This is a Statement of Objectives (SOO) for the installation of video teleconferencing (VTC) equipment and integration of STIG-compliant matrix equipment in Building 1758 at Joint Base McDill-Dix-Lake Hurst (JB MDL). The contractor shall replace existing Atlona A/V equipment with Security Technical Implementation Guides (STIG) compliant equipment that integrates with both Nonsecure Video Teleconferencing System (NVTC) and Secure Video Teleconferencing System (SVTC) in compliance with DOD Instruction 8100.04. All hardware and software must be new, installed within the facility, and controllable from two centralized locations via contractor-furnished control panels. The 15-panel display wall must support multiple display configurations and simultaneously display secured and non-secured data while maintaining communications security (COMSEC) and emission security (EMSEC) requirements. All equipment must be DISA-approved and registered through the DISA REM Vendor STIG program.

Key contractor deliverables include: transmitter/receiver/matrix equipment supporting 21 locations displaying on the 15-panel wall, two control panels for Briefer 1 and Mission Control locations, microphone solutions for both NVTC and SVTC communication, four 27-inch monitors for the Mission Control area, and mounting brackets for two existing GFE CISCO pan-tilt-zoom 12x cameras. The contractor must program all devices including existing CISCO codecs, provide programming code and updated schematics upon completion, ensure the GFR BIAMP Tesira HD-2 dialer integration, develop a mission control area with four-monitor control capability, coordinate with 87 Communications Squadron for Information Assurance controls, and move the GFE IPS container to a designated location. The contractor must demonstrate documented experience connecting SVTC systems to AFNET or equivalent DoD enterprise networks through past performance, prior DoD contracts, government references, or technical documentation including architecture diagrams and sanitized configuration examples. The period of performance shall not exceed 180 days from contract date, with all installation, training, testing, and acceptance completed within this timeframe.

View the file

Other files

File Type Posted
Solicitation Amendment - FA448426Q00050001.pdf PDF
Solicitation Amendment FA448426Q00050001 SF 30.pdf PDF
Ceiling 1.jpg JPG image
Rack 2.jpg JPG image
Left Camera 1.jpg JPG image
Rack 3.jpg JPG image
Touchscreen 4.jpg JPG image
Touchscreen 2.jpg JPG image
Ceiling 3.jpg JPG image
Ceiling 2.jpg JPG image
Rack 4.jpg JPG image
Rack 1.jpg JPG image
Right Camera 1.jpg JPG image
CAT Video Wall.jpg JPG image
CAT Video Wall 2.jpg JPG image
Rack 5.jpg JPG image
Touchscreen 5.jpg JPG image
Rack 7.jpg JPG image
Rack 6.jpg JPG image
Site Visit Questions and Answers.pdf PDF
Atlona.pdf PDF
Extron.pdf PDF
Samsung.pdf PDF
Biamp.pdf PDF
Crestron.pdf PDF
Denon.pdf PDF
Shure.pdf PDF
CAT AV Wall Submission_MCS_.1685122168553.pdf PDF
Warranties.pdf PDF
Extreme.pdf PDF
Middle Atlantic.pdf PDF
JBMDL Atlona.pdf PDF
JBMDL-CAT.xlsx XLSX spreadsheet
JB MDL AT Awareness Guide for Contractors .pdf PDF
JB MDL AT Awareness for Contractors Trifold.pdf PDF
Past Performance Questionnaire.pdf PDF
SOO AT Statement.pdf PDF
Medical Statement.docx DOCX document
SOO For JBOC Upgrade.docx DOCX document
SFS Appendix.pdf PDF
Solicitation - FA448426Q0005.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF OBJECTIVES

INSTALLATION OF VTC EQUIPMENT AND INTEGRATION OF STIG COMPLIANT

MATRIX EQUIPMENT IN BLDG 1758

1. Objective. Contractor shall replace Atlona A/V equipment with equipment compliant with

Security Technical Implementation Guides (STIGs) and interoperability requirements as prescribed in DOD Instruction 8100.04. The new equipment will integrate with existing government furnished property to support both a Nonsecure Video Teleconferencing System (NVTC) and Secure Video Teleconferencing System (SVTC). All hardware and software must be installed within Bldg. 1758. NVTC, SVTC, and other inputs must be controllable from the same location, via contractor-furnished control panels capable of displaying to the 15-panel wall. All hardware and software that Contractor is required to install must be STIG compliant. All equipment and materials will be new and refurbished equipment is not acceptable.

Cybersecurity requirements have transferred to the DISA REM Vendor Security Technical Implementation Guides (STIG) program. The process is outlined here:

https://www.cyber.mil/stigs/vendor-process

Interoperability requirements will be identified by the Unified Capabilities Requirements (UCR)- CORE document and enforced through contractual provisions.

