 4.1) The paragraph 4.1. PART 1 – TECHNICAL PROPOSAL: States “Limited to no more than 40 pages as defined in para 6.1. Remark: We have submitted many of these and if there was only one Plan i.e. and overall management and work plan for the MACC it could be made to fit 40 pages but this requirement includes essentially 2 Management / Work plans one for the overall MACC Sub Factor 1 and Subfactor 2 Seed Project Work performance plan. QUESTION: can the page limitation for this Volume be increased to 60 pages??

Answer The page limit has been increased to 50 pages to accommodate all subfactors of the Technical Volume.

Question #2 (Section L, Part III – Price Proposal – Para 4.3.1) There is reference to an “original copy” of the SF1442 that should be “clearly marked under a separate cover.” Please provide clarification:

If an offeror submits their proposal via email using an electronic signature on the SF1442, is the offeror also required to send a hardcopy original (wet signature) to the government by mail, no later than the due date and time? Or is the emailed “original copy” sufficient?

Answer The email marked “Original Copy” is sufficient with an official electronic dated signature.

Question #3 (Section L, Part II -Past Performance and Section M – Section L Para 4.2.2.3 and Section M Para 2.3.2.2) Section L, para 4.2.2.3 states that a maximum of 5 different “contracts and/or task/delivery orders” can be provided. Please provide clarification:

1) Is an IDIQ contract (e.g., MACC, MATOC, SABER, JOC, etc.) an acceptable type of contract to submit for Past Performance, or is the requirement that each “contract” must be an individual project (e.g., stand-alone project, task order, delivery order, etc.)?

2) Section 2.3.2.2 of Section M states that each contract must have a minimum contract dollar value of $1,000,000. If IDIQ contracts can be submitted for the Past Performance factor, please clarify whether this minimum contract value requirement is for individual task/delivery orders awarded under the IDIQ, or if it can be for a combination of task/delivery orders awarded under the IDIQ.

Answer

1) IDIQ contracts are acceptable as long as it meets the recent/relevant criteria. In addition, you may provide individual task/delivery orders that meets the recent/relevant criteria.

2) Minimum contract value is met at contract or individual task/delivery order value. A combination of task/delivery orders in order to meet minimum contract value is not acceptable.

Question #4 (Section L Part II Past Performance – Section L Para 4.2.2.3) Reference Section 4.2.2.3: “Offerors shall provide information for a maximum of five (5) different contracts and/or task/delivery orders for which they have served as the prime contractor, a subcontractor, a partner or a Joint venture partner that are recent and relevant…”.

Question: If an Offeror includes contracts for which it had served as a Joint Venture partner, how will that Joint Venture experience be weighted in the evaluation? Will projects for which the Offeror was the sole prime contractor be given more weight than projects for which the Offeror was a Joint Venture partner?

Answer Past performance is not weighted. As per section M, paragraph 2.3.1, each Offeror will receive a performance confidence rating.

Question #5 (Section L – Para 6.1) The RFP states: *A redacted copy constitutes of a copy of your proposal with all company “information” and logos concealed. Want to confirm, so we meet the requirements of redacting correctly, that we are to change our company name to say “Our Company” while yet still providing you our company information?

Answer A redacted copy of the proposal has no company name, logos or information that would elude to your company specifically on it.

Question #6 (Section L – Para 6.6) Want to confirm that if we email our proposal that the Bid Bond is the only document we need to mail in separately by due date/time?

Answer As stated in Section L, Paragraph 6.6, the distribution of the Offerors bid must be delivered to the address provided or emailed by the date/time specified.

Question #7 (Section M – Para 2.2.1.1.1 & 2.2.4.1.2) Please clarify if you are wanting resumes in both Sub-factor 1 and Sub-factor 4?

Answer Yes.

Question #8 (General Conditions) Is the work at Dyess AFB, Texas exempt from sales and use taxes? In not tax exempt, What is the sales tax rate and any special use tax requirements?

Answer

This is a Government contract and is exempt from sales tax.

Question #9 (Section L – Para 4.1.4) Subfactor 4 – Seed Project Quality Control/Safety Plan and Certifications. Offerors are to provide a plan and certification and due to 40-page limitation offerors would have to condense company QC and Safety plans that are 200-300 pages down to 5-10 pages to allow for other Sub Factors to be discussed.

Question – Can QC and Safety plans be separate attachments for Subfactor 4 without page limitations?

Answer No, the QC and Safety plans are part to the total page count for Volume I, Technical. The total page limit is now 50 pages. Subfactor 4 requests summary plans; a finalized, more detailed Quality Control and Safety Plan may be required to be submitted and approved after contract award IAW the Statement of Work.

Question #10 (Section L – Para 4.2.3) The RFP calls for Past Performance Questionnaires (PPQs) to be sent to those agencies responsible for the administration of the identified projects in the FACTS Sheets. Due to the current COV-19 situation and the fact that many government agencies are working remotely, would the government allow Past Performance to be addressed using previously submitted materials, such as a previously completed PPQ, rather than having to reach out to past clients through email and potentially spotty communications for a new process? For example, our firm has received previous Past Performance evaluations for one of our feature projects on a different form.

Answer No. Previously submitted PPQs will not be accepted.

Question #11 The Cybersecurity Maturity Model Certification (CMMC) is scheduled to be implemented later this fall. Given the current COVID-19 situation and the inherent delays it will cause, will there be a requirement to comply with the CMMC certification during the course of this contract?

Answer At this time the CMMC is not mandatory and future requirements are not known.

