About this file

This is Amendment 0001 to Solicitation FA461326R0001, issued by the 90th Contracting Squadron at F.E. Warren Air Force Base, Wyoming on March 11, 2026. The amendment modifies a simplified acquisition for construction services under FAR Part 13 procedures for a 100% Small Business Set-Aside. The requirement involves replacing site lighting electrical conduits at 5 linear feet at F.E. Warren AFB. The contract will be awarded on a Firm Fixed-Price basis. The amendment extends the original response deadline from March 26, 2026 to April 22, 2026 at 11:00 am Mountain Daylight Time and adjusts the delivery lead time from 14 calendar days to 10 calendar days. The amendment also changes the time zone from Mountain Standard Time (UTC -7) to Mountain Daylight Time (UTC -6).

Key procedural changes include scheduling a mandatory site visit for April 14, 2026 at 9:00 am MDT at Gate 2 Parking Lot off Missile Drive outside F.E. Warren AFB, with attendees required to submit driver's license images by 3:00 pm MDT on March 16, 2026 for Entry Authorization List processing. Written questions are due by 11:00 am MDT on April 15, 2026 (the day after the site visit). Proposals must be submitted by email only to Megan Evans (megan.evans.3@us.af.mil) and SSgt Kyra Niece (kyra.niece@us.af.mil). Required submissions include a Statement of Work (SOW) dated December 18, 2025, AF Form 66 submittal register, CUI Map Layout documentation confirming NIST SP 800-171 basic score or CMMC Level 2 compliance, Davis Bacon Act wage determinations, SF 24 Bid Bond Form (20 percent of bid price), and Cost Estimate Breakdown. Offers are valid for 60 calendar days from proposal receipt date, and late submissions will not be accepted.

View the file

Other files for this federal contract opportunity

Other files attached to AMENDMENT 02: Replace Site Lighting Electrical Conduits at 5 LFs, newest first.
File Type Posted
Solicitation Amendment - Conformed .pdf PDF
Atch 7 Post Site Visit Question and Answer.pdf PDF
Solicitation Amendment FA461326R00010002 SF 30.pdf PDF
RFP Amendment 02.pdf PDF
Atch 1 Statement of Work 13 Apr 2026 Rev 1.pdf PDF
Conformed Solicitation.pdf PDF
RFP Amendment 01.pdf PDF
Solicitation - FA461326R0001.pdf PDF
Atch 5 SF 24 Bid Bond Form.pdf PDF
Atch 6 Cost Estimate Breakdown.xlsx XLSX spreadsheet
Atch 3b NIST SP 800-171 Entry Guide.pdf PDF
Atch 3a NIST SP 800-171 Assessment.pdf PDF
Atch 2 AF 66 Submittal Register.xlsx XLSX spreadsheet
Request for Proposal_Signed.pdf PDF
Atch 3 MFR CUI Control_Receipt.pdf PDF
Atch 4 Combined Wage Determinations.pdf PDF
Atch 1 Statement of Work 18 Dec 25.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

J

2. AMENDMENT/MODIFICATION NUMBER

3. EFFECTIVE DATE

11 Mar 2026

4. REQUISITION/PURCHASE

REQUISITION NUMBER

5. PROJECT NUMBER (if applicable)

GHLN 26-6277

6. ISSUED BY CODE FA4613

FA4613 90 CONS PK

CP 307 773 3888, 7505 BARNES LOOP BLDG 208

FE WARREN AFB, WY 82005-2860

UNITED STATES

MEGAN EVANS, Email: megan.evans.3@us.af.mil Telephone: 307-773-6645 Liezel McIntyre, Email: liezel.mcintyre@us.af.mil Telephone: (307) 773-3411

7. ADMINISTERED BY (if other than Item 6) CODE

SCD: PAS:

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)

CODE: FACILITY CODE:

9A. AMENDMENT OF SOLICITATION NUMBER

FA461326R0001

9B. DATED (SEE ITEM 11)

04 Mar 2026

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; 1 or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required) See Section G - Contract Administration Data

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE

A.THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN

ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See Schedule

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Liezel C. McIntyre

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

11 Mar 2026 (Signature of person authorized to sign) (Signature of Contracting Officer)

Computer generated. Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA-FAR (48 CFR) 53.243

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The purpose of this amendment is to offer a Site Visit on Tuesday 14 April 2026 at 9:00 am MDT. Meet at Gate 2 Block 14 (Description of Amendment/Modification):

Parking Lot, off of Missile Dr. outside of F.E. Warren AFB, WY.

To attend the site visit, a Driver's License image must be submitted to Contract Specialist Megan Evans at megan.evans.3@us.af.mil and Contracting Officer SSgt Kyra Niece at kyra.niece@us.af.mil by 3:00 pm MDT, Monday 16 March 2026 to be processed and added to the Entry Authorization List (EAL). Those who do not submit a Driver's License image by the deadline are unable to attend the Site Visit and will be turned away.

Questions will be due Wednesday 15 April 2026 by 11:00 am MDT.

Proposals will be due Wednesday 22 April 2026 by 11:00 am MDT.

