Attch_2_Material_Submittal_Schedule.xls

XLS spreadsheet 39 KB Posted

Attached to
Repair UST Fuel Tanks IDIQ Federal contract opportunity
Solicitation number
FA4626-13-R-0007
Issued by
Department of the Air Force Global Strike Command

About this file

Attach 2 Material Submittal Schedule

View the file

Other files for this federal contract opportunity

Other files attached to Repair UST Fuel Tanks IDIQ, newest first.
File Type Posted
General_Decision_Number_MT76.docx DOCX document
General_Decision_Number_MT78.docx DOCX document
Amendment_2-6-2014.docx DOCX document
Amendment_0003.doc DOC document
General_Decision_Number_MT67.docx DOCX document
312300_-_Earthwork.doc DOC document
SECTION_B_CONTINUATION_SHEET.docx DOCX document
231113_-_Fuel-Oil_Storage_Tank_Piping_and_Monitoring_Leak_Detection_System.doc DOC document
Amend_3_Drawings.zip ZIP file
Specification_Section_010000.docx DOCX document
Questions_and_Answers.docx DOCX document
Amendment_02.doc DOC document
Amendment_01.doc DOC document
Pre-Proposal_Site_Visit.pdf PDF
Attch_5-3_Wage_Determination.docx DOCX document
Solicitation.doc DOC document
Attach_1_Specifications.zip ZIP file
Attach_6_Past_Performance_Questionnaire.docx DOCX document
Attch_8_Base_Entery_Policy.pdf PDF
Attch_5-1_Wage_Determination.docx DOCX document
Attch_4_Drawings.zip ZIP file
Attach_5-2_Wage_Determination.docx DOCX document
Attch_7_-_Subcontractor_Consent_Form_-_10R0027.docx DOCX document
Attach_3_Schedule_of_Drawings.doc DOC document
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIALS SUBMITTALSProject NumberProject Title:Solicitation/Contract No.
NZAS 13-6006Repair Malmstrom USTsFA4626-13-R-0007
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR
Number of Copies Required
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSNOTIFICATIONOTHERREQUIRED SUBMISSION DATE (BY CONTRACTOR)DATE RECEIVED IN CONTRACTINGDATE TO MISSILE ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDIS- APPROVED
1GENERAL REQUIREMENTS 01 00 00 - 1.8.A and 3.13.B Quality Control Plan410d ANTP
2GENERAL REQUIREMENTS 01 00 00 - 1.8.A Contractor Design Drawings110d ANTP
3GENERAL REQUIREMENTS 01 00 00 - 1.8.A MDEQ Permits445d AFIFor each LF site
4GENERAL REQUIREMENTS 01 00 00 - 1.8.A and 3.16.A As-Built Drawings445d AFI
5GENERAL REQUIREMENTS 01 00 00 - 1.8.A and 3.27 O&M Manuals (AF Form 3000)445d AFI
6GENERAL REQUIREMENTS 01 00 00 - 1.8.A and 3.21.A Work Clearance Request (AF Form 103)43d PTOFor each LF site
7GENERAL REQUIREMENTS 01 00 00 - 1.8.A and 3.11.A Utility Outages410d PTO
8GENERAL REQUIREMENTS 01 00 00 - 1.8.A Transfer & Acceptance of Military Real Property Form (DD 1354)430d PTFPFor each LF site
9GENERAL REQUIREMENTS 01 00 00 - 3.6 Construction Work Schedule4*5d PNTP* Tentative Work Schedule at Pre-Performance Meeting
10GENERAL REQUIREMENTS 01 00 00 - 3.8 Start of Work Notification46d PTSW
11ENVIRONMENTAL PROTECTION 01 36 00 - 2.2 Environmental Permit Deliverables45d SRO
