AMENDMENT 02: Replace Site Lighting Electrical Conduits at 5 LFs Federal contract opportunity
Solicitation number
FA461326R0001
Issued by
Department of the Air Force Global Strike Command

About this file

This is a Solicitation, Offer, and Award document for construction services issued by the U.S. Air Force 90th Contracting Squadron at F.E. Warren Air Force Base, Wyoming. The solicitation number is FA461326R00010001, issued March 4, 2026, with a deadline for sealed bids at 11:00 AM local time on April 22, 2026. The project involves replacing site lighting electrical conduits at five (5) Launch Facilities located in Nebraska and Colorado. This is a 100% Small Business Set-Aside solicitation with a NAICS code of 236220 and a size standard of $45,000,000 in annual receipts. The contract type is Firm Fixed-Price with a mandatory performance period of 120 calendar days from Notice to Proceed, with contractor performance beginning within 10 calendar days of award. Performance and payment bonds at 10 calendar days post-award are required. All offers must provide at least 3 calendar days for Government acceptance after the offer due date.

The evaluation methodology is Lowest Price Technically Acceptable (LPTA), with price and technical acceptability weighted equally. Technical evaluation includes a work plan demonstrating ability to complete the project within 120 calendar days (proposals exceeding this timeline are technically unacceptable) and submission of a SF 24 Bid Bond Form with evidence of bonding capacity from an approved surety. Offerors must be registered in SAM.gov, maintain no active exclusions, and possess either a NIST SP 800-171 basic assessment score (with a plan of improvement if below 110) or CMMC Level 2 certification to obtain the required CUI Map Layout attachment demonstrating full project scope understanding. A mandatory site visit is scheduled for April 14, 2026, at 9:00 AM MDT at F.E. Warren AFB, with driver's license submissions required by March 16, 2026, for Entry Authorization List processing. Questions are due by 11:00 AM MT the day after the site visit. The Davis Bacon Act Wage Determination applies to this construction contract.

View the file

Other files for this federal contract opportunity

Other files attached to AMENDMENT 02: Replace Site Lighting Electrical Conduits at 5 LFs, newest first.
File Type Posted
Solicitation Amendment FA461326R00010002 SF 30.pdf PDF
RFP Amendment 02.pdf PDF
Atch 1 Statement of Work 13 Apr 2026 Rev 1.pdf PDF
Solicitation Amendment - Conformed .pdf PDF
Atch 7 Post Site Visit Question and Answer.pdf PDF
Amendment 01 SF 30.pdf PDF
RFP Amendment 01.pdf PDF
Solicitation - FA461326R0001.pdf PDF
Request for Proposal_Signed.pdf PDF
Atch 3 MFR CUI Control_Receipt.pdf PDF
Atch 4 Combined Wage Determinations.pdf PDF
Atch 1 Statement of Work 18 Dec 25.pdf PDF
Atch 5 SF 24 Bid Bond Form.pdf PDF
Atch 6 Cost Estimate Breakdown.xlsx XLSX spreadsheet
Atch 3b NIST SP 800-171 Entry Guide.pdf PDF
Atch 3a NIST SP 800-171 Assessment.pdf PDF
Atch 2 AF 66 Submittal Register.xlsx XLSX spreadsheet
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION

NUMBER

FA461326R00010001

2. TYPE OF SOLICITATION

SEALED BID (IFB) INVITATION FOR BID

NEGOTIATED (RFP) REQUEST FOR

PROPOSAL

3. DATE ISSUED

04 Mar 2026

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

GHLN 26-6277

7. ISSUED BY CODE: FA4613

FA4613 90 CONS PK

CP 307 773 3888, 7505 BARNES LOOP BLDG 208

FE WARREN AFB, WY 82005-2860

UNITED STATES

MEGAN EVANS, Email: megan.evans.3@us.af.mil Telephone: 307-773-6645 Liezel McIntyre, Email: liezel.mcintyre@us.af.mil Telephone: (307) 773-3411

8. ADDRESS OFFER TO

9. FOR

INFORMATION CALL:

a. NAME

MEGAN EVANS

b. TELEPHONE NUMBER (include area code) (NO COLLECT CALLS) 307-773-6645

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

10.THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

Project Title: Replace Site Lighting Electrical Conduits at 5 LFs Project Location: Nebraska and Colorado

The Contractor shall provide all labor, materials, equipment, and transportation necessary for the site lighting electrical conduits at five (5) Launch Facilities (LFs) as specified in the Stateme nt of Work, in strict compliance with the specifications, applicable drawings, attachments, and the Terms and Conditions of the Contract as well as all applicable building codes, standards, a nd practices in the industry. The period of performance (PoP) for this contract will be 120 calendar days.

