Food_Service_Draft_Solicitation_-_FINAL_13_Nov_14.pdf
PDF 2 MB Posted
- Attached to
- Dix Full Food Service Federal contract opportunity
- Solicitation number
- FA4484-15-R-0005
About this file
Solicitation - Dix Food Service
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Food_Service_Solicitation_-_Amendment_3-_15_Dec_14.pdf | ||
| Food_Service_Solicitation_-_Amendment_3_Modification_15_Dec_14.pdf | ||
| Questions_and_Answers_-_15_Dec_14.pdf | ||
| Food_Service_Draft_Solicitation_-_Amendment_2_Modification_11_Dec_14.pdf | ||
| Food_Service_PWS_4_Dec_14_-_Revision_1.pdf | ||
| Food_Service_Draft_Solicitation_-_Modification_1_-_9_Dec_14.pdf | ||
| CBA_Supplement_-_2015.pdf | ||
| Food_Service_Draft_Solicitation_-_Amendment_1-_9_Dec_14.pdf | ||
| Questions_and_Answers_-_4_Dec_14.pdf | ||
| Site_Visit_Minutes_-_2_Dec_14.pdf | ||
| Food_Service_PWS_v4.0_6_Nov_14_-_FINAL.pdf | ||
| Dix_Food_Service_CBA_-_Feb_2014.pdf | ||
| Past_Perf_Questionnaire_22_Oct_14.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4484-15-R-0005
87 CONS/LGC
2402 VANDENBERG AVE
JB MCGUIRE-DIX-LAKEHURST NJ 08641
609-754-3735
UNDER DPAS (15 CFR 700)
11. DELIVERY FOR FOB
RFQ
SEE SCHEDULE
14. METHOD OF SOLICITATION
IFB RFP
CODE
SEE ADDENDUM
BLOCK IS MARKED
DESTINATION UNLESS
12. DISCOUNT TERMS
(No Collect Calls)
35500000
13b. RATING
13a. THIS CONTRACT IS A RATED ORDER
X
CODE
FA4484-15-R-0005 13-Nov-2014
b. TELEPHONE NUMBER
609-754-4768
8. OFFER DUE DATE/LOCAL TIME
03:00 PM 17 Dec 2014
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV 3/2005)
Prescribed by GSA
FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER) 31c. DATE SIGNED
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
22. UNIT 23. UNIT PRICE 24. AMOUNT21. QUANTITY
CODE 10. THIS ACQUISITION IS
UNRESTRICTED
FAX: NAICS:
TEL:
CODE 18a. PAYMENT WILL BE MADE BYOFFEROR
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TEL.
FA4484
SIZE STD:
9. ISSUED BY
FACILITY
CODE
17a.CONTRACTOR/
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
15. DELIVER TO CODE F3A390 16. ADMINISTERED BY
87 FSS/SVFA-F3A390
BETTY PERCY
2905 TUSKEGEE AIRMAN AVE
MCGUIRE AFB NJ 08641-5012
TEL: 609-754-4046 FAX:
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
MICHAEL R. PETTY
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
19. ITEM NO. 20. SCHEDULE OF SUPPLIES/ SERVICES
SEE SCHEDULE
722310
TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS
SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS
SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.
SB
HUBZONE SB
SET ASIDE: 100 % FOR
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
TEL: EMAIL:
1 COPIES
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
.OFFER DATED YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 29. AWARD OF CONTRACT: REFERENCE
X
8(A)
SVC-DISABLED VET-OWNED SB
EMERGING SB
X
X
Section SF 30 - BLOCK 14 CONTINUATION PAGE
SUMMARY OF PRICES FOR BASE PERIOD AND FOUR OPTION PERIODS
BASE PERIOD (1 May 2015 – 30 April 2016) $_____________
OPTION YEAR 1 (1 May 2016 – 30 April 2017) $_____________
OPTION YEAR 2 (1 May 2017 – 30 April 2018) $_____________
OPTION YEAR 3 (1 May 2018 – 30 April 2019) $_____________
OPTION YEAR 4 (1 May 2019 – 30 April 2020) $_____________
GRAND TOTAL (BASE PLUS FOUR OPTION YEARS) $_____________
Note 1: Complete unit prices and total amounts. Total must be exact. Please round off to the nearest cent.
Note 2: In case of variation between the unit price and estimated net amount, unit price will be considered the offer.
Note 3: Failure to provide pricing on all CLINs will be considered a non-conforming proposal and will preclude the proposal from any further award consideration.
Note 4: Clauses and provisions in this document will be numbered in sequence, but will not necessarily appear in consecutive order.
Note 5: Instructions to offerors for commercial acquisitions, offeror representations and certification- commercial items and proposal preparation instructions will be physically removed from any resultant award, but will be deemed to be incorporated by reference in the award.