Question #12 (Section L – Para 6.6) We intend to email our proposal following the instructions in the RFP, adhering to the specified email size limitation. Due to the impacts of the COVID-19 situation, some of our government customers have been experiencing a delay in receiving information via email and other electronic means (e.g., AMRDEC SAFE). In some instances, the agencies have not confirmed receipt until much later than the information was transmitted. This raises some concern with regards to receipt of our proposal submission, even if the proposal is emailed hours before the time it is due. The RFP states that “It is the contractor’s responsibility to ensure all emails were received”. What method would the government prefer contractors use to ensure timely receipt of their proposal?

The method for contractors to ensure timely receipt of their proposal is the contractor’s option.

If you choose to email your proposal “It is the contractor’s responsibility to ensure all emails were received.”

Question #13 (Section L/52.228-1 – Para 7.3) If emailing the proposal, are offerors also required to send a hardcopy original of the bid guarantee for receipt by 7CONS/PKA no later than the proposal due date and time?

Answer It is up to the Offeror how they are going to submit their bid. There is no requirement to submit a separate bid guarantee outside of your proposal package.

Question #14 (Section L – Para 4.2.2.4 and 6.1) Instructions for Attachment 10, Subcontractor Consent Form, are provided in Section L, Part II - Past Performance, para 4.2.2.4. However, the form is listed in Table 1, Proposal Organization, as a required item to be included in Part III, Price and Administrative Documents. Please confirm that the Subcontractor Consent Form should be included in proposal Part III rather than along with the past performance information in Part II.

Answer Attachment 10 is a “Subcontractor consent form for the release of past and present performance information to the prime contractor” and should be included in the proposal Part II for Past Performance. Proposal Organization table has been corrected to include this attachment in Volume II.

Question #15 (Attachment 6 – Pricing Worksheet) Under place for date it says:

Note: Due no later than 2 hours after official bid time Please clarify if this is correct and if so, how would that work?

Answer This has been removed, pricing worksheets shall be submitted by the due date/time included in the proposal.

Question #16 (FACTS Sheet) Fact Sheet, Question H States “For each of the applicable sub-factors under the Technical factor in Section M, illustrate how your experience on this program applies to that sub-factor.”

Since the fact sheet is for past performance should offerors illustrate how their experience applies to the Past Performance factor (recent and relevant) instead of the technical factors (Project Management Plan, Seed Project Performance Plan, Seed Project Work Schedule, and Seed Project Quality Control Plan)?

Answer The FACTS sheet is for past performance, question H is establishing how well you have performed in respect to the technical factors of this solicitation.

Question #17 (PPQs) Considering the current unprecedented conditions and restrictions imposed by the COVID-19 crisis, many government personnel are much more difficult to reach and more overloaded with critical priorities and have (when we can reach them) refused to fill out PPQ’s for projects they have already done so for. Will the government consider accepting previously completed PPQ’s for this factor?

Answer No, previously completed PPQs will be accepted.

Question #18 (PPQs) Given that most CPAR evaluations are geared toward the performance of the prime contractor and usually does not speak of the performance of the designer of record, will the government accept previously completed PPQ evaluations for the DOR performance even when a CPAR exists? If so, will this evaluation be given the same or more consideration than the CPAR evaluation?

Answer No, previously completed PPQs will be accepted.

Question #19 (General Conditions) What are the electricity rates (generation, transmission, distribution and delivery charges) for Dyess AFB?

Answer For the purpose of life cycle cost analysis, use $0.07/kWh.

Question #20 (Base Pricing Item 2) There are a lot of cubicle desk that will need to be disassembled to be moved out, when moved back, do we need to re-assembly them for re-use?

Answer If furniture is disassembled for removal and storage, reassembly would be required upon reinstallation.

Question #21 (Section L – Para 4.2.2) Section L, paragraph 4.2.2 states “A FACTS Sheet is provided with the solicitation for Offerors to send to a maximum of five (5) references/projects of their choice.” While we understand that our references need to complete and submit the PPQ, Attachment 8, directly back to the government, it is unclear why we need to “send” the FACTS Sheets to our references since we will be completing the entirety of the document. Can you confirm that offerors are only required to send the PPQ, Attachment 8, to project references?

Answer Corrected Para 4.2.2 to “A FACTS Sheet is provided with the solicitation for Offerors to send a maximum of five (5) references/projects of their choice”. FACTS Sheets are to be submitted in your proposal and doesn’t have to be submitted to project references.

Question #22 (Section L – Para 4.3.2) Section L, paragraph 4.3.2 provides directions for completing the Pricing Worksheet (Attachment 6) but also references “ The total price proposed on the Offer Schedule is the price that shall be honored by the Offeror who is awarded the resultant task order.” Is the Pricing Worksheet (Attachment 6) also considered to be the Offer Schedule? If not, can you please provide additional direction on what should be completed to satisfy the Offer Schedule requirement?

The pricing schedule is included in the Statement of Work Attachment G, these are your totals for the pricing worksheet (Attachment 6) shows a breakdown of your offer. Both must be completed and submitted in Volume III of the proposal.

Question #23 (Section L – Para 4.3.3) Section L, paragraph 4.3.3 requires the completion of fill-in and certifications in Section F through K; however, Table 1 provided under Section L, paragraph 6.1 (page 5) does not clearly indicate where these documents should be included within Volume III. Should these pages be included under an additional Tab (e.g. Tab 4)?

Answer Added new Tab to Proposal Organization Table. Place in Volume III, Tab 4: Fill in sheets from Section F-K.