11. The contractor shall begin performance within calendar days and complete it within calendar days after receiving 10 120 award, notice to proceed. This performance period is mandatory negotiable. (See ). FAR 52.211-10

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

YES NO

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) 11:00 AM local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes 22 Apr 2026 containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected. 3

Computer generated. STANDARD FORM 1442 (REV. 12/2022) Prescribed by GSA-FAR (48CFR) 53.236-1(d)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE 11 Mar 2026 20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

10 U.S.C 3204(A) ( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document

Contractor agrees to furnish and return copies to issuing office.)

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

Computer generated. STANDARD FORM 1442 (REV. 12/2022) BACK

Section A - Solicitation/Contract Form PKAB Replace Site Lighting Electrical Conduits at 5 Launch Facilities (LFs) (Construction)

NAICS: 236220

Size Standard: USD 45,000,000.00 Annual receipts

Small Business Type: Small Business Set Aside Percent: 100

Product Service Code: Z2JZ

FA461326R00010001

Section B - Supplies or Services & Prices or Costs Additional Information/Notes

Item Supplies / Services Quantity Unit Unit Price Amount

Replace Site Lighting Electrical Conduits at 5 LFs.

Product Type Code: Z2JZ Product Service Code: Z2JZ Pricing Arrangement: Firm Fixed Price

1 Job

Section C - Description/Specifications/Statement of Work

Requirements This project includes replacing site lighting electrical conduits at five (5) Launch Facilities (LFs). The LFs are under the control of F.E. Warren Air Force Base, Wyoming.

Section D - Packaging and Marking

Section E - Inspection and Acceptance

FAR Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

52.246-12 Inspection of Construction. Aug 1996 Overall Contract Inspection/Acceptance Locations

Inspection and Acceptance Location

Both Destination Instructions: See Statement of Work (SOW) for Acceptance/inspection criteria.

DoDAAC: F1Y3DA CountryCode: USA

90 CES

AF BPN NO MILSBILLS PROCESSES, 300 VESLE DR

FE WARREN AFB, WY 82005-2782

UNITED STATES

Section F - Deliveries or Performance Overall Contract Delivery Period

Line Item Delivery Schedule Quantity Address and POC

Delivery Schedule From date of lead time event to completion of performance 120 Calendar Days Date of Notice to Proceed Receipt

1 Job Place of Performance DoDAAC: F1Y3DA CountryCode: USA

90 CES

AF BPN NO MILSBILLS PROCESSES, 300 VESLE DR

FE WARREN AFB, WY 82005-2782

UNITED STATES

Section G - Contract Administration Data

DFARS Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. Dec 2018 252.236-7000 Modification Proposals--Price Breakdown. Dec 1991

DFARS Clauses Incorporated by Full Text

252.232-7006 Wide Area WorkFlow Payment Instructions. (Jan 2023)

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) As used in this clause- Definitions.

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Electronic invoicing.

Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) To access WAWF, the Contractor shall- WAWF access.

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before WAWF training.

submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol. WAWF methods of document submission.

(f) The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract WAWF payment instructions.

or task or delivery order:

(1) The Contractor shall submit payment requests using the following document type(s): Document type.