Section SF 1449 - CONTINUATION SHEET
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
5610 - Base Period 1 May 15 - 30 Apr 16
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5610 is a primary dining facility and is anticipated to be open 365 days per year during the base period. See the Dix Food
Service PWS specific requirements and hours of operation. The contractor shall provide a fixed price for the DAILY operation of dining facility 5610 IAW all the requirements of the PWS. Dining facility 5610 is funded with 20% Operations and
Maintenance (O&M) funds and 80% Overseas Contingency Operating funds
(OCO). Therefore, the contractor is required to break out the price total for each associated SLIN for 5610 using the 80/20 split. Please read each line item carefully to identify the correct funding type.
FOB: Destination
ESTIMATED
NET AMT
UNIT UNIT PRICE ESTIMATED AMOUNT
0001AA 365 Days
Operate Dining Facility 5610 - OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5610 IAW all the requirements of the PWS. This line item represents 80% of the daily total cost to operate 5610. The remaining 20% shall be captured in
SLIN 0001AB.
UNIT UNIT PRICE ESTIMATED AMOUNT
0001AB 365 Days
Operate Dining Facility 5610 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5610 IAW all the requirements of the PWS. This line item represents 20% of the daily total cost to operate 5610. The remaining 80% shall be captured in
SLIN 0001AA.
UNIT UNIT PRICE ESTIMATED AMOUNT
0001AC 6 Each
Short Range Closure of 5610 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5610. The remaining 20% shall be captured in SLIN 0001AD.
UNIT UNIT PRICE ESTIMATED AMOUNT
0001AD 6 Each
Short Range Closure of 5610 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for less than 30 days in accordance with paragraph 1.7.5.1 of the PWS. This line item represents 20% of the daily total cost to operate 5610. The remaining 80% shall be captured in SLIN 0001AC.
UNIT UNIT PRICE ESTIMATED AMOUNT
0001AE 1 Each
Long Range Closure of 5610 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5610. The remaining 20% shall be captured in SLIN 0001AF.
UNIT UNIT PRICE ESTIMATED AMOUNT
0001AF 1 Each
Long Range Closure of 5610 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for more than 30 days in accordance with paragraph 1.7.5.2 of the PWS. This line item represents 20% of the daily total cost to close 5610. The remaining 80% shall be captured in SLIN 0001AE.
UNIT UNIT PRICE ESTIMATED AMOUNT
0001AG 6 Each
Open Dining Facility 5610 - OCO Funds
FFP
The contractor shall provide a fixed price to open dining facility 5610 in accordance with the PWS. This line item represents 80% of the daily total cost to open 5610. The remaining 20% shall be captured in SLIN 0001AH.
UNIT UNIT PRICE ESTIMATED AMOUNT
0001AH 6 Each
Open Dining Facility 5610 - O&M Funds
FFP
The contractor shall provide a fixed price to open dining facility 5610 in accordance with the PWS. This line item represents 20% of the daily total cost to open 5610. The remaining 80% shall be captured in SLIN 0001AG.
UNIT UNIT PRICE ESTIMATED AMOUNT
5904 - Base Period 1 May 15 - 30 Apr 16
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5904 is a primary dining facility and is anticipated to be open 365 days per year during the base period. See the Dix Food
Service PWS specific requirements and hours of operation. The contractor shall provide a fixed price for the DAILY operation of dining facility 5904 IAW all the requirements of the PWS. Dining facility 5904 is funded with 20% Operations and
Maintenance (O&M) funds and 80% OCO funds. Therefore, the contractor is required to break out the price total for each associated SLIN for 5904 using the
80/20 split. Please read each line item carefully to identify the correct funding type.
UNIT UNIT PRICE ESTIMATED AMOUNT
0002AA 365 Days
Operate Dining Facility 5904 - OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5904 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5904. The remaining 20% shall be captured in SLIN
0002AB.
UNIT UNIT PRICE ESTIMATED AMOUNT
0002AB 365 Days
Operate Dining Facility 5904 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5904 in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5904. The remaining 80% shall be captured in SLIN
0002AA.
UNIT UNIT PRICE ESTIMATED AMOUNT
0002AC 1 Each
Short Range Closure of 5904- OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5904. The remaining 20% shall be captured in SLIN 0002AD.
UNIT UNIT PRICE ESTIMATED AMOUNT
0002AD 1 Each
Short Range Closure of 5904 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904 for less than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5904. The remaining 80% shall be captured in SLIN 0002AC.
UNIT UNIT PRICE ESTIMATED AMOUNT
0002AE 1 Each
Long Range Closure of 5904 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5904. The remaining 20% shall be captured in SLIN 0002AF.
UNIT UNIT PRICE ESTIMATED AMOUNT
0002AF 1 Each
Long Range Closure of 5904 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904 for more than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to close 5904. The remaining 80% shall be captured in SLIN 0002AE.
