This document is a Questions and Answers (Q&A) file for a federal contract opportunity at Joint Base Charleston, South Carolina. The solicitation (FA441825R0002) involves repair and maintenance work for Dock B578 and IMC Pavements Area F, requiring comprehensive renovation services including structural, mechanical, electrical, and architectural modifications. Key project details include removing and replacing infrastructure elements such as a High Expansion Foam (HEF) concentrate tank, performing resinous flooring installation, updating door hardware, implementing lightning protection system updates, and renovating fire alarm systems.

The Q&A document addresses 32 specific contractor inquiries covering technical specifications, safety requirements, and project execution details. Notable requirements include: using Trane-standardized air cooled chillers, completing Level I Antiterrorism Awareness Training, submitting a cost-loaded Critical Path Method project schedule, and following specific surface preparation and coating standards for steel surfaces. The project will not occupy the building during renovation, and contractors must comply with base access and security protocols. The work is being executed by the Department of the Air Force Air Mobility Command, with an estimated project cost not disclosed in the document.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 JB Charleston Offeror Question and Answer Form NOTICE TO OFFERORS Any offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all offerors before the submission of their proposals. Oral explanations or instructions given before the award of a contract will not be binding. Answers to offeror questions concerning a solicitation will be posted to sam.gov, if that information is necessary in preparing proposals or if the lack of it would be prejudicial to others.

Solicitation NumberFA441825R0002
Project Name:Repair Maintenance Dock B578 and Repair IMC Pavements Area F
#Specification Reference (Section & Paragraph Reference, i.e. 23 00 00, para 1.3)Drawing Reference (Sheet and Detail or Note Reference, i.e. M-101, Detail 2)Solicitation Reference (Section, paragraph, sub-paragraph Reference, i.e. Section M, Paragraph 2.3)Attachments or Other (i.e. Submittal Register, Wage Determination, Site Visit Note, etc.)
1Question
4/A410The new 8'x8" access panel is shown behind the grab bar. 1. Confirm the chase wall construction is CMU. 2. Should this panel be below the grab bar so it can open? 3. Is there a valve in the wall to where this panel is required?
Answer
22 00 00 | 3.3.61. Yes the chase wall for new 8'x8 access panel install is 6" CMU 2. Per Spec Section 22 00 00 Para 3.3.6 Access Panels shall be of sufficient size and located so that the concealed items may be serviced, maintained, or replaced. 3. Per Spec Section 22 00 00 Para 3.3.6 Access Panels shall be of sufficient size and located so that the concealed items may be serviced, maintained, or replaced.
2Question
Keynote 8.30 on A400Any chance the base would have around 60 brick that already match for this CMU/ brick infill?
Answer
No
3Question
Fuel Resistant Resinous Flooring 09 67 23.16Keynote 1.2 A100Please confirm the building will not be occupied during the renovation work. If the building is occupied, how many phases will the five coat floor system will we have to perform this in?
Answer
Bldg will not be occupied
4Question
G201 SecurityStates the contractor is provide and maintain security from a professional security firm at contractor access gates for the duration of use. Also states a guard stationed at each contractor access gate. 1. It papers the access for the bid option work will require a guard at Airfield gate V-4 as well as V-3, is this correct?
Answer
Gate guards will not be required.
5Question
Solicitation - Bid ScheduleA413 blue keynoteOption Line Item 0003, states the structural steel to be painted as an option . A413 blue keynote also states apply new paint in entire hangar area. Please clarify if the wall panels and bottom of the roof deck is to be painted as well and if so, are the panels and deck to be in the base bid or bid option?
Answer
The blue keynote on A413 through A416 applies to the structural members that are colored blue/purple in the pictures. "In entire hangar area" only intends to make it clear that this scope applies throughout the hangar bay area, not that the paint requirement extends beyond what is color-coded.
6Question
FP051States to remove HEF concentrate tank. Please confirm the tank is empty and does contain hazardous material. If not FP051empty, are the contents of hazardous matinal, If so, what are the procedures disposing of the material?
