Amendment_2-6-2014.docx

DOCX document 15 KB Posted

Attached to
Repair UST Fuel Tanks IDIQ
Solicitation number
FA4626-13-R-0007
Issued by

About this file

List of Amendment

View the file

Other files

File Type Posted
General_Decision_Number_MT78.docx DOCX document
Amendment_0003.doc DOC document
312300_-_Earthwork.doc DOC document
General_Decision_Number_MT67.docx DOCX document
SECTION_B_CONTINUATION_SHEET.docx DOCX document
231113_-_Fuel-Oil_Storage_Tank_Piping_and_Monitoring_Leak_Detection_System.doc DOC document
Amend_3_Drawings.zip ZIP file
General_Decision_Number_MT76.docx DOCX document
Specification_Section_010000.docx DOCX document
Questions_and_Answers.docx DOCX document
Amendment_02.doc DOC document
Amendment_01.doc DOC document
Pre-Proposal_Site_Visit.pdf PDF
Attch_8_Base_Entery_Policy.pdf PDF
Attach_6_Past_Performance_Questionnaire.docx DOCX document
Attach_3_Schedule_of_Drawings.doc DOC document
Attch_5-1_Wage_Determination.docx DOCX document
Attch_2_Material_Submittal_Schedule.xls XLS spreadsheet
Attach_5-2_Wage_Determination.docx DOCX document
Attch_4_Drawings.zip ZIP file
Attch_7_-_Subcontractor_Consent_Form_-_10R0027.docx DOCX document
Solicitation.doc DOC document
Attch_5-3_Wage_Determination.docx DOCX document
Attach_1_Specifications.zip ZIP file
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 0003 February 6, 2014 Solicitation FA4626-13-R-0007 Repair Malmstrom USTs

NZAS 13-6006

1. Page LF-1 – Delete “Flexible Vent Hose” paragraph from Miscellaneous Equipment Schedule. Insert in its place: “Piping and Vent: Flex-ing Flex-Connector System including, but not limited to, APT Flexible Pipe (XP-150-SC), APT Ducting (DCT-400-xxx), Clamshell Swivel Pipe Fittings (MS-XP-150-150 or MS-XP-150-150SS), Flexible Entry Boots (DEB-150-SC) and Clamshell Secondary Test Boots (STB-150).”

2. Page LF-2, Detail 3: Add General Note “C. Install Morrison Bros. extractor (or equal) with cap in vent system.”

3. Page LF-2: Add Detail 4: “Dual Sump Tank Detail.”

4. Page LF-3, Detail 1: Modify note on sump wall to read “Fiberglass laminated water-tight joint both interior and exterior (factory-installed) for piping sump extension ring. See specification section 231115.”

5. Page LF-3, Detail 5: Add “General Note: Install Morrison Bros. extractor (or equal) with cap in vent system.”

6. Page LF-4, Detail 3: Add “General Note: When installing new piping, extend APT flexible pipe (or equal) through wall into LSB and then make necessary transitions inside building.”

7. Page LF-4, Detail 5: Delete new trench information and notations for new trench excavation. Reduce distance from piping to native material as follows: 6” min. to sides, 4” min. to bottom and 4” min. between pipes per manufacturer instructions.

8. Page LF-5, Detail 1: Add “Note: Program leak detection panel to only print when manually requested by operator.”

9. Specification 010000, 3.21.C: Change phone number to 731-7146. Change second-to-last sentence to read “The Contractor shall be held responsible for any damage to the utility by excavation procedures if within 3 feet of markings (either side) by government.”

10. Specification 231113, 3.6.B: Add “5. Program panel to print only when manually requested by operator.”

11. Specification 312300, 3.5.A: Delete last 3 sentences of paragraph.

12. Line Item BE, Anti-Siphon Valve, is still valid and should remain as a line item option in this contract.