UNIT UNIT PRICE ESTIMATED AMOUNT
0002AG 6 Each
Open Dining Facility 5904 - OCO Funds
FFP
The contractor shall provide a fixed price to open dining facility 5904 in accordance with the PWS. This line item represents 80% of the daily total cost to open 5904. The remaining 20% shall be captured in SLIN 0002AH.
UNIT UNIT PRICE ESTIMATED AMOUNT
0002AH 6 Each
Open Dining Facility 5904 - O&M Funds
FFP
The contractor shall provide a fixed price to open dining facility 5904 in accordance with the PWS. This line item represents 20% of the daily total cost to open 5904. The remaining 80% shall be captured in SLIN 0002AG.
UNIT UNIT PRICE ESTIMATED AMOUNT
5986 - Base Period 1 May 15 - 30 Apr 16
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5986 is anticipated to be open for 183 days per year for overflow and personnel surges. This dining facility will only be opened at the direction of the contracting officer. The contractor shall provide a fixed price for the DAILY operation of dining facility 5986 IAW all the requirements of the
PWS. Dining facility 5986 is funded with 20% Operations and Maintenance
(O&M) funds and 80% OCO funds. Therefore, the contractor is required to break out the price total for each associated SLIN for 5986 using the 80/20 split. Please read each line item carefully to identify the correct funding type.
UNIT UNIT PRICE ESTIMATED AMOUNT
0003AA 183 Days
Operate Dining Facility 5986- OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5986 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5986. The remaining 20% shall be captured in SLIN
0003AB.
UNIT UNIT PRICE ESTIMATED AMOUNT
0003AB 183 Days
Operate Dining Facility 5986 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5986 in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5986 The remaining 80% shall be captured in SLIN
0003AA.
UNIT UNIT PRICE ESTIMATED AMOUNT
0003AC 24 Each
Short Range Closure of 5986 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5986. The remaining 20% shall be captured in SLIN 0003AD.
UNIT UNIT PRICE ESTIMATED AMOUNT
0003AD 24 Each
Short Range Closure of 5986 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for less than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5986. The remaining 80% shall be captured in SLIN 0003AC.
UNIT UNIT PRICE ESTIMATED AMOUNT
0003AE 12 Each
Long Range Closure of 5986 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5986. The remaining 20% shall be captured in SLIN 0003AF.
UNIT UNIT PRICE ESTIMATED AMOUNT
0003AF 12 Each
Long Range Closure of 5986 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for more than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to close 5986. The remaining 80% shall be captured in SLIN 0003AE.
UNIT UNIT PRICE ESTIMATED AMOUNT
0003AG 24 Each
Open Dining Facility 5986 - OCO Funds
FFP
The contractor shall provide a fixed price to open dining facility 5986 in accordance with the PWS. This line item represents 80% of the daily total cost to open 5986. The remaining 20% shall be captured in SLIN 0003AH.
UNIT UNIT PRICE ESTIMATED AMOUNT
0003AH 24 Each
Open Dining Facility 5986 - O&M Funds
FFP
The contractor shall provide a fixed price to open dining facility 5986 in accordance with the PWS. This line item represents 20% of the daily total cost to open 5986. The remaining 80% shall be captured in SLIN 0003AG.
UNIT UNIT PRICE ESTIMATED AMOUNT
5640 - Base Period 1 May 15 - 30 Apr 16
FFP
Dining facility 5640 is anticipated to be open for 30 days per year for overflow and personnel surges. This dining facility will only be opened at the direction of the contracting officer. The contractor shall provide a fixed price for the DAILY operation of dining facility 5640 IAW all the requirements of the PWS. Dining facility 5640 is funded with 20% Operations and Maintenance (O&M) funds and
80% OCO funds. Therefore, the contractor is required to break out the price total for each associated SLIN for 5640 using the 80/20 split. Please read each line item
UNIT UNIT PRICE ESTIMATED AMOUNT
0004AA 30 Days
Operate Dining Facility 5640 - OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5640 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5640. The remaining 20% shall be captured in SLIN
0004AB.
UNIT UNIT PRICE ESTIMATED AMOUNT
0004AB 30 Days
Operate Dining Facility 5640 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5640 IAW all the requirements of the PWS. This line item represents 20% of the daily total cost to operate 5640. The remaining 80% shall be captured in
SLIN 0004AA
UNIT UNIT PRICE ESTIMATED AMOUNT
0004AC 12 Each
Short Range Closure of 5640 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5640. The remaining 20% shall be captured in SLIN 0004AD.
UNIT UNIT PRICE ESTIMATED AMOUNT
0004AD 12 Each
Short Range Closure of 5640 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for less than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5640. The remaining 80% shall be captured in SLIN 0004AC.
