This file is a Questions and Answers (Q&A) document for a two-phase HVAC duct cleaning and sanitization project at Maxwell Air Force Base and Gunter Annex, Alabama. The project covers approximately 460,000 square feet across multiple dormitory buildings, with Phase 1 requiring professional duct cleaning of supply and return ducts, registers, grilles, diffusers, and air handling units (AHUs), including fan coil units and unit ventilators where applicable. Phase 2 involves installation of hydrogen peroxide vapor-based air sanitization systems (zero ozone) in four specified buildings (1430, 1431, 696, and G1410) with post-remediation verification testing performed by an independent qualified third-party industrial hygienist. The project must be completed within 150 days, with Phase 2 system installation required immediately after Phase 1 cleaning completion for each facility. Work must be performed one facility at a time to avoid limiting dorm occupancy. The applicable wage determination is the Service Contract Labor Standards (updated on SAM.gov), not Davis-Bacon Act rates.
Key contract specifics include: the solicitation is unrestricted (no small business set-aside); pre-remediation verification baseline sampling is required for all buildings, with post-cleaning surface sampling required for all cleaned buildings and post-installation airborne spore trap analysis required only for the four buildings receiving sanitization systems, per IICRC S520 standards; active mold treatment identified during work is the contractor's responsibility and included in firm-fixed-price CLINs; existing sanitization equipment in Buildings 1430, 1431, and G1410 requires upgrade or change-out; payment is made only after full project completion with no progress payments; the Government will not provide site visit photos, mechanical schedules, CFM specifications, or air handler details beyond as-built drawings (which may not reflect current conditions); contractor personnel must complete background checks and base access coordination controlled by 42 Security Forces Squadron; and the Government expected contract award within one week of proposal closure with Q&A posted to SAM.gov by July 7, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 6-QNA_Dorm Duct Cleaning.docx | DOCX document | |
| Attachment 3-Wage Determination-May 2026.pdf | ||
| Attachment 6-QNA_Dorm Duct Cleaning.docx | DOCX document | |
| Clean and Sanitize Dorm Combo-Amendment 0005.docx | DOCX document | |
| Attachment 2-Dorm Ducts Provision-Clauses.pdf | ||
| Clean and Sanitize Dorm Combo-Amendment 0004.docx | DOCX document | |
| Clean and Sanitize Dorm Combo-Amendment 0003.docx | DOCX document | |
| Clean and Sanitize Dorm Combo-Amendment 0002.docx | DOCX document | |
| Attachment 6-Provisions And Clauses-Clean And Sanitize Dorm Ducts v2.docx | DOCX document | |
| Clean and Sanitize Dorm Combo-Amendment 0001.docx | DOCX document | |
| Attachment 4-Site Visit Sign-Dorm HVAC Ducts.docx | DOCX document | |
| Clean and Sanitize Dorm Combo.docx | DOCX document | |
| Attachment 2-Provisions And Clauses-Clean And Sanitize Dorm Ducts.pdf | ||
| Attachment 1-SOW_AirDuctCleaning-Sanitize.docx | DOCX document | |
| Attachment 3-Wage Determination-June 2026.pdf | ||
| Attachment 5-Updated Dorm Duct Drawings.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maxwell Dorm Duct Cleaning Q&A
1. Wage determination. Attachment 3 appears to be a Davis-Bacon Act wage determination, while the solicitation assigns services NAICS 561790 and incorporates the Service Contract Labor Standards clauses at FAR 52.222-41, 52.222-42, and 52.222-44. Please confirm which labor standard governs this requirement, provide the applicable wage determination the Government intends to apply, and confirm whether separate determinations apply to the Phase 1 cleaning (service) work and the Phase 2 installation work. A. SAM.gov has been updated with the Service wage determination
2. Mold treatment scope. SOW paragraph 1.1 makes the Contractor responsible for treating active mold if identified, but sets no quantity, location, or not-to-exceed limit. Will the Government establish a separate CLIN or unit price for mold treatment, or define a not-to-exceed quantity, so that offerors can price this scope consistently? A. Per SOW Section 1.1, "If active mold is identified at any point, the Contractor is responsible for its treatment." The SOW does not mention a separate CLIN, unit price, or a not-to-exceed quantity for this work.