2. Requirements.

a. Transmitter/receiver equipment. Contractor must install/connect transmitter/receiver equipment such that 21 locations can utilize the equipment to display onto the 15-panel wall. Locations in the room are named in the image below. (Briefer 1, JB MDL/CD-A, SIPR, etc.).

https://www.cyber.mil/stigs/vendor-process

b. Video Wall: Contractor will ensure the 15-panel can display in multiple different configurations (15 different displays, 15 panels functioning as one display, two sets of four screens functioning as a single display, etc.) Video wall configurations must be robust, scalable, and adaptable.

c. Expertise: The Contractor shall demonstrate documented experience connecting Secure Video Teleconferencing (SVTC) systems to the Air Force Network (AFNET) or equivalent DoD enterprise networks.

Evidence shall include one or more of the following:

• Documented past performance involving SVTC, Unified Capabilities (UC), or secure collaboration services connected to AFNET

• Prior contracts or task orders with the U.S. Air Force, DISA, or other DoD components supporting SVTC or UC integration

• References from Government Contracting Officer’s Representatives (CORs) or technical authorities validating successful performance

• Evidence of sustained operations and maintenance of AFNET-connected systems

• Experience working within classified and unclassified AFNET enclaves

• Architecture diagrams illustrating SVTC integration with AFNET, including boundary protections and traffic flows

• Sanitized configuration examples demonstrating:

o VLAN segmentation o Quality of Service (QoS) policies for video traffic o Firewall rules and Access Control Lists (ACLs)

• Experience integrating DoD-approved SVTC platforms and endpoints

• Implementation and validation of applicable Security Technical Implementation Guides (STIGs), including:

o Network Infrastructure STIGs o Unified Capabilities STIGs

• Familiarity with DISA Unified Capabilities requirements and applicable AFIs

d. Control panels. NVTC and SVTC must be controllable from the same locations, via contractor-furnished control panels. The SVTC, NVTC, and 21 transmitter/receiver outputs will connect to the 15-panel wall and be controllable via the two control panels.

Control panels will be located at the Briefer 1 and Mission Control location illustrated in the image provided above.

e. Cameras. Contractor will install two GFE CISCO pan-tilt-zoom 12x cameras, replacing the defunct cameras currently stationed on the wall. These cameras must integrate with the NVTC, SVTC, and other government furnished equipment.

f. Microphones. Contractors will provide a microphone solution sufficiently allow for any one individual to communicate across the VTCs without having to leave their seat.

Microphones must be capable of being utilized for both NVTC and SVTC. The micro-phone/speaker configuration will provide the greatest audio range and clarity throughout the room as system design provides, ensuring audio feedback, noise and interference is minimal or nonexistent across the system’s volume and sensitivity range.

g. Phone Conference: Contractor will ensure that the GFR BIAMP Tesira HD-2 dialer connects to the matrix equipment/control panels and overhead speakers.

h. Programming. Contractor will program all devices, including existing CISCO codecs, ensuring they meet intended specifications and operability. A programmed codec is required on the SIPR portion of the SVTC, not the NIPR portion. Contractor will provide programming code and up-to-date schematics/diagrams detailing system connections upon project completion.

i. Mission control area. Contractor will develop and install a “mission control” area. Users must be able to control, at minimum, four monitors from a single computer in the mission control area. Each monitor will serve as a separate display input into the control panels and videowall. This will allow the control of a Common Operating Picture by a single operator.

j. DISA Compliance: Contractor will provide confirmation that only DISA-approved equipment will be procured under this contract. The Security Technical Implementation Guide (STIG) process is detailed here: https://www.cyber.mil/stigs/vendor-process

k. Other requirements.

i. Contractor will be responsible for any new cabling, wiring, and connectors where needed.

ii. Contractor will be responsible for routing all required cables and installing connectors for connection into the system.

iii. Contractor will be responsible for mounting/installing/integrating all new components to existing system and be responsible for reprogramming any and all existing components to ensure functionality of the entire system.

iv. The contractor will coordinate with the 87 CS to ensure all Information Assurance (IA) controls are met as needed. This includes but is not limited to: all EMSEC controls, ensuring approved products are utilized when required, and design approval before installation is performed. Failure to ensure that all IA requirements are met will result in correction by the contractor at their expense.

v. Contractor will be responsible for moving the GFE IPS container into the location determined best suited to house the SVTC. Location will be in the corner of the room, behind the mission control seat.

3. Government Furnished Equipment. Contractor shall ensure the equipment integrates seamlessly with the following existing equipment and systems

a. 15-panel display wall

i. Equipment must be configured such that the 15-panel wall can be tailored, as needed, to provide a Common Operating Picture pulling from multiple sources displayed simultaneously.

ii. The equipment must include flexible programming to allow multiple display options on how given sources are portrayed on the 15-panel wall.

iii. Contractor will ensure the ability to display secured and non-secured data on the video display wall while meeting all communications security (COMSEC) and emission security (EMSEC) requirements. Secured and non-secured data will not be shown concurrently. All screens will show secured or non-secured data only.

b. Two Cisco Codecs

i. One codec is intended for NVTC, while the other is intended SVTC.

ii. Both SVTC and NVTC, through the contractor-furnished control panels, must allow a user to select the given computer input and the desired display output projected onto the 15-panel wall.

c. Speaker systems. Existing speakers must be capable of playing audio from any given source.