UNIT UNIT PRICE ESTIMATED AMOUNT
0004AE 6 Each
Long Range Closure of 5640 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5640. The remaining 20% shall be captured in SLIN 0004AF.
UNIT UNIT PRICE ESTIMATED AMOUNT
0004AF 6 Each
Long Range Closure of 5640 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for more than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to close 5640. The remaining 80% shall be captured in SLIN 0004AE.
UNIT UNIT PRICE ESTIMATED AMOUNT
5509 - Base Period 1 May 15 - 30 Apr 16
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5509 is the Army’s Officer Education School and anticipated to be open approximately 92 days per year typically May through
Aug.
UNIT UNIT PRICE ESTIMATED AMOUNT
0005AA 92 Days
Operate Dining Facility 5509
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5509 in accordance with the PWS.
UNIT UNIT PRICE ESTIMATED AMOUNT
0005AB 1 Each
Short Range Closure of 5509
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5509 for less than 30 days in accordance with the PWS.
UNIT UNIT PRICE ESTIMATED AMOUNT
0005AC 1 Each
Long Range Closure of 5509
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5509 for more than 30 days in accordance with the PWS.
UNIT UNIT PRICE ESTIMATED AMOUNT
0005AD 1 Each
Open Dining Facility 5509
FFP
The contractor shall provide a fixed price to open dining facility 5509 in accordance with the PWS.
UNIT UNIT PRICE ESTIMATED AMOUNT
5517- Base Period 1 May 15 - 30 Apr 16
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5517 services the Army Noncommissioned
Officer School is anticipated to be open 275 days per year (approximately 3 weeks per month), all year around.
UNIT UNIT PRICE ESTIMATED AMOUNT
0006AA 275 Days
Operate Dining Facility 5517
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5517 in accordance with the PWS.
UNIT UNIT PRICE ESTIMATED AMOUNT
0006AB 12 Each
Short Range Closure of 5517
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5517 for less than 30 days in accordance with the PWS.
UNIT UNIT PRICE ESTIMATED AMOUNT
0006AC 1 Each
Long Range Closure of 5517
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5517 for more than 30 days in accordance with the PWS.
UNIT UNIT PRICE ESTIMATED AMOUNT
0006AD 12 Each
Open Dining Facility 5517
FFP
The contractor shall provide a fixed price to open dining facility 5610 in
UNIT UNIT PRICE ESTIMATED AMOUNT
COL - Base Period 1 May 15 - 30 Apr 16
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - The Contingency Operating Location (COL) is anticipated to be open 183 days per year. This dining facility is located 18 miles east of the Dix area and is comprised of two general purpose tents (18 x 36). The contractor is required to prepare/serve meals for breakfast and dinner and issue operational rations for lunch.
UNIT UNIT PRICE ESTIMATED AMOUNT
0007AA 183 Days
Daily Operation of the COL
FFP
The contractor shall provide a fixed price for the DAILY operation of the COL in
UNIT UNIT PRICE ESTIMATED AMOUNT
0007AB 10 Hours
Extended Hours of Operation for the COL
FFP
The contractor shall provide a HOURLY price for extended hours of operation for the COL beyond serving times identified in appendix 3 of the PWS. This price shall reflect the TOTAL price of all labor/supplies etc. to run the entire COL operation per hour past the stated hours of operation. See the PWS for extended hours of operation requirements. Note this CLIN is ONLY for the COL.
UNIT UNIT PRICE ESTIMATED AMOUNT
0008 70 Hours
Extended Hours of Operation - Base Yr
FFP
The contractor shall provide a HOURLY price to extend the dining facility hours of operation beyond serving times identified in appendix 3 of the PWS. This price shall reflect the TOTAL price of all labor/supplies etc. to continue the entire dining facility operation on a per hour basis past the stated hours of operation. This is
NOT an individual labor rate. See the PWS for extended hours of operation requirements. Extended hours of operation for this CLIN apply to dining facilities
5610, 5904, 5640, 5986, 5517 and 5509. Note this CLIN does not include the COL which is priced separately.
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5610 - Option Yr 1 1 May 16 - 30 Apr 17
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5610 is a primary dining facility and is anticipated to be open 365 days per year during the base period. See the Dix Food
Service PWS specific requirements and hours of operation. The contractor shall provide a fixed price for the DAILY operation of dining facility 5610 IAW all the requirements of the PWS. Dining facility 5610 is funded with 20% Operations and
Maintenance (O&M) funds and 80% Overseas Contingency Operating funds
(OCO). Therefore, the contractor is required to break out the price total for each associated SLIN for 5610 using the 80/20 split. Please read each line item
UNIT UNIT PRICE ESTIMATED AMOUNT
1001AA 365 Days
OPTION Operate Dining Facility 5610 - OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5610 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5610. The remaining 20% shall be captured in SLIN
1001AB.
