32 11 16 - Base Course for Rigid and Subases for Flexible Pavements.doc

DOC document 59 KB Posted

Attached to
Centralized Aircraft Support System (CASS) Upgrade
Solicitation number
FA3016-17-R-0025
Issued by

About this file

SOW Appendix A, Specifications, FA3016-17-R-0025

View the file

Other files

File Type Posted
FA3016-17-R-0025-0004_Revise_Section_L_signed.pdf PDF
CASS_Attachment_5_PLC_Hardware.pdf PDF
CASS_Attachment_4_Touch_Screens_Hardware.pdf PDF
CASS_Attachment_3_Station_Hardware.pdf PDF
CASS_Attachment_7_Pneumatics_Hardware.pdf PDF
FA3016-17-R-0025_CASS_System_Upgrades_2nd_Site_Visit_Q&A.docx DOCX document
CASS_Attachment_6_PLC_Program_Data.pdf PDF
CASS_Attachment_8_3052_JBA_400Hz_SingleJacket_Sept_2016.pdf PDF
CASS_Attachment_2__Schematics.pdf PDF
CASS_Attachment_1_Description,_Operation_and_Maintenance.pdf PDF
FA3016-17-R-0025_New_SOW_attch_D.pdf PDF
Appendix_D_-_CASS_Existing_Drawings,_2001.zip ZIP file
2_-_SOW_TYMX150072_CASS_T-38_Row_2-7_Rev_22Jun2017.docx DOCX document
Questions_and_Answers__2.docx DOCX document
FA3016-17-R-0025-P00002_Unsuspend.pdf PDF
Appendix_D,_CASS_Drawing_2001.zip ZIP file
Atch_2_Wage_Determination_02_June_17.pdf PDF
Atch_1_Statement_of_Work.pdf PDF
Questions_and_Answers__1.xlsx XLSX spreadsheet
FA3016-17-R-0025-P00001_Suspend_Solicitation.pdf PDF
01 54 00 - Green Procurement —
Atch_5_Contractor_Responsibility_Questionnaire.docx DOCX document
Section_01_35_35__Environmental_Protection Mar 15.pdf PDF
Atch_11_Project_Location.pdf PDF
01 21 53 —
03 20 02 STEEL BARS AND WELDED WIRE FABRIC FOR CONCRETE REINFORCEMENT FOR CIVIL WORKS.doc DOC document
Appendix_C_Computerized_Master_Control_CASS_System.pptx PPTX presentation
03 39 00 00 10 - Concrete Curing.docx DOCX document
Atch_10_Local_Information.pdf PDF
32 12 11 - Bituminous Surface Treatments.doc DOC document
32 01 17.16 - Sealing of Cracks in Bituminous Pavements.doc DOC document
32 01 19 - Field Molded Sealants for Sealing Joints in Rigid Pavements.doc DOC document
02 41 00 —
Atch_8_HAZMAT_Letter.pdf PDF
03 15 13.00 10 EXPANSION JOINT, CONTRACTION JOINT & WATER STOPS.doc DOC document
09 90 00.00 40 PAINTING AND COATING.doc DOC document
03 11 13.00 10 STRUCTURAL CONCRETE FORMWORK.doc DOC document
03 15 00 00 10 - Concrete Accessories.docx DOCX document
00 00 00 - Construction Contract Security Requirements.doc DOC document
01 00 00 - General Requirements —
32 13 11 - Concrete Pavement for Airfield and Other Heavy-Duty Pavements.docx DOCX document
Atch_4__Financial_Information_Questionnaire.docx DOCX document
Atch_7_AETC_Form_47.pdf PDF
03 31 01 00 10 - Cast In Place Structural Concrete For Civil Works.docx DOCX document
32 17 24 00 10 - Pavement Markings.docx DOCX document
Atch_1_Statement_of_Work.pdf PDF
32 13 73 - Compression Joint Seals for Concrete Pavement.docx DOCX document
32 01 11 52 Rubber Removal.doc DOC document
02 83 00 —
01 03 00 - Project Closeout.docx DOCX document
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISION 32 – EXTERIOR IMPROVEMENTS

SECTION 32 11 16

BASE COURSE FOR RIGID AND SUBBASES FOR FLEXIBLE PAVING

08/08

PART 1 GENERAL

This guide specification covers the requirements for subbase, select-material subbase and rigid base courses for airfield pavements, roads and streets.

