This Pre-Proposal Addendum 02 relates to two construction projects at Joint Base Charleston: Project DKFX 1052062 (Repair Maintenance Dock, B578) and Project DKFX 1069806 (Repair IMC Pavements, Area F). The addendum provides several key modifications, including drawing and specification updates, and clarifications on project requirements. Significant changes include deleting the Bonded Security Guards requirement, noting an existing 400-gallon HEF tank is full, modifying door hardware specifications, and allowing alternative surface preparation and coating methods for metalwork (accepting surface tolerant polyamide epoxy primer instead of inorganic zinc primer, with surface prep downgraded from SSPC-SP-10 to SSPC-SP-1/2/3 standards).
The project, solicited by the Department of the Air Force Air Mobility Command under Solicitation Number FA441825R0002, requires the contractor to provide labor, equipment, materials, and supervision to complete repairs at the maintenance dock and IMC pavements. Notable additional requirements include installing door switches on hangar doors to disable infrared heaters when doors are open, preserving existing door frames, and maintaining the existing automatic wet-pipe sprinkler system. The project is scheduled for completion by 06 Mar 2025, with revised technical specifications and drawings attached to the addendum.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| Joint Base Charleston – Air Base | Pre-Proposal Addendum 02 | |
| Project DKFX 1052062 – Repair Maintenance Dock, B578 | 06 Mar 2025 |
Project DKFX 1069806 – Repair IMC Pavements, Area F
Pre-Proposal Addendum 02
1. Replace drawing A100 dated 6/8/2023 with the attached A100 bearing Rev 1 dated 3/5/2025:
2. Replace specification 08 71 00 Door Hardware with the attached Spec 08 71 00 Door Hardware.
3. IMC Area F sheet G201 calls for Bonded Security Guards at the manning the gates. This requirement is deleted.
4. Existing HEF tank is 400 gallons, and contractor is to assume that it is full.
5. B578, FP051, Detail 2 - Each keynote 4 should be another keynote 3: "existing automatic wet-pipe sprinkler system to remain.”
6. In B.578 the existing door frames are to remain.
7. Contractor to install door switches on hangar doors that will disable the infrared heaters when doors are open.
8. The Government will accept a surface tolerant polyamide epoxy for prime coat in lieu of the specified inorganic zinc primer. Surface prep can be downgraded from the specified SSPC-SP-10 (Near white metal blast cleaning) to SSPC-SP-1 (Solvent Cleaning), SSPC-SP-2 (Hand Tool Cleaning), and SSPC-SP-3 (Powertool Cleaning). Aliphatic polyurethane is specified for the top/finish coat, which this recommended system appears to include.