UNIT UNIT PRICE ESTIMATED AMOUNT
1001AB 365 Days
OPTION Operate Dining Facility 5610 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5610 in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5610. The remaining 80% shall be captured in SLIN
1001AA.
UNIT UNIT PRICE ESTIMATED AMOUNT
1001AC 6 Each
OPTION Short Range Closure of 5610 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5610. The remaining 20% shall be
UNIT UNIT PRICE ESTIMATED AMOUNT
1001AD 6 Each
OPTION Short Range Closure of 5610 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for less than 30 days in accordance the PWS. This line item represents 20% of the daily total cost to operate 5610. The remaining 80% shall be captured in SLIN 1001AC.
UNIT UNIT PRICE ESTIMATED AMOUNT
1001AE 1 Each
OPTION Long Range Closure of 5610 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5610. The remaining 20% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
1001AF 1 Each
OPTION Long Range Closure of 5610 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for more than 30 days in accordance the PWS. This line item represents 20% of the daily total cost to close 5610. The remaining 80% shall be captured in SLIN 1001AE.
UNIT UNIT PRICE ESTIMATED AMOUNT
1001AG 6 Each
OPTION Open Dining Facility 5610 - OCO Funds
FFP
The contractor shall provide a fixed price to open dining facility 5610 in accordance with the PWS. This line item represents 80% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
1001AH 6 Each
OPTION Open Dining Facility 5610 - O&M Funds
FFP
The contractor shall provide a fixed price to open dining facility 5610 in accordance with the PWS. This line item represents 20% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5904 - Option Yr 1 1 May 16 - 30 Apr 17
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5904 is a primary dining facility and is anticipated to be open 365 days per year during the base period. See the Dix Food
Service PWS specific requirements and hours of operation. The contractor shall provide a fixed price for the DAILY operation of dining facility 5904 IAW all the requirements of the PWS. Dining facility 5904 is funded with 20% Operations and
Maintenance (O&M) funds and 80% OCO funds. Therefore, the contractor is required to break out the price total for each associated SLIN for 5904 using the
80/20 split. Please read each line item carefully to identify the correct funding
UNIT UNIT PRICE ESTIMATED AMOUNT
1002AA 365 Days
OPTION Operate Dining Facility 5904 - OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5904 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5904. The remaining 20% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
1002AB 365 Days
OPTION Operate Dining Facility 5904 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5904 in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5904. The remaining 80% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
1002AC 1 Each
OPTION Short Range Closure of 5904- OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5904. The remaining 20% shall be
UNIT UNIT PRICE ESTIMATED AMOUNT
1002AD 1 Each
OPTION Short Range Closure of 5904 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904 for less than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5904. The remaining 80%
UNIT UNIT PRICE ESTIMATED AMOUNT
1002AE 1 Each
OPTION Long Range Closure of 5904 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5904. The remaining 20% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
1002AF 1 Each
OPTION Long Range Closure of 5904 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904 for more than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to close 5904. The remaining 80% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
1002AG 6 Each
OPTION Open Dining Facility 5904 - OCO Funds
FFP
The contractor shall provide a fixed price to open dining facility 5904 in accordance with the PWS. This line item represents 80% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
1002AH 6 Each
OPTION Open Dining Facility 5904 - O&M Funds
FFP
The contractor shall provide a fixed price to open dining facility 5904 in accordance with the PWS. This line item represents 20% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5986 - Option Yr 1 1 May 16 - 30 Apr 17
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5986 is anticipated to be open for 183 days per year for overflow and personnel surges. This dining facility will only be opened at the direction of the contracting officer. The contractor shall provide a fixed price for the DAILY operation of dining facility 5986 IAW all the requirements of the
PWS. Dining facility 5986 is funded with 20% Operations and Maintenance
(O&M) funds and 80% OCO funds. Therefore, the contractor is required to break out the price total for each associated SLIN for 5986 using the 80/20 split. Please
UNIT UNIT PRICE ESTIMATED AMOUNT
1003AA 183 Days
OPTION Operate Dining Facility 5986- OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5986 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5986. The remaining 20% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
1003AB 183 Days
OPTION Operate Dining Facility 5986 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5986 in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5986 The remaining 80% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
1003AC 24 Each
OPTION Short Range Closure of 5986 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5986. The remaining 20% shall be
UNIT UNIT PRICE ESTIMATED AMOUNT
1003AD 24 Each
OPTION Short Range Closure of 5986 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for less than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5986. The remaining 80%