12ENVIRONMENTAL PROTECTION 01 36 00 - 4.3.A Stormwater Discharge Permit Compliance410d PTSW
13ENVIRONMENTAL PROTECTION 01 36 00 - 8.1.A Hazardous Materials List Attachment 5430d PTSW
14ENVIRONMENTAL PROTECTION 01 36 00 - 8.1.B Authorization Request Worksheets, AF Form 3952410d SRO
15ENVIRONMENTAL PROTECTION 01 36 00 - 8.1.D Hazmat Final Report4PTFA
16ENVIRONMENTAL PROTECTION 01 36 00 - 10.4 Non-Hazardous Solid Waste Diversion Report410d ANTP
17ENVIRONMENTAL PROTECTION 01 36 00 - 11.1 Recycled Material Use Report Attachment 3410d SRO
18SELECTIVE DEMOLITION 017320 - 1.5.B. Schedule of Selective Demolition Activities.410d PTSW
19DRYLAND SEEDING AND FERTILIZING 029120 - 1.4.A. Seed and Fertilizer Data415d PTSW
20ROUND CONCRETE COLUMN FORMS 03 10 50 - 1.4.B. Manufacturer's product data.415d ANTP
21CAST-IN-PLACE CONCRETE 03 30 00 - 1.4 .B. Manufacturer's product data.415d ANTP
22FUEL-OIL STORAGE TANK PIPING AND MONITORING/ LEAK DETECTION SYSTEM 23 11 13 - 1.4.A.2. Installer Credentials115d ACA
23FUEL-OIL STORAGE TANK PIPING AND MONITORING/ LEAK DETECTION SYSTEM 23 11 13 - 1.4.B. Product Data415d ANTP
24FUEL-OIL STORAGE TANK PIPING AND MONITORING/ LEAK DETECTION SYSTEM 23 11 13 - 1.5. Field Quality Reports & Warranty1145d AFI
25FUEL-OIL STORAGE TANK PIPING AND MONITORING/ LEAK DETECTION SYSTEM 23 11 13 - 1.6. Close-out Submittals (Emergency, O&M Manuals)4445d AFI
26PIPING SUMP MODIFICATION AND WATER-TIGHTNESS TESTING 23 11 15 - 1.4.B. Fiberglass Lay-up415d ANTP
27PIPING SUMP MODIFICATION AND WATER-TIGHTNESS TESTING 23 11 15 - 1.4.C. Installer Credentials115d ACA
28GENERAL PROVISIONS FOR ELECTRICAL WORK - 26 00 00 - 1.20 (As-Built Drawings)445d AFI
29GENERAL PROVISIONS FOR ELECTRICAL WORK - 26 00 00 - 2.1.B.2 Product Data445d AFI
30RACEWAYS AND FITTINGS 26 11 00 - 1.2 Product Data415d ANTP
31CONDUCTORS 26 12 00 - 1.2 Product Data415d ANTP
32SHIELDED SHRINK TUBING 26 12 50 - 1.2 Product Data415d ANTP
33BOXES 26 13 00 - 1.3 Product Data415d ANTP
34CATHODIC PROTECTION 26 60 00 - 1.2.A Cathodic Protection Manufacturer Information430d ANTP
34EARTHWORK 31 23 00 - 2.4, 3.4 Manufacturer's product data for Geotextile and Marking Tape415d ANTP
Schedule of Abbreviations:
AWC= After Work CompletedPTFA= Prior to Final AcceptancePTCW=Prior to Completing Work
PTSW= Prior to Starting WorkACA=After Contract AwardAFI=After Final Inspection
AFA= After Final AcceptanceBMF=Before Material DeliveryPT=Prior To
PTO= Prior to OutageSN=Advance NotificationPSS=Per Submittal Schedule
PTNP= Prior to Notice to ProceedSRO=After Each Occurrence
ANTP= After Notice to ProceedPTFI=Prior to Final Inspection
EWD= Each work day AF Form 3000 not requiredPTFP=Prior to Final Payment

&L&"Times New Roman,Regular"&12Attachment 2&C&"Times New Roman,Regular"&12Repair Malmstrom USTs&R&"Times New Roman,Regular"&12FA4626-13-R-0007 &L&"Times New Roman,Regular"&12AF Form 66 02:

&F-&D&C&"Times New Roman,Regular"&12 SS-&P

REQUIRED TECHNICAL SUBMITTALS