Amendment 0003 February 6, 2014 Solicitation FA4626-13-R-0007 Repair Malmstrom USTs
NZAS 13-6006
1. Page LF-1 – Delete “Flexible Vent Hose” paragraph from Miscellaneous Equipment Schedule. Insert in its place: “Piping and Vent: Flex-ing Flex-Connector System including, but not limited to, APT Flexible Pipe (XP-150-SC), APT Ducting (DCT-400-xxx), Clamshell Swivel Pipe Fittings (MS-XP-150-150 or MS-XP-150-150SS), Flexible Entry Boots (DEB-150-SC) and Clamshell Secondary Test Boots (STB-150).”
2. Page LF-2, Detail 3: Add General Note “C. Install Morrison Bros. extractor (or equal) with cap in vent system.”
3. Page LF-2: Add Detail 4: “Dual Sump Tank Detail.”
4. Page LF-3, Detail 1: Modify note on sump wall to read “Fiberglass laminated water-tight joint both interior and exterior (factory-installed) for piping sump extension ring. See specification section 231115.”
5. Page LF-3, Detail 5: Add “General Note: Install Morrison Bros. extractor (or equal) with cap in vent system.”
6. Page LF-4, Detail 3: Add “General Note: When installing new piping, extend APT flexible pipe (or equal) through wall into LSB and then make necessary transitions inside building.”
7. Page LF-4, Detail 5: Delete new trench information and notations for new trench excavation. Reduce distance from piping to native material as follows: 6” min. to sides, 4” min. to bottom and 4” min. between pipes per manufacturer instructions.
8. Page LF-5, Detail 1: Add “Note: Program leak detection panel to only print when manually requested by operator.”
9. Specification 010000, 3.21.C: Change phone number to 731-7146. Change second-to-last sentence to read “The Contractor shall be held responsible for any damage to the utility by excavation procedures if within 3 feet of markings (either side) by government.”
10. Specification 231113, 3.6.B: Add “5. Program panel to print only when manually requested by operator.”
11. Specification 312300, 3.5.A: Delete last 3 sentences of paragraph.
12. Line Item BE, Anti-Siphon Valve, is still valid and should remain as a line item option in this contract.