Question #24 (Section L – Para 7.3) Section L, paragraph 7.3 requires bonding capacity documents according to FAR 52.228-1.

Based on the response to Question #15, it seems that a bid guarantee is required for the Seed Project. Since offerors are allowed to submit proposals electronically, is it acceptable to submit a digital scan of the bid guarantee? If not, please provide direction on submission of the original bid bond in hard copy to include the timeline for submission after the proposal due date. In other words, will offerors be allowed to submit the original bid bond within two business days of proposal submission?

Answer It is up to the Offeror how they are going to submit their bid. There is no requirement to submit a separate bid guarantee outside of your proposal package. All documents must be submitted on time, prior to proposal closing date and time.

Question #25 (Section L – Para 6.2.1) Section L, paragraph 6.2.1 requires pages to be numbered sequentially by volume. Please confirm that documents excluded from the page limitation (e.g., cover pages, table of contents, etc.) should still be numbered sequentially with the required contents of each volume?

Answer As per Section L, Paragraph 6.3, Cover page, Table of Content, List of Table or Figure, and the List of Appendices are not included in the page count and do not need to be numbered.

Question #26 (Section L/M – Para 4.1.4) Section L, paragraph 4.1.4 shows the title of Subfactor 4 as “Seed Project Quality Control/Safety Plan and Certifications.” However, Section M, paragraph 2.2.4 only references the Quality Control Plan and not Safety Plan and Certifications in the title of Subfactor 4. Based on the Measure of Merit listed in paragraph 2.2.4.1, please confirm that offerors are not required to provide Safety Plan and Certification information to receive an Acceptable rating for Subfactor 4.

Answer Subfactor 4 in Section M has been corrected to match Section L, additional information has been provided in L and M to clarify information requested.

Question #27 (Section L, Instructions, Conditions, and Notices to Offerors, page 5, 6.

Proposal Organization/Limits/Distribution, Table 1 Proposal Organization, Volume III Price and Administrative Documents: Tab 1 Pricing Worksheet) Are we to complete the form with our numbers and data and then safe to a pdf so it can be combined into the Volume III PDF for electronic submission or do we Send the Excel form itself as a separate attachment since an excel cannot be combined into a PDF bundle without converting it to PDF?

Answer The Pricing Worksheet must be submitted in Excel as provided. The excel worksheet maybe be a separate attachment since it cannot be combined with other PDF documents.

Question #28 (SOW Page 3, Section 4, Para 4) Are only NEW interior walls to be STC-55, or are all interior and exterior walls to be updated to meet STC-55?

Answer No, it is not possible to achieve STC-55 on interior walls framed with 3-5/8” framing at 16” o.c.

It is the Government’s intent to maximize available STC using 5/8” Gyp Bd, sound attenuation batt insulation, acoustic sealant at top and bottom of gyp bd to floor and deck, each side. Also stagger wall penetrations so only there is one penetration per stud cavity. Ensure all partitions extend to ceiling. Acoustic baffles would not be required for most wall penetrations.

Question #29 (SOW Page 4, Section 8.6.1) Please advise if RF filters are required. If so, please provide perimeter wall locations.

Answer RF Shielded areas will not be recertified in this facility. RF Filters would not be required.

Question #30 (SOW Page 3, Section 4, Para 4) What is the STC requirement for the exterior windows on the first and second floor of Bldg.

6030A?

Answer STC requirements woud only be relevant for new window installation. Existing windows to remain would not need to be modified.

Question #31 (SOW Page 3, Section 4, Para 4) Is there any STC requirements in the vestibule between building 6030A and 6030B?

Answer SOW 4.4 sets minimum STC ratings for NEW walls. SOW 4.5.29 provides requirements for existing wall, floor and ceiling openings. SOW 4.5.14 provides requirements for existing exterior wall insulation.

Question #32 (Drawing 5) Please confirm that no scope is required in the connecting corridor between Bldg. 6030A and 6030C?

With the exception of designing and constructing a new entrance to 6030C, which will affect the connecting corridor, the SOW makes no references to new work in the connecting corridor.

Question #33 (SOW Page 5, Section 4, Para 5.14) Please confirm if the exterior wall insulation is required for all exterior walls of Bldg. 6030A, 6030A 2nd floor, 6030c?

Answer All exterior walls are to receive additional exterior wall insulation, as required by SOW 4.5.14.

Question #34 (SOW Page 18, Section 9, Para 3) SOW asks to reduce slope of the concrete walkway connector between Bldg. 6030A and 6030C.

Is this scope in relation to the ramp outside of the south end of the enclosed connecting corridor or is the enclosed connecting corridors foundation sloped and the foundation slope needs to be reduced? Please clarify scope?

Answer The concrete walkway referenced is part of the new entance at the east end of the 6030A-6030C connector. Refer to SOW 3.1.2

Question #35 (SOW Page 11, Section 6) Please confirm if DDC system is required for the existing mechanical system that is remaining in Bldg. 6030C?

Answer A BACNet DDCS is required for complete HVAC System Control and monitoring of the HVAC equipment and utilities. The Existing Siemens BACNet system should be adequate; and expanded as necessary to provide control and monitoring of any new equipment.

Question #36 (SOW) Please confirm is Commissioning is required and if so, for what systems?

Answer Refer to Addenddum 1 for spec section 23 08 00 Commissioning. See also SOW spec section 23 09 23.

Question #37 (SOW) Please confirm if Commissioning and TAB is required for one or both of the mechanical systems in Bldg. 6030A and 6030C?

