Atch-05_WWTP List of Repairs.pdf

PDF 80 KB Posted

Attached to
Joint Base Charleston Waste Water Treatment Plant Operation and Maintenance
Solicitation number
FA441826Q0031
Issued by

About this file

This document is a corrective action and repairs completion log for a wastewater treatment facility. The log details 18 corrective actions and repairs performed on various treatment system components, with completion dates ranging from December 27, 2023, to September 1, 2025.

The repairs encompass critical treatment infrastructure including tank maintenance (surge tank, aeration basin, and clarifier pump-out completed December 27, 2023), media and nozzle replacements in the tertiary filtration system (completed November 6, 2024), air diffuser system upgrades (completed September 1, 2024), and chlorination chamber structural repairs (completed September 10, 2024). Equipment replacements include aeration pumps in the surge tank (May 24, 2024), submersible pumps in the equalization chamber (November 6, 2024), mudwell and backwash pumps in the tertiary tank (November 6, 2024), and blower silencers (November 6, 2024). The facility also upgraded monitoring and control systems, including installation of automatic timer controls for blowers (October 10, 2024) and a digital analyzer system for total residual chlorine, dissolved oxygen, and pH testing (May 2, 2025). Additional work includes barscreen replacement (September 1, 2025), electrical control panel updates (May 2, 2025), power washing and protective coating of treatment chambers (September 1, 2024), metallurgy repairs, and lift pump replacement (May 2, 2025).

View the file

Other files

File Type Posted
Atch-01 WWTP O_M Services PWS_13 Jan 2026 - Rev 1.pdf PDF
Atch-06_QandA - Short Stay WWTP O_M.pdf PDF
Atch-01 PWS Attachment 8.9. Short Stay Wastewater Treatment Plant PMI Spreadsheet - Rev 1.pdf PDF
Atch-01 PWS Attachment 8.8.4. Digital Analyzer US – Field Service Report.pdf PDF
Atch-04_RFQ Pricing Workbook WWTP OM_FA441826Q0003_05 Mar 2026.xlsx XLSX spreadsheet
Atch-02_Provisions and Clauses.pdf PDF
Atch-04_RFQ Pricing Workbook WWTP OM_FA441826Q0003.xlsx XLSX spreadsheet
Atch-01 PWS Attachment 8.4. Short Stay Fire Line and Hydrants Map.pdf PDF
Atch-01 PWS Attachment 8.9. Short Stay Wastewater Treatment Plant PMI Spreadsheet.pdf PDF
Atch-01 PWS Attachment 8.8.2. Digital Analyzer Certificate of Instrument Performance.pdf PDF
Atch-01 PWS Attachment 8.8.5. LDO Sensor Manual.pdf PDF
Atch-01 PWS Attachment 8.6. Short Stay RV Dump Station Operation and Maintenance Manual.pdf PDF
Atch-01 PWS Attachment 8.8.6. Output Module Manual.pdf PDF
Atch-01 PWS Attachment 8.7. Short Stay Wastewater Treatment Facility O&M Manual Book 3.pdf PDF
Atch-01 PWS Attachment 8.8.7. pH ORP Sensor Manual.pdf PDF
Attachment 03 Wage Determination 2015-4427 Rev 32.pdf PDF
Atch-01 PWS Attachment 8.7. Short Stay Wastewater Treatment Facility O&M Manual Book 2.pdf PDF
Atch-01 PWS Attachment 8.3. Short Stay Wastewater Treatment Plant Site Layout Drawings and Photos.pdf PDF
Atch-01 PWS Attachment 8.5. Short Stay Water Distribution Map.pdf PDF
Atch-01 PWS Attachment 8.7. Short Stay Wastewater Treatment Facility O&M Manual Book 1.pdf PDF
Atch-01 PWS Attachment 8.8.3. Digital Analyzer Install Inspection.pdf PDF
Atch-01 PWS Attachment 8.1. Short NPDES Stay Permit Jan 2026.pdf PDF
WWTP O_M Services PWS_16 Jan 2026.pdf PDF
Atch-01 PWS Attachment 8.8.1. Analyzer Controller Manual.pdf PDF
Atch-01 PWS Attachment 8.2. Short Stay Wastewater Treatment Plant Layout As-builts.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Corrective Action & Repairs Date Completed

1 TANKS - Complete full pump out of surge tank, aeration basin, and clarifier - access components 27-Dec-2023

2 Duckweed removal of all pipes 27-Dec-2023

3 Replace Tertiary Media - Filter Sand/Torpedo Sand/Anthracite & Replace Filter Nozzles 6-Nov-2024

4 Replace Filter Nozzles in Tertiary Tank 6-Nov-2024

5 Replace Air diffusers, piping, and disks 1-Sep-2024

6 Scab Repair to Diffuser Pipe 1-Sep-2024

7 Scab Repair/Replace Underflow Baffles in the Chlorination Chamber 10-Sep-2024

8 Support bracket in Chlor/Dechlor chamber - Wall Repair - Metallurgy Repair 10-Sep-2024

9 Tertiary Tank: Replace Mudwell Pumps, Airscour & Backwash Pumps 6-Nov-2024

10 Blower Silencers replaced 6-Nov-2024

11 Surge Tank: 2ea. Pump - Aeration Pump Replaced 24-May-2024

12 Elec. System on an Automatic Timer switch for Blowers in Contact Chamber 10-Oct-2024

13 Replace Submersible Pumps in the Equalization Chamber 6-Nov-2024

14 Digital Analyzer - Automatic System for TRC, dissolved oxygen, and pH testing 2-May-2025

15 Replace lights, alarms, and covers on Electrical Control Panel Buttons 2-May-2025

16 Barscreen replacement 1-Sep-2025

PW & Protective Coating = Power wash and thoroughly clean all weirs, troughs, channels, and chambers & Paint

1-Sep-2024

18 Metallurgy Repair & Lift Pump Replacement 2-May-2025

File details come from the government source that posted it. Updated .