UNIT UNIT PRICE ESTIMATED AMOUNT
1003AE 12 Each
OPTION Long Range Closure of 5986 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5986. The remaining 20% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
1003AF 12 Each
OPTION Long Range Closure of 5986 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for more than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to close 5986. The remaining 80% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
1003AG 24 Each
OPTION Open Dining Facility 5986 - OCO Funds
FFP
The contractor shall provide a fixed price to open dining facility 5986 in accordance with the PWS. This line item represents 80% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
1003AH 24 Each
OPTION Open Dining Facility 5986 - O&M Funds
FFP
The contractor shall provide a fixed price to open dining facility 5986 in accordance with the PWS. This line item represents 20% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5640 - Option Yr 1 1 May 16 - 30 Apr 17
FFP
Dining facility 5640 is anticipated to be open for 30 days per year for overflow and personnel surges. This dining facility will only be opened at the direction of the contracting officer. The contractor shall provide a fixed price for the DAILY operation of dining facility 5640 IAW all the requirements of the PWS. Dining facility 5640 is funded with 20% Operations and Maintenance (O&M) funds and
80% OCO funds. Therefore, the contractor is required to break out the price total for each associated SLIN for 5640 using the 80/20 split. Please read each line item
UNIT UNIT PRICE ESTIMATED AMOUNT
1004AA 30 Days
OPTION Operate Dining Facility 5640 - OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5640 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5640. The remaining 20% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
1004AB 30 Days
OPTION Operate Dining Facility 5640 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5640 IAW all the requirements of the PWS. This line item represents 20% of the daily total cost to operate 5640. The remaining 80% shall be captured in
SLIN 1004AA
UNIT UNIT PRICE ESTIMATED AMOUNT
1004AC 12 Each
OPTION Short Range Closure of 5640 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5640. The remaining 20% shall be
UNIT UNIT PRICE ESTIMATED AMOUNT
1004AD 12 Each
OPTION Short Range Closure of 5640 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for less than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5640. The remaining 80%
UNIT UNIT PRICE ESTIMATED AMOUNT
1004AE 6 Each
OPTION Long Range Closure of 5640 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5640. The remaining 20% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
1004AF 6 Each
OPTION Long Range Closure of 5640 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for more than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to close 5640. The remaining 80% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5509 - Option Yr 1 1 May 16 - 30 Apr 17
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5509 is the Army’s Officer Education School and anticipated to be open approximately 92 days per year typically May through
UNIT UNIT PRICE ESTIMATED AMOUNT
1005AA 92 Days
OPTION Operate Dining Facility 5509
FFP
The contractor shall provide a fixed price for the DAILY operation of dining
UNIT UNIT PRICE ESTIMATED AMOUNT
1005AB 1 Each
OPTION Short Range Closure of 5509
FFP
The contractor shall provide a fixed price to perform the tasks required to close
UNIT UNIT PRICE ESTIMATED AMOUNT
1005AC 1 Each
OPTION Long Range Closure of 5509
FFP
The contractor shall provide a fixed price to perform the tasks required to close
UNIT UNIT PRICE ESTIMATED AMOUNT
1005AD 1 Each
OPTION Open Dining Facility 5509
FFP
The contractor shall provide a fixed price to open dining facility 5509 in
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5517- Option Yr 1 1 May 16 - 30 Apr 17
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5517 services the Army Noncommissioned
Officer School is anticipated to be open 275 days per year (approximately 3 weeks
UNIT UNIT PRICE ESTIMATED AMOUNT
1006AA 275 Days
OPTION Operate Dining Facility 5517
FFP
The contractor shall provide a fixed price for the DAILY operation of dining
UNIT UNIT PRICE ESTIMATED AMOUNT
1006AB 12 Each
OPTION Short Range Closure of 5517
FFP
The contractor shall provide a fixed price to perform the tasks required to close
UNIT UNIT PRICE ESTIMATED AMOUNT
1006AC 1 Each
OPTION Long Range Closure of 5517
FFP
The contractor shall provide a fixed price to perform the tasks required to close
UNIT UNIT PRICE ESTIMATED AMOUNT
1006AD 12 Each
OPTION Open Dining Facility 5517
FFP
The contractor shall provide a fixed price to open dining facility 5610 in
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION COL - Option Yr 1 1 May 16 - 30 Apr 17
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - The Contingency Operating Location (COL) is anticipated to be open 183 days per year. This dining facility is located 18 miles east of the Dix area and is comprised of two general purpose tents (18 x 36). The contractor is required to prepare/serve meals for breakfast and dinner and issue operational
UNIT UNIT PRICE ESTIMATED AMOUNT
1007AA 183 Days
OPTION Daily Operation of the COL
FFP
The contractor shall provide a fixed price for the DAILY operation of the COL in
UNIT UNIT PRICE ESTIMATED AMOUNT
1007AB 10 Hours
OPTION Extended Hrs COL - Option Yr 1
FFP
The contractor shall provide a HOURLY price for extended hours of operation for the COL beyond serving times identified in appendix 3 of the PWS. This price shall reflect the TOTAL price of all labor/supplies etc. to run the entire COL operation per hour past the stated hours of operation. See the PWS for extended