Answer Both Commissioning and TAB are required for the mechanical systems in 6030A and 6030C.

Question #38 (SOW Page 5, Section 4, Para 5.14) If exterior insulation is to be placed on interior side of exterior wall, is the government’s intent for it to be a continuous envelope? This would be an issue with the many existing interior partitions that tie into exterior wall.

Answer It is not possible to create a continuous envelope without extensive demolition. The intention of the added insulation is to provide a higher level of energy efficiency to an older building, to reduce energy usage in general. The added insulation will be broken up by the “Z” furring channels and any existing interior partitions scheduled to remain. We are attempting to improve the existing condition.

Question #39 (SOW) Please confirm if there are any air barrier requirements for this project?

Answer Not sure in what context the term “air barriers” is being used. But don’t know of any special needs for any type of barrier unless intended to be used during construction.

Question #40 (SOW Page 15, Section 8, Para 6.1) Please confirm if the intent is to have Main Electrical Room shared with Mechanical Room on the first floor of Bldg. 6030A?

Answer The existing Electrical and Mechanical Rooms are shared spaces in most facilities at Dyess. The Mechanical Room in 6030A will be expanded; and the Service Entrance and Distribution Panels will be relocated in that Room for better access and to meet NFPA required clearances.

Question #41 (SOW) Please confirm location of CPT Area and its function?

Answer CPT area is the Cockpit Procedures Training area in 6030A on the first floor where the cockpit simulators are.

Question #42 (SOW Page 16, Section 6, Para 8.2) For bidding purposes, how many outlets does the government estimate need new circuits as a result of nuisance tripping issues in Bldg. 6030C?

Answer The revised furniture plan will require reconfiguration of the receptacles for desktop equipment.

The using organization will provide a list of existing and/or proposed new electronic equipment that should include electrical requirements.

Question #43 (SOW Page 20, Section 11, Para 3) For bidding purposes, how many data drops does the end user anticipate according to the conceptual furniture plan provided by the government?

Answer The revised furniture plan will require reconfiguration of the receptacles for desktop equipment.

The using organization will provide a list of existing and/or proposed new electronic equipment that should include electrical requirements.

Question #44 (SOW Page 20, Section 11, Para 5) SOW mentions providing Access Control System and Intrusion Detection System rough-ins in Room 100 for duress buttons within a secure space. Can the government indicate where Room 100 is and where the secure space is located and its perimeter?

Answer There is to be a new egress door installed in the NE corner of the CPT area o the first floor of 6030A. This new door is the only door that should require access control and IDS with Duress buttons.

Question #45 (SOW Page 20, Section 11, Para 5) Can the government define the meaning of secure space as mentioned above?

Answer Secure Space generally refers to a room that is certified to secure and store classified information.

Question #46 (SOW Page 20, Section 11, Para 5) Can the government provide rough-in requirements for the selected Electronic Security System?

Answer Generally, there is a j-box adjacent to the door strike in the wall, one above the door, one in the ceiling near the center of the space, conduit with pull-string provided to all three locations, as well as from the ceiling jbox to the security system’s control panel, usually mounted in a remote location. However, I know of no reason that the existing Monaco Intrusion Detection System would not be adequate, be recommissioned, and be reused.

Question #47 (SOW Page 3, Section 4, Para 4) SOW mentions all interior walls to be STC-55. Is there any STC requirements for the floor/ceiling assemblies between the first and second floor of Bldg. 6030A?

Answer STC ratings shall apply only in areas of new construction, unless noted otherwise.

Question #48 (SOW Page 4, Section 21.1) It is indicated furrings on existing walls are to be designed for an STC of 55 or greater. Can the assumed STC rating of the exiting wall to be furred be inclusive of the furring rating to make a composite STC of 55 or greater?

Answer No, it is not possible to achieve STC-55 on interior walls framed with 3-5/8” framing at 16” o.c.

It is the Government’s intent to maximize available STC using 5/8” Gyp Bd, sound attenuation batt insulation, acoustic sealant at top and bottom of gyp bd to floor and deck, each side. Locate, detail, & stagger duct & conduit penetrations, outlet boxes, & intersections to reduce transfer of sound. Contractor shall infill existing openings to limit the transfer of sound. Ensure all partitions extend to ceiling. Acoustic baffles would not be required for most wall penetrations.

Question #49 (SOW Page 4, Section 21.1) Should not "UFC 3-101-01 CH5 Architecture" be a referenced Criteria?

Answer Yes, UFC 3-101-01, most recent edition, should be included in referenced criteria, Dyess AFB may have local changes that modify the UFC.

Question #50 (SOW) Please advise if RF shielding is required?

Answer No new RF shielding is anticipated. I know there is shielding in 6030B and believe there is existing shielding in 6030A that should appear on original construction drawings. I don’t think there are any additional requirements. But this is a question for the users.

Question #51 (SOW) Please advise if the design needs to meet ICD 705 design requirements?

Answer Areas within the facility will need to conform to ICD/ICS705 requirements.

Question #52 (SOW) Please provide the amount of comm networks to each desk?

Answer The revised furniture plan will require reconfiguration of the receptacles for desktop equipment.

The using organization will provide a list of existing and/or proposed new electronic equipment that should include electrical requirements.

Question #53 (SOW) Please provide the equipment heat loads for the occupants.

Answer The number of occupants can be be provided to us by the users. The occupant heat load should be based on sedentary working operations in the facility.

Question #54 (SOW) Please advise if the building has a secure perimeter?

Answer Yes, specific areas within the building will have secure perimeters.

