576_LSS_CLIN_STRUCTURE_OVERVIEW.pdf

PDF 24 KB Posted

Attached to
Provide 576th FLTS Launch Facility Support Services Federal contract opportunity
Solicitation number
FA4610-17-R-0011
Issued by
Department of the Air Force Space Command

About this file

The purpose of this CLIN Structure Overview is to show the contractor an overview of CLINs and quantities that were updated and capture the changes to avoid any confusion.

View the file

Other files for this federal contract opportunity

Other files attached to Provide 576th FLTS Launch Facility Support Services, newest first.
File Type Posted
Atch_1_-_LSS_PWS_dtd_20170504_amend_01.doc DOC document
FA4610-17-R-0011-0001_Amendment_01_(Conformed_-_ktr_propose).docx DOCX document
QA_Response_to_RFP_5_May_2017.docx DOCX document
FA4610-17-R-0011-0001_Amendment_01_(Sign_Amendment).docx DOCX document
Atch_5_-_DBA_CA_170023_dtd_6_Jan_2017.docx DOCX document
Atch_6a_-_DD_254_Handling_FOUO.doc DOC document
FA4610-17-R-0011.docx DOCX document
Atch_1_-_LSS_PWS_dtd_20170323.doc DOC document
Atch_2_-_Consolidated_GFP_List_dtd_24_Feb_17.pdf PDF
Atch_3__Environmental_Specs_dtd_May_2016.docx DOCX document
Atch_6_-_DD_254_576_LSS.pdf PDF
Atch_7_-_LSS_Tech_Accept_Quest_17-R-0011_20170404.doc DOC document
Atch_4_-_CBA_between_LIUNA_and_ATS.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

576 Launch Support Services CLIN Structure Overview

CLIN NAME OF CLIN QTY UNIT

9999 Phase-In 1 MO

0001 Launch Support Services 11 MO

0002 After Hours Support 600 LH 0003 FDE Additional Refurb Tasks for (4th Fire) 2 EA 0004 Materials 1 JOB

1001 Launch Support Services 12 MO 1002 After Hours Support 600 LH 1003 FDE Additional Refurb Tasks for (4th Fire) 2 EA 1004 Materials 1 JOB 1005 OTHER TESTS Refurbishment 1 EA 1006 OTHER TESTS Refurbishment 4th Fire 1 EA 1007 OTHER TESTS Materials 1 JOB 1008 OTHER TESTS After Hour Support 300 LH

2001 Launch Support Services 12 MO 2002 After Hours Support 600 LH 2003 FDE Additional Refurb Tasks for (4th Fire) 2 EA 2004 Materials 1 JOB 2005 OTHER TESTS Refurbishment 1 EA 2006 OTHER TESTS Refurbishment 4th Fire 1 EA 2007 OTHER TESTS Materials 1 JOB 2008 OTHER TESTS After Hour Support 300 LH

3001 Launch Support Services 12 MO 3002 After Hours Support 600 LH 3003 FDE Additional Refurb Tasks for (4th Fire) 2 EA 3004 Materials 1 JOB 3005 OTHER TESTS Refurbishment 1 EA 3006 OTHER TESTS Refurbishment 4th Fire 1 EA 3007 OTHER TESTS Materials 1 JOB 3008 OTHER TESTS After Hour Support 300 LH

4001 Launch Support Services 12 MO 4002 After Hours Support 600 LH 4003 FDE Additional Refurb Tasks for (4th Fire) 2 EA 4004 Materials 1 JOB 4005 OTHER TESTS Refurbishment 1 EA 4006 OTHER TESTS Refurbishment 4th Fire 1 EA 4007 OTHER TESTS Materials 1 JOB 4008 OTHER TESTS After Hour Support 300 LH

5001 Launch Support Services 6 MO

5002 After Hours Support 300 LH 5003 FDE Additional Refurb Tasks for (4th Fire) 1 EA 5004 Materials 1 JOB 5005 OTHER TESTS Refurbishment 1 EA 5006 OTHER TESTS Refurbishment 4th Fire 1 EA 5007 OTHER TESTS Materials 1 JOB 5008 OTHER TESTS After Hour Support 150 LH

6-Month Extension: 1 Sep 2022 – 28 Feb 2023

Option Year 3: 1 Sep 2020 – 31 Aug 2021

Base: 1 Oct 2017 - 31 Aug 2018

Option Year 1: 1 Sep 2018 – 31 Aug 2019

Option Year 4: 1 Sep 2021 – 31 Aug 2022

Phase-In: 1 Sep 2017 - 30 Sep 2017

TOTAL AMOUNT OF BASIC YEAR

TOTAL AMOUNT OF OPTION YEAR 1

Option Year 2: 1 Sep 2019 – 31 Aug 2020

TOTAL AMOUNT OF PHASE-IN

Entire PoP IGE

File details come from the government source that posted it. Updated .