UNIT UNIT PRICE ESTIMATED AMOUNT
1008 70 Hours
OPTION Extended Hrs of Operation - Option Yr 1
FFP
The contractor shall provide a HOURLY price to extend the dining facility hours of operation beyond serving times identified in appendix 3 of the PWS. This price shall reflect the TOTAL price of all labor/supplies etc. to continue the entire dining facility operation on a per hour basis past the stated hours of operation. This is
NOT an individual labor rate. See the PWS for extended hours of operation requirements. Extended hours of operation for this CLIN apply to dining facilities
5610, 5904, 5640, 5986, 5517 and 5509. Note this CLIN does not include the COL
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5610 - Option Yr 2 1 May 17 - 30 Apr 18
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5610 is a primary dining facility and is anticipated to be open 365 days per year during the base period. See the Dix Food
Service PWS specific requirements and hours of operation. The contractor shall provide a fixed price for the DAILY operation of dining facility 5610 IAW all the requirements of the PWS. Dining facility 5610 is funded with 20% Operations and
Maintenance (O&M) funds and 80% Overseas Contingency Operating funds
(OCO). Therefore, the contractor is required to break out the price total for each associated SLIN for 5610 using the 80/20 split. Please read each line item
UNIT UNIT PRICE ESTIMATED AMOUNT
2001AA 365 Days
OPTION Operate Dining Facility 5610 - OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5610 IAW all the requirements of the PWS. This line item represents 20% of the daily total cost to operate 5610. The remaining 20% shall be captured in
SLIN 0001AB.
UNIT UNIT PRICE ESTIMATED AMOUNT
2001AB 365 Days
OPTION Operate Dining Facility 5610 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5610 IAW all the requirements of the PWS. This line item represents 20% of the daily total cost to operate 5610. The remaining 80% shall be captured in
SLIN 0001AA.
UNIT UNIT PRICE ESTIMATED AMOUNT
2001AC 6 Each
OPTION Short Range Closure of 5610 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5610. The remaining 20% shall be
UNIT UNIT PRICE ESTIMATED AMOUNT
2001AD 6 Each
OPTION Short Range Closure of 5610 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for less than 30 days in accordance with paragraph 1.7.5.1 of the PWS. This line item represents 20% of the daily total cost to operate 5610. The remaining 80% shall be captured in SLIN 0001AC.
UNIT UNIT PRICE ESTIMATED AMOUNT
2001AE 1 Each
OPTION Long Range Closure of 5610 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5610. The remaining 20% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
2001AF 1 Each
OPTION Long Range Closure of 5610 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5610 for more than 30 days in accordance with paragraph 1.7.5.2 of the PWS. This line item represents 20% of the daily total cost to close 5610. The remaining 80% shall be captured in SLIN 0001AE.
UNIT UNIT PRICE ESTIMATED AMOUNT
2001AG 6 Each
OPTION Open Dining Facility 5610 - OCO Funds
FFP
The contractor shall provide a fixed price to open dining facility 5610 in accordance with the PWS. This line item represents 80% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
2001AH 6 Each
OPTION Open Dining Facility 5610 - O&M Funds
FFP
The contractor shall provide a fixed price to open dining facility 5610 in accordance with the PWS. This line item represents 20% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5904 - Option Yr 2 1 May 17 - 30 Apr 18
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5904 is a primary dining facility and is anticipated to be open 365 days per year during the base period. See the Dix Food
Service PWS specific requirements and hours of operation. The contractor shall provide a fixed price for the DAILY operation of dining facility 5904 IAW all the requirements of the PWS. Dining facility 5904 is funded with 20% Operations and
Maintenance (O&M) funds and 80% OCO funds. Therefore, the contractor is required to break out the price total for each associated SLIN for 5904 using the
80/20 split. Please read each line item carefully to identify the correct funding
UNIT UNIT PRICE ESTIMATED AMOUNT
2002AA 365 Days
OPTION Operate Dining Facility 5904 - OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5904 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5904. The remaining 20% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
2002AB 365 Days
OPTION Operate Dining Facility 5904 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5904 in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5904. The remaining 80% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
2002AC 1 Each
OPTION Short Range Closure of 5904- OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5904. The remaining 20% shall be
UNIT UNIT PRICE ESTIMATED AMOUNT
2002AD 1 Each
OPTION Short Range Closure of 5904 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904 for less than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5904. The remaining 80%
UNIT UNIT PRICE ESTIMATED AMOUNT
2002AE 1 Each
OPTION Long Range Closure of 5904 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5904. The remaining 20% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
2002AF 1 Each
OPTION Long Range Closure of 5904 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5904 for more than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to close 5904. The remaining 80% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
2002AG 6 Each
OPTION Open Dining Facility 5904 - OCO Funds
FFP