Question #55 (SOW Page 4, Section 4.5.21) Please provide quantities for the self-leveling cementitious topping needed?

Answer Refer to SOW.

Question #56 (SOW Page 4, Section 6 of 11) The drawings show several folding partitions. Please advise on the STC rating for the partitions.

Answer UFC 3-101-01 specifies STC ratings for partitions in secure areas to meet the requirements of

ICD/ICS 705.

Question #57 (SOW Page 4, Section 6 of 11) The drawings show several folding partitions. Please advise if these are overhead partitions and if structural support steel is required?

Answer This will be determined by the folding partition selected. Refer to manufatcurer’s recommendations and structural engineer of record’s calculated requirements. The folding partition must meet ICD/ICS 705 requirements.

Question #58 (SOW Page 4, Section 11.3) Please provide networks and where they will be running so cable tray quality and length can be determined.

Answer The layout of the existing communications cabling should be investigated as part of the Design Build Survey. The functional operations and communications requirements should not change.

Question #59 (SOW Page 4, Section 11.2 & 11.4) Section 11.2 states “full IT/Telecomm design package” however, 11.4 states “Provide pull string for all conduits and rough-ins.” - where design is not needed but coordinated with the end user.

Please advise if the contractor needs to provide design?

Answer If I understand this question properly, there will likely be raceways with pull strings required for unspecified or future use. The size and routing will be provided by the using organization; and should require no design other than layout and presentation on the design drawings.

Question #60 (Attachment 8 Page 1) If Offeror has been issued a CPARS, CCASS, ACASS evaluation is the offeror required to submit a PPQ. The government will not fill out a PPQ if they have already provided an evaluation.

Answer The Government may but is not required to pull all CPARS, CCASS, ACASS evaluations. In accordance with Section L Para 4.2.3 the Offeror shall submit PPQs to those agencies responsible for the administration of the identified project in the FACTS Sheet.

Question #61 (SOW Page 18, Section 9, Para 4) Please advise a count and location of portable fire extinguishers that the Dyess AFB Fire Department shall request for pricing purposes.

Answer Fire extinguishers shall meet the quantities required by NFPA 101, IBC, and any applicable UFC. Refer to SOW 9.1. New carbon dioxide portable fire extinguishers and cabinets with minimum rating of 10B:C were provided as required in the computer area and other areas of the facility. The number and locations of the portable fire extinguishers can be found on drawings for FNWZ 10-0095.

Question #62 Drawing Sheet 4 of 11 shows the vault door to remain, please confirm. If replaced, please provide pricing information.

Answer Correct, vault door is to remain.

Question #63 (SOW, Section 6) On Sheet 6 of Attachment 4 of the RFP: The Existing Heritage Room in our opinion is an assembly area < 300 occupants and is more than 10%of the building area is a mixed-use occupancy. The occupant load for this room (@ 15 sq. ft. per person) is 81. This would require 2 exits more than the one half the diagonal of the room and doors to swing in the direction of travel. Will the conceptual drawings be modified to show compliance with the NFPA/ICC code?

Answer This is a design build project, concept drawings are just that… conceptual. Any modifications required as a result of the code analysis must be made to ensure compliance to the building code and life safety. The concept drawings will not be modified, but the changes will be reflected in the design documents provided by the designer of record.

Question #64 (SOW, Section 6) On Sheet 6 of Attachment 4 of the RFP: The Existing Heritage Room if the Government confirms it is a mixed occupancy, will it require a one-hour separation. In the as-built drawings this area was not a meeting room but a Contractors Office. Will this require the DB Contractor to upgrade the walls to an one hour fire assembly?

Answer The DB contractor is required to ensure final product meets all applicable building codes, UFCs, etc.

Question #65 (SOW, Section 6) On Sheet 6 of Attachment 4 of the RFP: The Existing Heritage Room has an existing Bar. Can the Government confirm that the existing Bar is ABA compliant? If not provide detailed drawings so appropriate modifications can be made and priced for this RFP.

Answer The bar is not included in renovation work, and not required to be modified.

Question #66 (SOW, Para 1.0) General: If the this is a comprehensive description of the project requirements etc. If corrections are made during design to comply with criteria that is illustrated differently in the SoW and associated drawings will the contractor be able to ask for an RFP from the government to correct SoW requirements to comply with the criteria?

Answer If the Contracting Officer (CO) determines a change to the contract needs to be made, then the CO would issue an RFP.

Question #67 (SOW Page 3, Para 4.4) "New gypsum board walls & furring on existing walls shall be designed with a Sound Transmission Class (STC) 55 or higher rating. Locate, detail, & stagger duct & conduit penetrations, outlet boxes, & intersections to reduce transfer of sound. Contractor shall infill existing openings to limit the transfer of sound." Some new walls & furrings that are indicated in the SoW Drawings are in/or bounding toilet areas. Is it the intent to have those walls meet an STC of 55? This could have a detrimental effect on the cost. Please identify those partitions that require this level of sound isolation. This also appears to be in conflict with drawing number 6 and 7, General Notes 2. that states "NEW WALLS TO MATCH EXISTING WALLS

CONSTRUCTION WHICH IS 3-5/8" (MIN.) METAL STUDS AT 16" O.C. WITH 5/8"

GYPSUM BOARD ON BOTH SIDES, PAINTED DB CONTRACTOR TO VERIFY FIRE

RATINGS AND REQUIRED WALL ASSEMBLY, INCLUDING DOOR AND DOOR

HARDWARE ASSEMBLY AND RATINGS.

No, it is not possible to achieve STC-55 on interior walls framed with 3-5/8” framing at 16” o.c.

It is the Government’s intent to maximize available STC using 5/8” Gyp Bd, sound attenuation batt insulation, acoustic sealant at top and bottom of gyp bd to floor and deck, each side. Locate, detail, & stagger duct & conduit penetrations, outlet boxes, & intersections to reduce transfer of sound. Contractor shall infill existing openings to limit the transfer of sound. Ensure all partitions extend to ceiling. Acoustic baffles would not be required for most wall penetrations.

Question #68 (SOW, Drawing 6) Intel/Classif. Server: Can there be ADA access through an area that is a Classified Server? If not, how do we get ADA access to the Auditorium?

Answer Yes. The access to the server room is already behind a secure vault door. If accessible access is required, the user can escort the person needing ABA access through the server room.

Question #69 (SOW, Para 4.5.7) Indicates H.M. Doors (Assume H.M. means Hollow Metal) are to have an STC of 54 is this the intent for all the doors to be converted from wood to hollow metal? And those doors in all applications have to meet the STC of 54 which may have an adverse impact on the cost. Please identify where the STC 54 H.M. Doors are required?

Answer No, it is not the intent to replace all doors. Hollow Metal (H.M.) will only be replaced where indicated on plans. Provide H.M. doors with polyiso insulation, which should achieve STC 26.

Question #70 (SOW, Drawing 7) Corridor running North and South: Are we to assume the distance of the dead-end corridor does not exceed 50 feet?

Answer Field verify all existing dimensions.

Question #71 (SOW) Are the Aluminum Glass Storefront Systems not required to meet the STC 54 requirement?

Answer No.

Question #72 (SOW, Drawing 5) The existing stair to the left of the floor plan indicates a new aluminum storefront with double doors. Should this not be a single door H.M. Door with a fire rating to comply with the one-hour fire rating for the stair? Also, the door swings into the egress path from the floor above.

Recommend the door be changed to a single H.M. Door to allow for the appropriate clearance for egress.

Answer Provide door with appropriate fire rating to meet code requirements. These doors were new just a few years ago. Verify if doors meet current code requirements for egress. Do not replace if doors are found to be in good shape and meet code requirements. If code allows storefront doors from existing north stair vestibule to vestibule of 6030A/B, they shall be provided as called out on plan.

Question #73 (SOW, Drawing 5) Please confirm the restrooms do not have to meet the ABA requirements?

Answer Restrooms must comply with ABA requirements.

Question #74 (SOW, Para 3.1) Civil/Site/Demolition, subsection 3.1.4: will the gov't provide direction where to reconnect the sanitary sewer lines.

Answer Refer to SOW plumbing 7.7 and 7.9. The government will provide ACAD drawings showing the best available information on exiting location and routing of the SS lines and manholes; and also provide available information on the invert elevations of existing manholes. However, the contractor shall provide all necessary survey to obtain or verify all information or data as such to be provided by the government.

Question #75 (SOW, Para 4.1 & 4.4) Walls: Will the gov't provide wall details outlining the composite of STC rated wall systems?

Answer No, it is not possible to achieve STC-55 on interior walls framed with 3-5/8” framing at 16” o.c.

It is the Government’s intent to maximize available STC using 5/8” Gyp Bd, sound attenuation batt insulation, acoustic sealant at top and bottom of gyp bd to floor and deck, each side. Locate, detail, & stagger duct & conduit penetrations, outlet boxes, & intersections to reduce transfer of sound. Contractor shall infill existing openings to limit the transfer of sound. Ensure all partitions extend to ceiling. Acoustic baffles would not be required for most wall penetrations.

Question #76 (SOW) "Wall Schedule" (typical): Please clarify if we are to assume that all existing walls schedule to remain will be STC 55 rated and consist of a metal stud assembly.

Answer Walls scheduled to remain will not be upgraded, unless noted otherwise.

Question #77 (SOW) Will the gov't provide drawings, referencing wall types, door schedule, room finish schedule?

Answer No. The DB contractor is responsible for developing those schedules and details, in accordance with applicable building codes, UFCs, ABA requirements, etc.

Question #78 (SOW) Page 4, 2nd floor demolition, Bldg. A, Demolition Key Note 1: Please clarify the composite of the 2nd floor substructure.

Answer If not provided with the RFP, as-built drawings will be provided upon award. The as-built drawings show 2nd floor as 3” poured concrete on 1-1/2” metal form deck. This is on bar joists with 5/8” type “X” f.b. gyp wall board on 1 -5/8” metal studs at 16” o.c.suspended from the bar joists.

Question #79 (SOW, Para 4.1 & 4.5.3) Section 4.1 Architectural, sub-section 4.5.3 For Kitchen at Heritage Room Only: Please clarify the type of laboratory casework (steel, stainless steel, wood, plastic laminate casework).

Answer Plastic Laminate and edge banding, with heavier duty hardware. This needs to be more durable than standard casework.

Question #80 (SOW, Para 4.1 & 4.5.5) Auditorium Room: With regards to the receptacles & USB ports, please clarify the layout and demand requirement for each individual seat.

Answer One Duplex outlet and two USB ports for every two seats would be an acceptable layout for the first three (3) rows of seating. An example of possible solutions would be E-Link for auditorium seating by Irwin Seating Company. See also SOW 4.5.5. The revised furniture plan will require reconfiguration of the receptacles for desktop equipment. The using organization will provide a list of existing and/or proposed new electronic equipment that should include electrical requirements.