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

N/A

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

Construction Invoice

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment Document routing.

requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC F87700

Issue By DoDAAC FA4613

Admin DoDAAC FA4613

Inspect By DoDAAC FA4613

Ship To Code FA4613

Ship From Code N/A

Mark For Code N/A

Service Approver (DoDAAC) FA4613

Service Acceptor (DoDAAC) FA4613

Accept at Other DoDAAC N/A

LPO DoDAAC N/A

DCAA Auditor DoDAAC N/A

Other DoDAAC(s) N/A

(4) The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the Payment request.

payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F. Receiving report.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

Contract Specialist: Megan Evans via megan.evans.3@us.af.mil

Contracting Officer: SSgt Kyra Niece via kyra.niece@us.af.mil

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

Section I - Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. Jan 2017 52.204-9 Personal Identity Verification of Contractor Personnel. Jan 2011 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (Deviation) Feb 2026 52.204-13 System for Award Management-Maintenance. (Deviation) Feb 2026 52.204-19 Incorporation by Reference of Representations and Certifications. Dec 2014 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Deviation) Feb 2026

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (Deviation) Feb 2026 52.213-4 Terms and Conditions-Simplified Acquisitions (Noncommercial). (Deviation) Feb 2026 52.219-6 Notice of Total Small Business Set-Aside. (Deviation) Feb 2026 52.222-3 Convict Labor. (Deviation) Feb 2026 52.222-4 Contract Work Hours and Safety Standards-Overtime Compensation. (Deviation) Feb 2026 52.222-6 Construction Wage Rate Requirements. (Deviation) Feb 2026 52.222-7 Withholding of Funds. (Deviation) Feb 2026 52.222-8 Payrolls and Basic Records. (Deviation) Feb 2026 52.222-9 Apprentices and Trainees. (Deviation) Feb 2026 52.222-10 Compliance with Copeland Act Requirements. (Deviation) Feb 2026 52.222-11 Subcontracts (Labor Standards). (Deviation) Feb 2026 52.222-12 Contract Termination-Debarment. May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. May 2014 52.222-14 Disputes Concerning Labor Standards. (Deviation) Feb 2026 52.222-15 Certification of Eligibility. May 2014 52.222-35 Equal Opportunity for Veterans. (Deviation) Feb 2026 52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation) Feb 2026 52.222-37 Employment Reports on Veterans. (Deviation) Feb 2026 52.222-50 Combating Trafficking in Persons. (Deviation) Feb 2026 52.222-54 Employment Eligibility Verification. (Deviation) Feb 2026 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation) Feb 2026 52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation) Feb 2026 52.223-5 Pollution Prevention and Right-to-Know Information. May 2024 52.223-23 Sustainable Products and Services. (DEVIATION 2025-O0004) Feb 2026 Deviation 2025-O0004 Mar 2025 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving. May 2024 52.228-2 Additional Bond Security. Oct 1997 52.228-11 Pledges of Assets (DEVIATION 2020-O0016) Feb 2021 Deviation 2020-O0016 Apr 2020 52.228-14 Irrevocable Letter of Credit. Nov 2014 52.228-15 Performance and Payment Bonds-Construction. Jun 2020 52.229-12 Tax on Certain Foreign Procurements. Feb 2021 52.232-8 Discounts for Prompt Payment. Feb 2002 52.232-17 Interest. May 2014 52.232-23 Assignment of Claims. May 2014 52.232-27 Prompt Payment for Construction Contracts. Jan 2017 52.232-33 Payment by Electronic Funds Transfer-System for Award Management. Oct 2018 52.232-39 Unenforceability of Unauthorized Obligations. Jun 2013 52.233-3 Protest after Award. (Deviation) Feb 2026 52.233-4 Applicable Law for Breach of Contract Claim. (Deviation) Feb 2026 52.236-5 Material and Workmanship. (Deviation) Feb 2026 52.236-7 Permits and Responsibilities. (Deviation) Feb 2026 52.240-91 Security Prohibitions and Exclusions. (Deviation) Feb 2026 52.240-92 Security Requirements. (Deviation) Feb 2026 52.242-14 Suspension of Work. Apr 1984 52.243-5 Changes and Changed Conditions. (Deviation) Feb 2026 52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation) Feb 2026 52.246-21 Warranty of Construction. Mar 1994 52.249-4 Termination for Convenience of the Government (Services) (Short Form). Apr 1984 52.249-10 Default (Fixed-Price Construction). Apr 1984

DFARS Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

252.203-7000 Requirements Relating to Compensation of Former DoD Officials. Sep 2011 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. Dec 2022 252.204-7000 Disclosure of Information. Oct 2016 252.204-7003 Control of Government Personnel Work Product. Apr 1992 252.204-7004 Antiterrorism Awareness Training for Contractors. Jan 2023 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. (DEVIATION 2024-