3. Sanitization installation basis and Building 1410 Gunter scope.
(a) For the ducted sanitization buildings 1430, 1431, and 696 (CLINs 0013, 0014, and 0015), please confirm whether one active in-duct air treatment device installed at the air handler supply per building satisfies the requirement, or whether a different installation basis is required. For example, the previous SOW specifically asked for .02 PPM of encapsulated hydroxyl groups. A. Section 2.2 defines the technology requirements (hydrogen peroxide vapor, zero ozone, etc.) that the proposed system must meet for the entire space.
(b) Building 1410 Gunter (CLINs 0012 and 0016) is served by approximately 90 chilled-water fan coil units, one per room, plus a separate ducted supply-air system. For cleaning under CLIN 0012, does the required scope include the individual fan coil units and their coils and drain pans, the central supply-air ductwork only, or both? For sanitization under CLIN 0016, is the active air treatment system required at each fan coil unit, in the central supply-air duct only, or both, and on what device basis? The fan coil units recirculate room air locally and are not treated by a device placed in the central supply-air duct, so the answer materially affects technical approach and price. A. the entire air conveyance system. This includes supply and return ducts, registers, grilles, diffusers, and air handling units
(c) Building 1410 Gunter currently has active air purification units installed and operating in the central supply-air duct. Please confirm whether CLIN 0016 requires installation of a new active air treatment system in this building, and if so, whether the existing equipment is to be removed, replaced, or supplemented, and whether the new system is required in the central supply-air duct only or also at the fan coil units, consistent with question 3(b). A. SOW Section 1.1 states that buildings 1430, 1431, and G1410 have "existing sanitizing equipment that will require upgrade or change out
4. Post-remediation verification scope and sampling.
(a) How many verification samples are required per building under SOW paragraph 2.3? A. reference IICRC S520 requirements.
(b) For the buildings receiving cleaning only and no Phase 2 installation, is only the Phase 1 post-cleaning surface verification required, with the Phase 2 airborne verification limited to the four buildings receiving sanitization (CLINs 0013 through 0016)? A. Yes, the SOW links the "airborne spore trap analysis" to the "Post-Installation (Phase 2)" verification (Section 2.3), which applies only to the four buildings receiving the sanitization systems. The surface sampling is linked to "Post-Cleaning (Phase 1)" and applies to all cleaned buildings.
5. Verification standard. SOW paragraph 2.3 sets a post-installation airborne acceptance standard comparing indoor samples to an outdoor baseline. A. reference IICRC S520 requirements.
(a) Microbial growth was observed outside the air conveyance system during the site visit. Such sources can cause an airborne verification to fail yet remediating them is outside the defined cleaning and installation scope. Please confirm this is outside the scope of this requirement, or that it is separately compensable under a defined CLIN or unit price. A. The SOW defines the scope of work as the HVAC systems and their components (Section 1.1, 2.1). It does not mention remediating microbial growth on surfaces outside of the air conveyance system.
(b) When HVAC systems are returned to service after cleaning, they re-entrain airborne particulate from the occupied indoor environment, which is frequently not at Condition 1. Please clarify how the post-cleaning verification is expected to be maintained under that condition. A. the air quality tests should verify the samples.
(c) The permitted active air treatment technologies reduce microbial viability rather than physically removing airborne particles, and are generally not labeled for airborne microbial-reduction efficacy, while spore-trap analysis counts total spores without distinguishing viable from non-viable. Please clarify the acceptance metric and verification method for Phase 2 so the metric matches the function of the installed technology, for example a culturable sampling method or a defined equipment-performance test. A. the printouts from the samples will be the verification method.
6.Will USG provide photos from the Site Visit? A. No
7.When does USG expect to award the contract and provide NTP? CONS believes within 1 week of offer close date, there shall be an award.
8.What is the purpose of the pre-remediation verification testing (SOW 2.3)?
0. If pre-remediation testing is required, is the requirement for both surface and air sampling? A. to be able to establish an environmental baseline.