Question #81 (SOW, Para 4.1 & 4.5.5) Please advise of the existing LVT is still available and will the gov't provide the product data information to price too.

Answer Existing installed LVT flooring is shown to be Armstrong Natural Creations Diamond 10 Technology Arbor Art, in Avila Oak Baltic Black, NA195, and is still listed on Armstrong’s web site as of 27 April 2020. See image below:

Question #82 (SOW, Para 4.1 & 4.5.6) Corner Guards: Please clarify if the proposed Corner Guards are Stainless Steel or Vinyl w/aluminum retainers.

Answer Basis of Design: Construction Specialties Acrovyn SSM series 2” wide, or equal.

Question #83 (SOW, Para 4.1 & 4.5.13) Exterior Masonry Substructure: Please identify the location of abandoned exterior masonry opening to be infilled.

Answer Refer to drawing 6 of 11, Attachment A, sheet 34 in the SOW pdf.

Question #84 (SOW, Para 4.1 & 4.5.20) Fire Extinguishers: Since the bldg. maintains a fire sprinkler system, please confirm that fire extinguishers are required.

Answer Fire extinguishers shall meet the quantities required by NFPA 101, IBC, and any applicable UFC. Refer to SOW 9.1. New carbon dioxide portable fire extinguishers and cabinets with minimum rating of 10B:C were provided as required in the computer area and other areas of the facility. The number and locations of the portable fire extinguishers can be found on drawings for FNWZ 10-0095.

Question #85 (SOW, Para 5.1 & 5.2.3) Existing Louvers; will the gov't provide drawings, elevations and location to support pricing efforts for existing louver replacement.

Answer There is no anticipated requirement for new Outside Air Louvers except where larger size louvers are required in the design to accommodate changes in HVAC equipment capacities. If not provided with the RFP, as-built drawings will be provided upon award.

Question #86 (Drawings, Demolition Plan) Demolition keynote “2A” indicates to chemically strip and clean existing tire floors; reseal. This note can be found in most corridors and stairways. Is there any further information regarding what type of flooring this is and what the seal is on the floors?

Answer There was a typo in the concept drawings included in the SOW. “Tire” should read “Tile” this product will be either porcelain or ceramic tile, or VCT, depending on location. It is recommended to site verify actual flooring present via the site visit video or by notes taken during the site visit.

Question #87 (Section L Page 2 – Para 4.1.3) Subfactor 3 – Seed Project Schedule. We assume that an AF3064 is required for the schedule.

Are MS Project or Primavera schedules acceptable?

Yes, the .pdf schedule shows the level of divisional breakdown required for a schedule to be approved.

Question #88 (Section L Page 4 – Para 4.2.2.3) Can past performance information be provided for 3 contracts from the offeror’s Design partner in addition to the 5 contracts/TOs provided by the Prime?

Answer No. A total of 5 (maximum) past performance contracts can be submitted. The 3 references from subcontractors or partners counts towards the 5 maximum allowed.

Question #89 (Section L Page 4 – Para 4.2.3) If a final CPAR evaluation has been completed for a project, can the CPAR be used instead of the Attachment 8 Past Performance Questionnaire?

Answer No.

Question #90 (Section L Page 6 – Para 6.1) Under Past Performance Tab 2, proof of PPQ submittal is to be provided. What constitutes “proof” of the PPQ submittal?

Answer A copy of the email transmittal or acknowledgement by the agency responsible for the administration of the project can be used as proof.

Question #91 (Section L Page 6 – Para 6.1) Is the “proof” of PPQ submittal in Volume II included in the page count?

Answer No, proof of PPQ will not count towards Volume II page limit.

Question #92 ( Section L Page 6 – Para 6.6) If an offeror chooses to submit a proposal via email, are the hard copies (1 original and 1 copy) still required?

Answer A hard copy and emailed copy are not necessary, the offeror chooses which method they prefer to use. If the Offeror chooses to submit via email, a “redacted” and “original” copy of Volume I and II is still required.

Question #93 (Section M Page 10 – Para 2.2.1.1.1) Are Resumes for Key Personnel required? If so, are the Resumes included in the page count for Volume I?

Answer Yes/Yes.

Question #94 (Section M Page 11 – Para 2.2.4.1.2) Are Resumes provided under Subfactor 4 – Seed Project Quality Control Plan included in the page count for Volume I?

Yes.

Question #95 (Section M Page 12 – Para 2.3.2.1) “Recency Assessment” states, “To be recent, the effort must be ongoing or must have been performed during the past 5 years…” For ongoing projects, is there a percentage of completion that a project should have achieved in order to be used or can any ongoing project be submitted regardless of percentage complete? Will projects that are further along be given more weight than projects just started?

Answer There is no percentage of completion; however, to be considered relevant you must meet the definition of relevancy. Past performance is based on the performance of a contractor on a project.

Question #96 (Section L Page 2 – Para 4.1.4.1) Please clarify the requirements of this section. Is this section requiring us to submit full QC and Safety plans along with associated forms? Given the 40 page limit, it might not be possible.

Answer The page limit is now 50 pages for the technical volume. Only a summary plan is required in accordance to Section M 2.2.4.

Question #97 (Section L Page 3 – Para 4.2.2.3) Please confirm. At maximum we are only allowed to submit 5 projects this includes both offeror’s AND subcontractors’ references.

Answer Yes.

Question #98 (Section L Page 4 – Para 4.3.3) Under which Tab should completed Sections I -K and F-I be submitted?

Answer Added new Tab to Proposal Organization Table. Place in Volume III, Tab 4: Fill in sheets from Section F-K.