O0013 REVISION 1)

May 2024 Deviation 2024-O0013 May 2024

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services. Jan 2023

252.204-7020 NIST SP 800-171 DoD Assessment Requirements. Nov 2023 252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials. Sep 2014 252.223-7008 Prohibition of Hexavalent Chromium. Jan 2023 252.225-7048 Export-Controlled Items. Jun 2013 252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime. Jan 2023 252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region. Jun 2023 252.232-7010 Levies on Contract Payments. Dec 2006 252.243-7001 Pricing of Contract Modifications. Dec 1991 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for Military Operations. Oct 2010 252.247-7023 Transportation of Supplies by Sea. Oct 2024

FAR Clauses Incorporated by Full Text

52.219-28 Postaward Small Business Program Rerepresentation. (Deviation) (Feb 2026)

Postaward Small Business Program Rerepresentation (Feb 2026) (Deviation)

(a) . As used in this clause-Definitions

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern-

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.

(2) , as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties Affiliates control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts-

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https:// www.sba.gov/document/support--table-size-standards.

(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition-

(1) Was set aside for small business and has a value above the simplified acquisition threshold;

(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or

(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause, that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

(1) The Contractor represents that it is, is not a small business concern under 236220 assigned to contract number.____ ____

(2) [ .] The Contractor represents that it is, is not, a small Complete only if the Contractor represented itself as a small business concern in paragraph (g)(1) of this clause disadvantaged business concern as defined in .13 CFR 124.1001

(3) . The Contractor represents that it is, is not a joint venture that complies with the Women-owned small business (WOSB) joint venture eligible under the WOSB Program requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __.]____

(4) . The Contractor represents that it is, is not a joint venture that complies with the Economically disadvantaged women-owned small business (EDWOSB) joint venture requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __ .]____

(5) . The Contractor represents that it is, is not an SDVOSB Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under the SDVOSB Program joint venture eligible under the SDVOSB Program that complies with the requirements of 13 CFR 128.402. [ The Contractor shall enter the name and unique entity ____ identifier of each party to the joint venture: __.]

(6) [ ] The offeror represents, as part of its HUBZone joint venture eligible under the HUBZone Program. Complete only if the offeror is a HUBZone small business concern.

offer, that It is, is not a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c). [ The Contractor shall enter the name and unique ____ entity identifier of each party to the joint venture: .] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern. [ Contractor to sign and date and insert authorized signer's name and title.] ____

(End of clause)

52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items. (May 2008)

Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)

(a) . As used in this clause-Definitions

Postconsumer materialmeans a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of "recovered material."

"Recovered material" means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

(b) The Contractor, on completion of this contract, shall-

(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and

(2) Submit this estimate to .SSgt Kyra Niece at kyra.niece@us.af.mil

(End of clause)

52.225-9 Buy American-Construction Materials. (Deviation) (Feb 2026)

Buy American-Construction Materials (Feb 2026) (Deviation)

(a) . As used in this clause-Definitions

Commercially available off-the-shelf (COTS) item-

(1) Means any item of supply (including construction material) that is-

(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work.

The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means-

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph

(1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means-

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if-

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

N/A_

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) .For domestic construction material that is not a critical item or does not contain critical components

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A) of this clause.(1)

(3) The procedures in paragraph (b)(3)(i)(A) of this clause will no longer apply as of January 1, 2030.(2)

(B) .For domestic construction material that is a critical item or contains critical components

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B) of this clause.(1)

(3) The procedures in paragraph (b)(3)(i)(B) of this clause will no longer apply as of January 1, 2030.(2)

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.

(d) . To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any Data applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction material description Unit of measure Quantity Price

(dollars)*

Item 1:

Foreign construction material. ____ ____ ____

Domestic construction material. ____ ____ ____

Item 2:

Foreign construction material. ____ ____

Domestic construction material. ____ ____ ____

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate ].is issued)

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach ]summary.

[ ]Include other applicable supporting information.

(End of clause)

52.228-13 Alternative Payment Protections. (Jul 2000)

Alternative Payment Protections (July 2000)

(a) The Contractor shall submit one of the following payment protections:

Payment Bond

(b) The amount of the payment protection shall be 100 percent of the contract price.

