02 - Period of Performance.pdf

PDF 78 KB Posted

Attached to
Repair MX Dock B578 and IMC Pavements Area F
Solicitation number
FA441825R0002
Issued by

About this file

This is a Performance Time Tabulation Form for project DKFX 1052062/1069806 to repair Maintenance Dock B578 and IMC Pavement Area F. The form details the project timeline and construction schedule, with a Notice to Proceed date of September 1, 2025.

The total contract period of performance is 398 days, broken down into 60 days for mobilization and submittal preparation, followed by 270 construction days (with 38 inclement weather days factored in), and 30 closeout days. The construction phase is scheduled to begin on October 31, 2025, with construction completion on September 3, 2026, and final contract completion on October 3, 2026. The form includes a detailed monthly breakdown showing construction days per month and anticipated inclement weather impacts, with construction activity percentages ranging from 45% to 74% during active months. The document indicates this data is linked to a Liquidated Damages tab and requires coordination with Contracting for current LD rates.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1-Sep-25

31-Oct-25 Number of Construction Days: 270

Construction Complete 3-Sep-26 Number of Closeout Days: 30

3-Oct-26

Month

Days

In

Month

Average Inclement

Weather

Days/Month (Ref.

Spec 01 32 00, para

3.3.8.1)

Number of

Construction

Days/Month

% of Days of

Month

Construction

Possible

Inclement

Weather

Days Per

Month Sep-25 31 9 0 0% 0

Sep-25 30 7 0 0% 0

Oct-25 31 5 14 45% 2

Nov-25 30 4 15 50% 2

Dec-25 31 6 22 71% 4

Jan-26 31 6 21 68% 4

Feb-26 29 5 20 69% 3

Apr-26 31 5 23 74% 4

May-26 30 5 22 73% 4

May-26 31 5 22 71% 3

Jun-26 30 8 21 70% 6

Aug-26 31 9 22 71% 6

Aug-26 31 9 0 0% 0

Sep-26 29 7 0 0% 0

Oct-26 31 5 0 0% 0

Nov-26 30 4 0 0% 0

Dec-26 31 6 0 0% 0

Total: 202 Total: 38

"Construction Time" =

Period of Performance (PoP) =

Construction Start Date:

Number of Inclement Weather Days:

Total Contract Days:

Estimated Contract Completion Date:

Special Order Materials Lead Time:

Insert estimated NTP.

Insert number of Mobilization & Submittal Preparation days you are allowing.

Insert number of days for any Special Order Materials Lead Time you are allowing.

Insert the Number of Construction Days/Month for each month without consideration of inclement weather days.

Insert the % of Month Impacted by Inclement Weather

Total number of Contract Days is displayed below.

Construction Complete Date is displayed below.

Performance Time tab data is linked to the Liquidated Damages tab. Coordinate current LD rates with Contracting.

Notice to Proceed Mobilization & Submittal Preparation:

Insert current date (data linked to Liquidated Damages tab).

Performance Time Tabulation Form

DKFX 1052062/1069806 Repair Maintenance Dock B578, Repair IMC Pavement Area F 21-Oct-24

Instructions:

Insert Project Number and Title (data linked to Liquidated Damages tab).

File details come from the government source that posted it. Updated .