Question #99 (Section L Page 6 – Para 6.1) Past Performance. What kind of proof does the Government want? Will a copy of the email suffice?

Answer A copy of the email transmittal or acknowledgement by the agency responsible for the administration of the project can be used as proof.

Question #100 (Section L Page 6 – Para 6.1) Price and Administrative Documents. Please confirm that a bid bond is required (for the seed project). If a bid bond is required does the Government want a hard copy of the original bid bond?

Answer Bid Bond is required per this Solicitation seed project. The contractor may submit hard copies or email their proposal. ALL documents shall be received by proposal the due date and time specified.

Question #101 (Pre-solicitation Q&As) Question #20 asks if furniture is part of the proposal. The govt. only answered that fixed Auditorium seating is to be proposed and does not mention any other furniture.

Drawings and drawing key symbols call out furniture items in individual rooms but I can’t find a list or design intent anywhere in the documents, so I’m confused as to what will be included in the bidding process.

In the statement of work these divisions are listed but I cannot find reference to them: 12 35 53 ;

12 36 00 ; 12 48 13 ; 12 50 00.13 10 ; 12 59 00 ; and 12 61 13.

Answer Furniture indicated in drawings is a conceptual representative of owner provided & installed equipment; refer to SoW 11.3. The exception is in the Bldg 6030C Auditorium fixed seating.

This fixed seating is contractor provided & installed; refer to SoW 8.8.2 & drawings. Go to WBDG.org for unified design guide specs for listed specs.

Question #102 (Pre-solicitation Q&As) If furniture (other than auditorium) will be bid, will all furniture items be delivered and installed at one time or will there be a phasing requirement?

Answer Other than the auditorium seating furniture is unit-funded equipment and is not included in this design contract.

Question #103 (Pre-solicitation Q&As) For furniture items (if included) and auditorium seating, is there a requirement to provide GSA Pricing schedules? If so, will the government accept GSA price increases? Some bids call out a specific date that pricing has to be held or protected. I cannot find such a date.

Answer Other than the auditorium seating furniture is unit-funded equipment and is not included in this design contract.

Question #104 (Pre-solicitation Q&As) Could not find any requirement to remove and dispose of existing furniture, except for the demo statement for the auditorium seating. Can this be clarified?

Answer Refer to SOW 4.8.

Question #105 (SOW Page 2 – Para 1.4) Per SOW section 1.4 Confirm both facilities B6030A and B6030C will be unoccupied for the duration of construction.

Answer The construction will need to be phased so 6030A is renovated first, and when fully operational, and turned over to the user, then 6030C will be renovated, requiring the use of temporary restroom facilities as required by SOW 7.29.

Question #106 (SOW Page 2 – Para 3.1.4) Per SOW section 3.1.4 Sewer: Contractor is to cap sewer lines at building connection points.

Please clarify extent of sewer line capping required.

Answer Refer to SOW plumbing 7.7 and 7.9.

Question #107 (SOW Page 4 – Para 4.5.5) Per SOW section 4.5.5 Auditorium Room: Confirm LVT Floor Finish is required throughout the Auditorium.

Answer Refer to SOW 4.5.5, New LVT is required to infill disturbed floor finish.

Question #108 (SOW Page 6 – Para 4.5.21) Per SOW section 4.5.21 Floor Leveling: Confirm extent of floor leveling required.

Answer Floor leveling is “…as required to achieve a perceived “flat” sub-surface… Re: 4.5.21

Question #109 (SOW Page 7 – Para 4.8) Per SOW section 4.8 Confirm bid option 0002 item 2 is for furniture only ie. chairs, desks, book cases. Please confirm the Government will remove all computer equipment, monitors, simulators, etc. from the project area prior to NTP for the project.

Answer SOW 4.8 refers to “…all existing furniture…” Equipment is not included.

Question #110 (SOW Page 13 – Para 7.29) Per SOW section 7.29 Confirm both facilities B6030A and B6030C will be unoccupied for the duration of construction and temporary restroom facilities are not required for building occupants.

Answer The construction will need to be phased so 6030A is renovated first, and when fully operational, and turned over to the user, then 6030C will be renovated, requiring the use of temporary restroom facilities as required by SOW 7.29.

Question #111 (SOW Page 15 – Para 8.3) Per SOW section 8.3 Confirm all existing conduit and boxes are to be demolished and replaced.

Answer The Contractor has the option in SOW 8.3 to reuse existing undamaged conduits/boxes IF sufficiently sized, meets current code…

Question #112 (SOW Page 18 – Para 8.12.2) Per SOW section 8.12.2 Confirm Lightning Protection System not required for B6030B as well as B6030A and B6030C.

Answer The requirement for lightning protection is determined by the risk assessment required by SOW 8.12.2

Question #113 (SOW Page 19 – Top Para 9.4) Per SOW section 9.4 Confirm FA/MNS in B6030A and B6030C are not to remain in service during construction as this project does not require phased construction.

Answer Both facilities are mission critical; they house expensive, in some cases irreplaceable, vintage B- 1b electronic simulator components; and shall remain protected by the Fire Alarm System at all times.

Question #114 (SOW Page 19 – 2nd from Last Para 9.4) Per SOW section 9.4 Confirm hydrant flow test is required for both B6030A and B6030C - total of two hydrant flow tests required.

Answer Yes, hydrant flow tests are required if the sprinkler system is being replaced or altered significantly. The existing system, however, should be good for 50 years or better; and it is not understood why it is being considered for replacement. May consider only flushing and replacing heads.