0. What is the expected number of pre-remediation sampling protocols? A. 1
0. Will contractors be allowed to take pre-remediation samples while dorms are still inhabited? A. Yes
9. Please verify the supply air flow of the AHUs for each facility. A. See As built drawings
10. Does phase II sampling need to occur within the duct work as well? A. Yes
11. Must the Qualified 3rd party be the one to take the samples or can they just be the one performing the testing? A. Yes
12. Does USG require phase II system installation immediately after duct cleaning and surface sampling is completed? A. Yes
13. Is only the supply and return ductwork required to be cleaned internally or is exhaust duct included as well? A. No
14. Are associated Air Handler Units, VAV Boxes and/or Fan Coil Units required to be cleaned? A. the cleaning includes "supply and return ducts, registers, grilles, diffusers, and air handling units
15. If there are stand alone wall fan coil units or unit ventilators are those required to be cleaned? A. Yes
16. Please confirm that hard surfaces (e.g. walls/Ceilings) are not required to be cut into in order to facilitate cleaning. A. No
17. Are prevailing Wage Rates / Davis Bacon Wage Rates required and if so, please provide. Updated on Sam.gov.
18. Please confirm that cleaning is required to remove dry/loose debris (e.g. staining is not required to be removed). A. Yes
19. My team cannot find reference to specific testing requirements in the IICRC S520 standard. Would USG be able to reference a specific section where sampling/testing information is provided? A. The SOW (Section 2.3) references IICRC S520 as the standard for achieving "Condition 1" post-cleaning but does not cite a specific section within that standard.
20. With answers being provided potentially by 7 July, would USG consider a proposal due date extension? No.
21. Can USG provide the Air Handler mechanical schedules for each facility? A. No
22. Could USG provide the CFM of each AHU? Same as #9
23. SOW Section 2.3 references “pre- and post-remediation verification performed by an independent, qualified third-party.” However, 2.3, subsection 1 only references “Post-Cleaning (Phase 1).” A. Pre and post verification is required
a. Can USG verify that no pre-cleaning testing is required? A. Yes
24. Is USG capable to extend the 150 day period of performance if need be? No
25. Would USG be capable to keep personnel out of all facilities if an offeror proposed to work on every facility simultaneously? A. No
26. Does Phase 2: Air Sanitization System Installation in 1430, 1431, 696 and G1410 and the follow-on Air Quality Sampling occur only after the Phase I Duct work cleaning in all facilities is completed? A. As each facility completes
27. When does USG expect to post Q&A to SAM.gov? 7JUL26
28. Is there an incumbent providing same/similar services to Maxwell AFB?
a. If so, who are they, what was their winning, contract number, and SOW? No.
29. Could USG verify the set-aside requirements for this solicitation? No set aside.
30. Could USG verify if “Attachment 6 Provisions And Clauses-Clean And Sanitize Dorm Ducts v2” is meant to superseded Attachment 2? Updated sam.gov
31. Will USG provide the sign-in sheet on SAM.gov once the Site Visit is concluded? No.
32. Is there a specific number of samples to be collected per square foot of building space? A. This is a duplicate of Question 4a.
33. Is there a minimum number of days of sampling required per facility? A. No
34. Could USG provide the number of AHUs serving each building and the Supply CFM of each AHU? A. see question 9
35. Please verify that only Buildings 1430, 1431, 696 and G1410 require the Phase II Air Sanitization System Installation and airborne spore trap analysis. A. See question 4b
36. Page 5 of the combo states “Manufacturer Specifications: The offeror’s provided manufacturer specifications will be evaluated to ensure they are sufficient in detail to clearly demonstrate their capability of providing all of the required items for CLIN 0002 as outlined in the attached Statement of Work (SOW) Paragraphs 2.0-2.3” Updated on sam.gov
a. Is there a reason only CLIN 0002: Duct Cleaning Bldg 1431 is referenced here? Updated on sam.gov
37. Will offerors be permitted to work on multiple facilities concurrently, or is the expectation to work on one facility at a time during the 150 days? A. the expectation is to do one at a time so dorm space is not limited
38. Building G1410 had 1 AHU that had 5 DW 8000 & 1 DW 16000 already installed are you looking to have this system replaced with a new sanitization system? A. SOW Section 1.1 states the existing equipment in G1410 requires an "upgrade or change out."