(c) The submission of the payment protection is required within days of contract award.5

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.

(End of clause)

52.232-5 Payments under Fixed-Price Construction Contracts. (May 2014)

Payments under Fixed-Price Construction Contracts (May 2014)

(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.

(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

(1) The Contractor's request for progress payments shall include the following substantiation:

(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.

(ii) A listing of the amount included for work performed by each subcontractor under the contract.

(iii) A listing of the total amount of each subcontract under the contract.

(iv) A listing of the amounts previously paid to each such subcontractor under the contract.

(v) Additional supporting data in a form and detail required by the Contracting Officer.

(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-

(i) Consideration is specifically authorized by this contract; and

(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.

(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)

I hereby certify, to the best of my knowledge and belief, that-

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor's performance.

____ (Name)

____ (Title)

____ (Date)

(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-

(1) Notify the Contracting Officer of such performance deficiency; and

(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8 thday after the date of receipt of the unearned amount until-

(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or

(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.

(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-

(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or

(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.

(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

(h) Final payment. The Government shall pay the amount due the Contractor under this contract after-

(1) Completion and acceptance of all work;

(2) Presentation of a properly executed voucher; and

(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 (31 U.S.C.3727 and 41 U.S.C.6305).

(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(j) Interest computation on unearned amounts. In accordance with 31 U.S.C.3903(c)(1), the amount payable under paragraph (d)(2) of this clause shall be-

(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and

(2) Deducted from the next available payment to the Contractor.

(End of clause)

52.232-16 Progress Payments. (Deviation) (Feb 2026)

Progress Payments (Feb 2026) (Deviation)

The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly, in amounts of $2,500 or more approved by the Contracting Officer, under the following conditions:

(a) Computation of amounts.

(1) Unless the Contractor requests a smaller amount, the Government will compute each progress payment as 80 percent of the Contractor's total costs incurred under this contract whether or not actually paid, plus financing payments to subcontractors (see paragraph (j) of this clause), less the sum of all previous progress payments made by the Government under this contract. The Contracting Officer will consider cost of money that would be allowable under Federal Acquisition Regulation (FAR) 31.205-10 as an incurred cost for progress payment purposes.

(2) The amount of financing and other payments for supplies and services purchased directly for the contract are limited to the amounts that have been paid by cash, check, or other forms of payment, or that are determined due and will be paid to subcontractors-

(i) In accordance with the terms and conditions of a subcontract or invoice; and

(ii) Ordinarily within 30 days of the submission of the Contractor's payment request to the Government.

(3) The Government will exclude accrued costs of Contractor contributions under employee pension plans until actually paid unless-

(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and

(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor's total costs for progress payments until paid).

(4) The Contractor shall not include the following in total costs for progress payment purposes in paragraph (a)(1) of this clause:

(i) Costs that are not reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices.

(ii) Costs incurred by subcontractors or suppliers.

(iii) Costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.

(iv) Payments made or amounts payable to subcontractors or suppliers, except for-

(A) Completed work, including partial deliveries, to which the Contractor has acquired title; and

(B) Work under cost-reimbursement or time-and-material subcontracts to which the Contractor has acquired title.

(5) The amount of unliquidated progress payments may exceed neither (i) the progress payments made against incomplete work (including allowable unliquidated progress payments to subcontractors) nor (ii) the value, for progress payment purposes, of the incomplete work. Incomplete work shall be considered to be the supplies and services required by this contract, for which delivery and invoicing by the Contractor and acceptance by the Government are incomplete.

(6) The total amount of progress payments shall not exceed 80 percent of the total contract price.

(7) If a progress payment or the unliquidated progress payments exceed the amounts permitted by subparagraphs (a)(4) or (a)(5) of this clause, the Contractor shall repay the amount of such excess to the Government on demand.

(8) Notwithstanding any other terms of the contract, the Contractor agrees not to request progress payments in dollar amounts of less than $2,500. The Contracting Officer may make exceptions.

(9) The costs applicable to items delivered, invoiced, and accepted shall not include costs in excess of the contract price of the items.

(b) Except as provided in the Termination for Convenience of the Government clause, all progress…