Answer
For bid purposes the contractor shall assume that the tank is full (400 gallons). The High Expansion Foam (HEF) can be disposed of as a non-regulated waste (Non-RCRA). It shall be collected and disposed of IAW applicable local, state, and federal laws and regulations. It can be delivered to any class of landfill. Manifest shall be provided to 628 CES/CEIE
7Question
Detail 2 on FP051On detail 2 there is a keynote 4, but cannot find what this is to be. Please clarify.
Answer
Each keynote 4 should be another keynote 3: "existing automatic wet-pipe sprinkler system to remain."
8Question
AD120Keynote D01 does not state the frames to be removed while in the door and hardware specs, welded frames are stated. Please confirm the door frames are to remain in place.
Answer
Correct - the frames are existing to remain.
9Question
Wage Scale BuildingsWe do not have the Wage Scale for the Building, just Highway. Did we miss it?
Answer
628 CONS has provided.
10Question
G-200 - Keynote 3Keynote 3 states "contractor shall keep door on B578 accessible for duration of construction? 1. Please provide the needed width of the area that must be left accusable. 2. Is needed path for access to be hard surface, in otherwards the entire area is not to be removed at one time?
Answer
With Area F and B.578 being awarded to one contractor, KN #3 can be deleted.
11Question
Lead Based Paint 02 02 00 00According to the abatement report, the paint on the building walls and CMU do not contain lead. Please confirm the shot blasting of the CMU walls for the resinous base as well as pressure washing the interior & exterior, no cost need to be included for testing or containment other than what is stated on the drawings to keep the debris from reaching the storm system
Answer
Correct
12Question
08 71 00, Door HardwareA100Sheet A100 door schedule shows 14 doors to be replaced. Spec section 07 71 00 only shows hardware schedule for door 102B. Is the existing hardware to be reused on the other 13 doors? If to be new hardware, please provide the hardware schedule to be followed.
Answer
See attached revised specification 08 71 00 Door Hardware and revised drawing A100 First Floor Plan
13Question
09 51 00 Acoustical CeilingsIs there acoustical ceilings to be provided for the project? The ceiling plan is only showing gyp ceilings.
Answer
Install per Finish Schedule (A100) and Enlarged Floor Plan A400
14Question
26 41 00 Lightning Protection SystemA spec is provided for a lightning protection system but not noted on any of the drawings. 1. Is there to be a new lightning protection system for the building? 2.. Where is the desired location for the grounding system? Is there anywhere around the building where there is not existing concrete? Can the existing grounding system be reused?
Answer
Install lightning protection system per plans and specifications. Work is limited to the replacement of air terminals and conductors at the rooftop. Existing downleads are to be reused. See E001 and E004
15Question
M101In other buildings it has been standard to disconnect heating abilities when the hangar doors are left open by installing door switches. Will we need to install door switches to disable the infrared heaters? If so, do you want them on each roll up door and the hangar door, or only the hangar door?
Answer
Door switches to disable the infrared heaters will only be installed on the hangar doors.
16Question
M003 BACnet Device ScheduleWill we be able to reuse existing controls conduits and wiring if they are in good shape?
Answer
Install per plans and specifications.
17Question
23 64 10 Section 2.4Will the air cooled chiller need to meet Joint Base Charleston's requirement to be standardized on Trane?
Answer
Yes.
18Question
M003 BACnet Device ScheduleIs it the intention for the devices on this list to be connected to the existing Trane building controller and campus control system?
Answer
Yes
19Question
Site Attendance ListCan you please add the contact information so we can get in touch with the contractors that attended?
Answer
Posted on Sam.gov
20Question
E301E301 Fire Alarm Renovation Key note 1 states Install Duct Mounted Smoke Detector in Supply air Duct of AHU-1. Coordinate install with mechanical Contractor. Please confirm this is the only F/A Scope.
Answer
Refer to E053 and E301 for fire alarm scope
21Question
FP051How big is the HEF tank?