39. Building G1410 had unit ventilators in each of the dorms, are these to be cleaned? A. Yes
40. Please confirm we are only cleaning HVAC ductwork and no bathroom exhaust. A. buildings where the venting is directly outside will not require cleaning, facilities that exhaust into the facility system will need to be cleaned
41. Please confirm that all sanitization system & equipment will be placed at the AHUs only. A. the entire air conveyance system. This includes supply and return ducts, registers, grilles, diffusers, and air handling units
42. Please confirm total AHU count for Buildings 1430, 1431 & 696. A. the contractor should verify in person
43. Are we doing any unit ventilator in any of the buildings or only what is connect to the AHUs? A. the entire air conveyance system.
44. Is the awarded contractor expected to replace filters? If so, can sizes and quantities be provided? If not, will the government provide new filters to be installed after cleaning? A. No
45. How many tape samples are expected to be collected per building and/or per unit cleaned? A. See answer 4a
46. How many air samples are expected to be collected per building and/or per unit cleaned? A. The IICRC S520 is the ANSI/IICRC Standard for Professional Mold Remediation, providing procedural guidelines for safely and effectively removing mold from buildings and contents. The number of environmental samples shall meet this standard.
47. What UV system (manufacturer & model) does the Government expect to be installed? Does the Government have a preference or are they willing to share the manufacturer/model the previously awarded (but unqualified) contractor selected? Currently, the SOW incentivizes prospective bidders to select the cheapest option. A. The SOW (Section 2.2) does not specify a UV system
48. Is cleaning of dryer vents and/or bathroom exhaust lines included in the base scope? A. No
49. Is Fiberlock IAQ 8000 an acceptable product to be used as an encapsulant? A. The SOW does not mention encapsulation or any specific encapsulant products.
50. Is Fiberlock Shockwave RTU an acceptable sanitizing agent? A. Phase 2, Section 2.2 specifies a hydrogen peroxide generation system for sanitization, not a chemical sanitizing agent applied during cleaning.
51. What certifications are required for the Industrial Hygienist? A. The SOW (Section 2.3) requires verification by an "independent, qualified third-party (e.g., an Industrial Hygienist)" but does not specify particular certifications for this
52. Will prospective bidders' previous experience on Federal duct cleaning projects be considered in the award decision? No
53. Please confirm whether this procurement is restricted to small businesses or is an unrestricted open-market acquisition. Unrestricted
54. What is the typical processing timeline for contractor base access at Maxwell AFB, and can any personnel or vehicle access steps begin before award? No prior to award coordination. Outside our control, dependent on 42SFS and individual background checks.
55. If active mold is identified, should mold remediation be included in the firm-fixed-price CLINs, or would it be handled by separate modification/change order? A. SOW Section 1.1 states the contractor is responsible for mold treatment, implying it is included in the base price
56. What is the Government’s review and approval process for the proposed Phase 2 air sanitization technology, and what is the expected review timeline? A. Timeline will be discussed at the preconstruction meeting
57. Do Buildings 1430, 1431, 696, or G1410 currently have any air treatment, UV, ionization, or purification systems that must be removed, decommissioned, or integrated? A. Section 1.1 states that for buildings 1430, 1431, and G1410, "existing sanitizing equipment.
58. Please confirm whether Attachment 5 drawings are current/as-built and can be relied upon for pricing. A. the as built drawings were provided to give you the basic idea of the system at construction time. Changes could have been made that are not recorded and you will have to verify potential changes,
59. Will the Government allow progress payments or partial invoicing by building/phase after acceptance, or is payment only made after full project completion? No
60. Which Wage Determination labor classifications apply to Phase 1 duct cleaning and Phase 2 system installation personnel? Updated on sam.gov.
61. Does the Industrial Hygienist/third-party testing firm require Government pre-approval, and should reports be submitted directly to the Contracting Officer as formal deliverables? A. See question 51 answer
File details come from the government source that posted it. Updated .