The contractor shall provide a fixed price to open dining facility 5904 in accordance with the PWS. This line item represents 80% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
2002AH 6 Each
OPTION Open Dining Facility 5904 - O&M Funds
FFP
The contractor shall provide a fixed price to open dining facility 5904 in accordance with the PWS. This line item represents 20% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5986 - Option Yr 2 1 May 17 - 30 Apr 18
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5986 is anticipated to be open for 183 days per year for overflow and personnel surges. This dining facility will only be opened at the direction of the contracting officer. The contractor shall provide a fixed price for the DAILY operation of dining facility 5986 IAW all the requirements of the
PWS. Dining facility 5986 is funded with 20% Operations and Maintenance
(O&M) funds and 80% OCO funds. Therefore, the contractor is required to break out the price total for each associated SLIN for 5986 using the 80/20 split. Please
UNIT UNIT PRICE ESTIMATED AMOUNT
2003AA 183 Days
OPTION Operate Dining Facility 5986- OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5986 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5986. The remaining 20% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
2003AB 183 Days
OPTION Operate Dining Facility 5986 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5986 in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5986 The remaining 80% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
2003AC 24 Each
OPTION Short Range Closure of 5986 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5986. The remaining 20% shall be
UNIT UNIT PRICE ESTIMATED AMOUNT
2003AD 24 Each
OPTION Short Range Closure of 5986 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for less than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5986. The remaining 80%
UNIT UNIT PRICE ESTIMATED AMOUNT
2003AE 12 Each
OPTION Long Range Closure of 5986 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5986. The remaining 20% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
2003AF 12 Each
OPTION Long Range Closure of 5986 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5986 for more than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to close 5986. The remaining 80% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
2003AG 24 Each
OPTION Open Dining Facility 5986 - OCO Funds
FFP
The contractor shall provide a fixed price to open dining facility 5986 in accordance with the PWS. This line item represents 80% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
2003AH 24 Each
OPTION Open Dining Facility 5986 - O&M Funds
FFP
The contractor shall provide a fixed price to open dining facility 5986 in accordance with the PWS. This line item represents 20% of the daily total cost to
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5640 - Option Yr 2 1 May 17 - 30 Apr 18
FFP
Dining facility 5640 is anticipated to be open for 30 days per year for overflow and personnel surges. This dining facility will only be opened at the direction of the contracting officer. The contractor shall provide a fixed price for the DAILY operation of dining facility 5640 IAW all the requirements of the PWS. Dining facility 5640 is funded with 20% Operations and Maintenance (O&M) funds and
80% OCO funds. Therefore, the contractor is required to break out the price total for each associated SLIN for 5640 using the 80/20 split. Please read each line item
UNIT UNIT PRICE ESTIMATED AMOUNT
2004AA 30 Days
OPTION Operate Dining Facility 5640 - OCO Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5640 in accordance with the PWS. This line item represents 80% of the daily total cost to operate 5640. The remaining 20% shall be captured in SLIN
UNIT UNIT PRICE ESTIMATED AMOUNT
2004AB 30 Days
OPTION Operate Dining Facility 5640 - O&M Funds
FFP
The contractor shall provide a fixed price for the DAILY operation of dining facility 5640 IAW all the requirements of the PWS. This line item represents 20% of the daily total cost to operate 5640. The remaining 80% shall be captured in
SLIN 2004AA
UNIT UNIT PRICE ESTIMATED AMOUNT
2004AC 12 Each
OPTION Short Range Closure of 5640 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for less than 30 days in accordance with the PWS. This line item represents 80% of the total cost to close 5640. The remaining 20% shall be
UNIT UNIT PRICE ESTIMATED AMOUNT
2004AD 12 Each
OPTION Short Range Closure of 5640 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for less than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to operate 5640. The remaining 80%
UNIT UNIT PRICE ESTIMATED AMOUNT
2004AE 6 Each
OPTION Long Range Closure of 5640 - OCO Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for more than 30 days in accordance with the PWS. This line item represents 80% of the daily total cost to close 5640. The remaining 20% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
2004AF 6 Each
OPTION Long Range Closure of 5640 - O&M Funds
FFP
The contractor shall provide a fixed price to perform the tasks required to close dining facility 5640 for more than 30 days in accordance with the PWS. This line item represents 20% of the daily total cost to close 5640. The remaining 80% shall
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION 5509 - Option Yr 2 1 May 17 - 30 Apr 18
FFP
THIS IS AN INFORMATIONAL CLIN ONLY DO NOT SUBMIT A PRICE
FOR THIS ITEM - Dining facility 5509 is the Army’s Officer Education School and anticipated to be open approximately 92 days per year typically May through
UNIT UNIT PRICE ESTIMATED AMOUNT
2005AA 92 Days
OPTION Operate Dining Facility 5509
FFP
The contractor shall provide a fixed price for the DAILY…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .