Landscaping - Questions and Answers.pdf

PDF 56 KB Posted

Attached to
Landscape Refresh, Bldg. 1 - Hurlburt Field, FL Federal contract opportunity
Solicitation number
FA441724Q0301
Issued by
Department of the Air Force Special Operations Command

About this file

This document contains questions and answers related to a federal contract opportunity for landscaping services at Hurlburt Field in Florida.

The key details are: The contract is for landscaping services associated with Building 1 at Hurlburt Field. It is a combined synopsis/solicitation for commercial services under FAR Subpart 12.6. The acquisition is set aside for small businesses and will be evaluated using lowest price technically acceptable (LPTA) criteria. The contractor will be required to provide all management, tools, supplies, equipment, and labor necessary to perform the landscaping services. The Statement of Work and drawings provide detailed information on the requirements. A site visit is scheduled for August 15, 2024, and offers are due by August 22, 2024. The questions and answers address topics such as tax-exempt status, permitting, irrigation, and turf repair.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Landscape Refresh – Questions & Answers 16 Aug 24

Q1. Will a tax-exempt certificate be issued to the awardee?

A1. No certificate will be issued, this contract is not tax-exempt. Typically, any local, state, federal taxes will be included in your quote.

Q2. Will any permits be required?

A2. Yes, upon award, the contractor will be required to submit the dig permit prior to beginning work. It takes about 2 weeks for the permit to be approved. The awardee will have to go to the CE office to submit one.

Q3. Will someone be available to allow us to turn on the system in order to determine whether modifications of existing irrigation or instillation of new irrigation will be required?

A3. No, it has been deemed that modification to or new installation of irrigation is not required and will no longer being considered as a part of this contract, as stated in the revised SOW. Irrigation is no longer being requested.

Q4. Is any turf repair needing to be done if we’re removing the Oaks? The grass in that area is in poor condition and the heavy equipment needed to do tree removal will leave it in even poorer condition.

A4. Any damage to the property, made by the contractor in the process of work, will need to be repaired. The contractor shall leave the area in the same or better condition than how they found it.

*** If any additional questions are received, this will be updated on Monday, August 19th ***