1.1 UNIT PRICES

1.1.1 Measurement

1.1.1.1 Area

Measure the quantity of subbase and select-material subbase or rigid pavement base course completed and accepted, as determined by the Contracting Officer, in square yards.

1.1.1.2 Volume

Measure the quantity of subbase and select-material subbase or rigid pavement base course completed and accepted, as determined by the Contracting Officer, in cubic yards. Determine the volume of material in-place and accepted by the average job thickness obtained in accordance with paragraph THICKNESS CONTROL and the dimensions shown.

1.1.1.3 Weight

The tonnage of subbase and select-material subbase or rigid pavement base course material will be the number of tons of aggregate, placed and accepted in the completed course as determined by the Contracting Officer. Deductions will be made for any material wasted, unused, rejected, or used for convenience of the Contractor, and for water exceeding specified amount at time of weighing.

1.1.2 Payment

1.1.2.1 Course Material

Quantities of subbase and select-material subbase or rigid pavement base course, determined as specified in paragraph Measurement, will be paid for at the respective contract unit prices, which will constitute full compensation for the construction and completion of the subbase and select-material subbase or rigid pavement base course.

1.1.2.2 Stabilization

Cohesionless subgrades or select subbase courses to be stabilized, as specified in paragraph PREPARATION OF UNDERLYING MATERIAL, will be paid as a special item on the tonnage basis including extra manipulation as required.

1.1.3 Waybills and Delivery Tickets

Submit copies of waybills and delivery tickets during the progress of the work.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)

AASHTO T 180(2001; R 2004) Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and an 457-mm (18-in) Drop

AASHTO T 224(2001; R 2004) Correction for Coarse Particles in the Soil Compaction Test

ASTM INTERNATIONAL (ASTM)

ASTM C 117(2004) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing

ASTM C 131(2006)Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine

ASTM C 136(2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates

ASTM C 29 (2007) Standard Test Method for Bulk Density ("Unit Weight") and Voids in Aggregate

ASTM D 1556(2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method

ASTM D 1557(2007) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)

ASTM D 2167(2008) Density and Unit Weight of Soil in Place by the Rubber Balloon Method

ASTM D 2487(2006e1) Soils for Engineering Purposes (Unified Soil Classification System)

ASTM D 422(1963; R 2007) Particle-Size Analysis of Soils

ASTM D 4318(2005) Liquid Limit, Plastic Limit, and Plasticity Index of Soils

ASTM D 6938(2007a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

ASTM D 75(2009) Standard Practice for Sampling Aggregates

ASTM E 11(2009) Wire Cloth and Sieves for Testing Purposes

1.3 DEFINITION

Degree of compaction required is expressed as a percentage of the maximum laboratory dry density obtained by the test procedure presented in ASTM D 1557 abbreviated as a percent of laboratory maximum dry density. One exception is as follows: Since ASTM D 1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve will be expressed as a percentage of the laboratory maximum dry density in accordance with AASHTO T 180 Method D and corrected with AASHTO T 224.

1.4 SYSTEM DESCRIPTION

All plant, equipment, and tools used in the performance of the work will be subject to approval before the work is started and shall be maintained in satisfactory working condition at all times. Submit a list of proposed equipment, including descriptive data. Provide equipment which is adequate and has the capability of producing the required compaction, meeting grade controls, thickness control, and smoothness requirements as set forth herein.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Equipment; G List of proposed equipment to be used in performance of construction work, including descriptive data.