Answer
400 gallons
22Question
01 45 00Section 01 45 00 - Quality Control. Please confirm if a Quality Control Manager independent of the Project Superintendent is required or can one person dual hat the two roles.
Answer
01 45 00 para. 3.2.5.1The QC Manager may not perform the duties of project superintendent.
24Question
01 14 00 para 1.3.1.3Are there any security/base access requirements to be aware of beyond the background check and Real ID required for badging?
Answer
Yes: JS-US007 - Level I Antiterrorism Awareness Training is required to be completed by all contractors within 30 days of requiring access, and annually thereafter. Coordination for training shall be by the contractor after contract award. This provision shall not apply to deliveries, contractors requiring access using single day passes, or any contractors requiring access for less than or equal to 180 continuous calendar days in a 1 year period. JS-US007 - Level I Antiterrorism Awareness Training can be located here:

https://jko.jten.mil/courses/AT-level1/launch.html Submit all completion certificates to the Contracting Officer for information only.

27Question
01 32 00, Para 3.201 32 00, Para 3.2 states "The Baseline Cost Loaded CPM Project Schedule shall be submitted for approval within 30 Calendar Days after the Notice of Award has been acknowledged." Please confirm the intent is for the Contractor to submit a cost loaded CPM Schedule prior to issuing Notice to Proceed (45-Calendar days after award).
Answer
Correct.
28Question
01 32 00, Para 1.101 32 00, Para 1.1 does not indicate an AF Form 3065 / AF Form 3064 to be submitted. Please confirm that this specification is for a Cost Loaded Critical Path Method (CPM) schedule to be utilized on a monthly basis for invoicing.
Answer
Correct.
29Question
Wage DeterminationAfter reviewing the project specification, could not find the Davis Bacon Wage & Determination for ( Construction Type Building) the only one provided as Wage & Determination for ( Highway). Please provide the wage determination for Construction Type: Building.
Answer
628 CONS has provided.
30Question
DWG G201Airspace 7460 notification by Contractors. Can we combined the site B 578 Hanger Renovation & IMC Pavement Area F as one 7460 notification to the FAA?
Answer
If required the FAA 7460-1 could be combined. Unless a crane is being utilized a 7460-1 is not anticipated to be required. This project is approximately 2300 ft. from nearest runway and as long as the contractor stays below the height of the surrounding buildings the FAA Notification of Construction will not be required.
31Question
09 97 13.00 40Specified steel coating primer is an inorganic zinc and is designed to be applied to abrasive blasted surface. Given the condition of the existing steel, the surface prep could be downgraded to an SP1, followed by an SP2 handtool cleaning and SP3 powertool clean of rusted surfaces. This would allow for a different coating system (surface tolerate epoxy): 1. Spot Prime with Carbomastic 94 epoxy or equal at 4-6 mils DFT 2. Full prime with the Carbomastic 94 epoxy or equal at 2-4 mils DFT 3. Finish coat with the carbothane 134HG or equal at 2-4 mils DFT . This would reduce the cost of the painting shop substantially. Would this be an acceptable to the Government?
Answer
The Government will accept a surface tolerant polyamide epoxy for prime coat in lieu of the specified inorganic zinc primer. Surface prep can be downgraded from the specified SSPC-SP-10 (Near white metal blast cleaning) to SSPC-SP-1 (Solvent Cleaning), SSPC-SP-2 (Hand Tool Cleaning), and SSPC-SP-3 (Powertool Cleaning). Aliphatic polyurethane is specified for the top/finish coat, which this recommended system appears to include.
32Question
09 67 23.16 / 1.3.5.5Qualification of Coating Contractors , All contractors that perform surface preperation or coating application must be certified to SSPC QP 8 and should also be SSPC QS 1 certified. Is this coating ceritification required for spec.(09 90 00 Paint and Coatings) and (09 97 13.00 40 Steel Coating) or just 09 67 23.16?
Answer
There is no intent to make the coating requirements of the resinous flooring specification (09 67 23.16) apply to the paint (09 90 00) or steel coating (09 97 13.00 40) sections.