Section A - Solicitation/Contract Form

The following modifications were made:

Information From To Begin Delivery Lead Time Duration 14 Calendar Days 10 Calendar Days

Response Due Time Zone Mountain Standard Time (UTC -7) Mountain Daylight Time (UTC -6) Response Due Date 26 Mar 2026 22 Apr 2026

Section B - Supplies or Services & Prices or Costs

Line Item 0001

The following Line Item modifications were made:

Information From To Description Replace Site Lighting Electrical Conduits at 5 LFs Replace Site Lighting Electrical Conduits at 5 LFs.

Section J - List of Attachments

The following Attachment(s) were added:

Amendment 01

Section L - Instructions, Conditions, & Notices to Offerors or Quoters

Header Miscellaneous Text (Modified):

This is a Combined Synopsis/Solicitation for simplified acquisition of a construction requirement. This announcement constitutes the only solicitation/notice, responses/ proposals are being requested, and further written solicitation will not be issued. This solicitation will be solicited as a 100% Small Business Set-Aside on SAM.gov. The 90th Contracting Squadron is issuing this requirement under FAR Part 13, Simplified Acquisition Procedures. The Government intends to award a Firm Fixed-Price contract. The solicitation document and incorporated provisions and clauses are those in effect through the Federal Acquisition Circular (FAC) 2025-06 published 01 December 2025, Defense Federal Acquisition Regulation Supplement (DFARS) published 10 November 2025, and Department of the Air Force Acquisition Regulation Supplement (DAFFARS) DAFAC 2024-1016 effective 16 October 2024. Proposals must be complete, self-sufficient, and respond directly to the requirements of this solicitation. It shall demonstrate the ability to provide the required services in accordance with the Statement of Work (SOW) dated 18 December 2025.

Instructions to Offerors:

1. Refer to Attachment 1 Statement of Work (SOW) dated 18 December 2025 to the above project to include all contract materials and workmanship to be supplied and performed in accordance with existing contract standards, codes, practices and specifications. Refer to Attachment 2 AF Form 66 for submittals.

2. Company must be registered in SAM.gov and fit the small business size standard of the solicited NAICS. Awardee shall be registered in SAM, no active exclusions, and acceptable supplier risk profile in SPRS module. A basic score in the NIST SP 800-171 (if below 110 a plan of improvement is required with proposal) or Level 2 in CMMC

Please fill out Attachment 3 MFR CUI Control & Receipt to have your assessment score checked and if of SPRS is required to obtain the Attachment 3 CUI Map Layout.

compliant, obtain the necessary CUI Map Layout to fully understand the scope of the project. Proposals received from Contractors who did not obtain Attachment 3 CUI Map Layout shall be deemed technically unacceptable due to not having the full scope of the project. Any offeror without a basic assessment of NIST SP 800-171 or

CMMC Level 2 shall not be eligible for award.

FA461326R00010001

3. Meet at Gate 2 off Missile Dr., outside of F.E. Warren AFB, WY to caravan to the site. Personnel The site visit is scheduled for Tuesday 14 April 2026 at 9:00 am MDT.

wishing to attend will need to provide their Drivers License image (front side) to be put on an Entry Authorization List (EAL) as the site to be visited is secured. Please submit the images of the Drivers Licenses of those wishing to attend to megan.evans.3@us.a.fmil and kyra.niece@us.af.mil by 3:00 pm MDT Monday 16 March 2026.

Those who do not submit a Driver License image by the deadline will not be able to attend the Site Visit.

4. Questions are due to 90 CONS by 11:00 am MT, the day after the site visit. Submit questions via email only to Ms. Megan Evans at megan.evans.3@us.af.mil and SSgt Kyra Niece at kyra.niece@us.af.mil. If there is no request for a site visit, the Questions are due by 11:00 am MT, Tuesday, 17 March 2026.

5. The Davis Bacon Act Wage Determination applies, refer to Attachment 4 Combined Wage Determinations.

6. A Bid Guarantee is required, please submit Attachment 5 SF 24 Bid Bond Form, along with your proposal.

7. This solicitation, along with Attachment 6 Cost Estimate Breakdown, is also to be submitted with the proposal.

8. by emailing proposals to megan.evans.3@us.af.mil and kyra.niece@us.af.mil. Submit proposal to this RFP no later than 11:00 am MDT on Wednesday 22 April 2026 Solicitation responses shall be sent via electronic means only (emailed only; mailed, hand-carried or faxed proposal shall not be accepted). Offers shall have a valid date of 60 calendar days from day of proposal receipt. Late offers shall not be accepted once solicitation has ended.

Attachment List:

1. Statement of Work 18 Dec 2025

2. AF 66 Submittal Register

3. CUI Map Layout/MFR CUI Control & Receipt

4. Combined Wage Determinations

5. SF 24 Bid Bond Form

6. Cost Estimate Breakdown

Additional Regulation or Supplemental Clauses Incorporated by Full Text

The following Clause modifications were made:

52.228-1 Bid Guarantee. Sep 1996 hereby reads as follows:

Bid Guarantee (Sept 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, bid bond supported by good and sufficient surety or sureties acceptable to the e.g., Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be percent of the bid price. Submit via SF24 as attached to this solicitation. 20

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of clause)

FA461326R00010001

SUMMARY OF CHANGES
Solicitation/Contract Form
Supplies or Services & Prices or Costs
List of Attachments
Instructions, Conditions, & Notices to Offerors or Quoters

File details come from the government source that posted it. Updated .