d. List of government furnished equipment:

Description Count 15 Panel Video Wall (Samsung VM55B-U panels with HDMI & DP connections) 1 Room Kit EQ w/Codec EQ No-Radio for TAA 2 Power Cord for United States of America 2m 10A 4 Cisco Room Navigator-Table Stand, First Light (White) 2 Pan-Tilt-Zoom 12x Camera 2 Cisco Codec EQ unit No-Radio for TAA 2 Trusted Systems GSA Class 5 IPS Container, 28Hx27Wx45D, 1,145 lbs empty, X10 lock, thermostatically controlled forced air-cooling system

BIAMP Tesira HD-1 dialer 1

e. List of equipment to be provided by the Contractor

Description Transmitter/receiver/matrix equipment (example: Crestron) to support 15 different sources capable of transmitting to the 15-panel wall in multiple different layouts.

2 control panels to allow control of the display wall and its inputs from two different locations within the room Microphone solution/equipment to allow communication via both NVTC and SVTC.

Four 27” monitors for the Mission Control Area Brackets to mount the Cisco Pan-Tilt-Zoom 12x Cameras

4. Period of Performance: The period of performance shall be determined by the winning contractor bid but should not exceed 180 days after the date of contract. All work including installation, training, testing and acceptance shall be completed within this timeframe.

5. Site Maintenance: The Contractor shall maintain work areas in a neat, clean, and safe condition.

The Contractor shall be responsible for providing, installing, and the removal of any temporary signage, barriers, barricade tape, etc. Which may be required to control pedestrian and/or vehicle traffic in the work area.

6. Cleanup: The Contractor shall collect all trash, debris, refuse, garbage, etc., which is generated and place it in appropriate containers with lids or approved covers daily. The aforementioned materials shall be removed from the site by appropriate means daily, unless otherwise approved by the CO. Disposal shall be outside the limits of government property.

7. Storage and Parking: Contractor storage and parking shall be near the job site or as designated by the PM. Limited storage may be available to contractor upon request. Storage of materials shall be coordinated with the PM. The Contractor shall keep all PM approved storage areas free of debris, refuse, spills, leaks, stains, splashes and excessive materials. All storage areas shall be maintained in a neat, clean, and safe condition.

8. Commercial Warranty: The Contractor agrees that the supplies/equipment or services furnished under this contract shall be covered by the manufacturer’s warranties. The printed terms and conditions of such warranties shall be provided to the Government with the delivery of any supplies/equipment or services covered.

9. Quality Control: The Contractor shall develop a Quality Control Plan (QCP) to include an adequate inspection system, safety, and security. Inspections shall be performed to monitor the contract work. The Contractor shall maintain Quality Control (QC) inspection records and make them available to the CO and PM upon request.

10. Local Communications Support: It is agreed that the local communications squadron’s support is limited to ensuring connectivity from the CODEC back to the AFNET network switch.

11. Operational Security: The contractor shall be responsible for safeguarding military information as outlined by the JB MDL Commander. Contractor personnel will not take photographs of military facilities, equipment or personnel unless cleared through the proper channels

12. Records Management: The Contractor shall manage all data created for Government use or legally controlled by the Government, in support of the functional activity or required by Air Force publication, IAW with the AF records management procedures in Air Force Instruction (AFI) 33 - 322, Records Management Program, paragraph 10, Air Force Manual (AFMAN) 37-123, paragraph 7.4, Air Force Manual (AFMAN) 37-138, paragraph 2.13, and the Air Force Records Disposition Schedule (AF RDS) located at https://afrims.amc.af.mil/rds_series.cfm or http://www.amc.af.mil/shared/media/document/AFD- 060803-003.pdf.

13. Quality Assurance: All work is subject to inspection, test by the Government at all places, and at all reasonable times ensure compliance with the terms of the contract.

a. Inspections and tests are for the sole benefit of the Government and do not:

http://www.amc.af.mil/shared/media/document/AFD-060803-003.pdf http://www.amc.af.mil/shared/media/document/AFD-060803-003.pdf

i. Relieve the Contractor of responsibility for providing adequate quality control measures.

ii. Relieve the Contractor of responsibility for damage to or loss of the material before acceptance.

iii. Constitute or imply acceptance; or effect the continuing rights of the Government after acceptance of the completed work

iv. The presence or absence of a government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the CO's written authorization.

14. Special Qualifications: The design and programming shall be accomplished under direction and supervision with an individual with project management experience, licensing and certification sufficient to ensure installation meets all government and testing standards, and all operational requirements. The physical installation of equipment will be accomplished installers with experience installing audio/video equipment. The work shall be in strict accordance with the contract documents and standards of the industry. For those trades not requiring a license, the Contractor shall ensure qualified and experienced personnel in their trades are assigned to government project work.

15. Labeling: All terminations shall be clearly labeled. To include a list of all the identified terminations and where they are located.

16. Work/Storage: The Contractor shall not work or store materials in a manner that would hinder or otherwise block pedestrian circulation to exit corridors and exit doors in the event of an emergency or fire.