Waybills and Delivery Tickets

Copies of waybills and delivery tickets during the progress of the work.

SD-06 Test Reports

Sampling and Testing; G Field Density Tests; G Certified copies of test results for approval not less than 30 days before material is required for the work.

Calibration curves and related test results prior to using the device or equipment being calibrated.

Copies of field test results within 24 hours after the tests are performed.

1.6 QUALITY ASSURANCE

Sampling and testing are the responsibility of the Contractor, to be performed by an approved testing laboratory in accordance with Section 01 45 01 QUALITY CONTROL. Perform tests at the specified frequency. No work requiring testing will be permitted until the testing laboratory has been inspected and approved. Test the materials to establish compliance with the specified requirements.

1.6.1 Sampling

Take samples for laboratory testing in conformance with ASTM D 75. When deemed necessary, the sampling will be observed by the Contracting Officer.

1.6.2 Tests

1.6.2.1 Sieve Analysis

Make sieve analysis in conformance with ASTM C 117 and ASTM C 136. Complete particle-size analysis of the soils in conformance with ASTM D 422. Sieves shall conform to ASTM E 11.

1.6.2.2 Liquid Limit and Plasticity Index

Determine liquid limit and plasticity index in accordance with ASTM D 4318.

1.6.2.3 Moisture-Density Determinations

Determine the laboratory maximum dry density and optimum moisture in accordance with ASTM D 1557, AASHTO T 180, Method D and corrected with AASHTO T 224.

1.6.2.4 Field Density Tests

Measure field density in accordance with ASTM D 1556, ASTM D 2167, or ASTM D 6938. For the method presented in ASTM D 1556, use the base plate, as shown in the drawing. For the method presented in ASTM D 6938, check and adjust the calibration curves, if necessary, using only the sand cone method as described in paragraph Calibration, of the ASTM publication. Tests performed in accordance with ASTM D 6938 result in a wet unit weight of soil and ASTM D 6938 will be used to determine the moisture content of the soil. The calibration curves furnished with the moisture gauges shall also be checked along with density calibration checks as described in ASTM D 6938. The calibration checks of both the density and moisture gauges shall be made by the prepared containers of material method, as described in paragraph Calibration, in ASTM D 6938, on each different type of material to be tested at the beginning of a job and at intervals as directed.

a. Submit certified copies of test results for approval not less than 30 days before material is required for the work.

b. Submit calibration curves and related test results prior to using the device or equipment being calibrated.

c. Submit copies of field test results within 24 hours after the tests are performed.

1.6.2.5 Wear Test

Perform wear tests in conformance with ASTM C 131.

1.6.3 Testing Frequency

1.6.3.1 Initial Tests

Perform one of each of the following tests on the proposed material prior to commencing construction to demonstrate that the proposed material meets all specified requirements prior to installation.

a. Sieve Analysis including 0.02 mm size material

b. Liquid limit and plasticity index

c. Moisture-density relationship

d. Wear

1.6.3.2 In-Place Tests

Perform one of each of the following tests on samples taken from the placed and compacted subbase and select-material subbase or rigid pavement base course. Samples shall be taken and tested at the rates indicated.

a. Perform density tests on every lift of material placed and at a frequency of one set of tests for every 500 square yards, or portion thereof, of completed area.

b. Perform sieve analysis, including 0.02 mm size material on every lift of material placed and at a frequency of one sieve analysis for every 1000 square yards, or portion thereof, of material placed.

c. Perform liquid limit and plasticity index tests at the same frequency as the sieve analysis.

d. Measure the thickness of each course at intervals providing at least one measurement for each 500 square yards or part thereof. The thickness measurement shall be made by test holes, at least 3 inches in diameter through the course.

1.6.4 Approval of Material

Select the source of materials 30 days prior to the time the material will be required in the work. Tentative approval will be based on initial test results. Final approval of the materials will be based on tests for gradation, liquid limit, and plasticity index performed on samples taken from the completed and compacted course.

1.7 ENVIRONMENTAL REQUIREMENTS

Perform construction when the atmospheric temperature is above 35 degrees F. When the temperature falls below 35 degrees F, protect all completed areas by approved methods against detrimental effects of freezing. Correct completed areas damaged by freezing, rainfall, or other weather conditions to meet specified requirements.

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 Subbase Course

Provide aggregates consisting of crushed stone or slag, gravel, shell, sand, or other sound, durable, approved materials processed and blended or naturally combined. Provide aggregates which are durable and sound, free from lumps and balls of clay, organic matter, objectionable coatings, and other foreign material. Material retained on the No. 4 sieve shall have a percentage of wear not to exceed 50 percent after 500 revolutions when tested as specified in ASTM C 131. Aggregate shall be reasonably uniform in density and quality. Slag shall be an air-cooled, blast-furnace product having a dry weight of not less than 65 pcf. Aggregates shall have a maximum size of 1 inch and shall be within the limits specified as follows:

Maximum Allowable Percentage by Weight

Passing Square-Mesh Sieve

Sieve Designation
No. 1
No. 2
No. 3
No. 10
50
80
100
No. 200
8
8
8

Particles having diameters less than 0.0008 inches shall not be in excess of 3 percent by weight of the total sample tested as determined in accordance with ASTM D 422. The portion of any blended component and of the completed course passing the No. 40 sieve shall be either nonplastic or shall have a liquid limit not greater than 25 and a plasticity index not greater than 5.

2.1.2 Select-Material Subbase Course

Provide materials consisting of selected soil or other materials from field excavation, stockpiles, or other sources and free from lumps and balls of clay and from organic and other objectionable matter. Not more than 25 percent by weight shall pass the No. 200 sieve. The portion of material passing the No. 40 sieve shall have a liquid limit less than 35 and a plasticity index less than 12. The maximum particle size shall not exceed 3 inches. Particles having diameters less than 0.02 mm shall not be in excess of 3 percent by weight of the total sample tested as determined in accordance with ASTM D 422.

2.1.3 Rigid Pavement Base Course

Provide aggregates consisting of crushed stone or slag, gravel, shell, sand, or other sound, durable, approved materials processed and blended or naturally combined. Provide aggregates which are durable and sound, free from lumps and balls of clay, organic matter, objectionable coatings, and other foreign material. Material retained on the No. 4 sieve shall have a percentage of wear not to exceed 50 percent after 500 revolutions when tested as specified in ASTM C 131. At least 50 percent by weight retained on each sieve shall have one freshly fractured face with the area at least equal to 75 percent of the smallest mid-sectional area of the piece. Aggregate shall be reasonably uniform in density and quality. Aggregates shall have a maximum size of 2 inches and shall be within the limits specified as follows:

Maximum Allowable Percentage by Weight

Passing Square-Mesh Sieve

Sieve Designation
Rigid Pavement Base Course
No. 10
50
No. 200
8

Particles having diameters less than 0.02 mm shall not be in excess of 3 percent by weight of the total sample tested as determined in accordance with ASTM D 422. The portion of any blended component and of the completed course passing the No. 40 sieve shall be either nonplastic or shall have a liquid limit not greater than 25 and a plasticity index not greater than 8. The Contractor is responsible for any additional stability required to provide a working platform for construction equipment. If the Contractor can demonstrate with a test section that a material has adequate stability to support construction equipment, the fractured face requirement can be deleted, subject to the approval of the Contracting Officer.

PART 3 EXECUTION

3.1 OPERATION OF AGGREGATE SOURCES

Clearing, stripping and excavating are the responsibility of the Contractor. Operate the aggregate sources to produce the quantity and quality of materials meeting the specified requirements in the specified time limit. Upon completion of work, aggregate sources on Government property shall be conditioned to drain readily, and shall be left in a satisfactory condition. Aggregate sources on private lands shall be conditioned in agreement with local laws and authorities.

3.2 STOCKPILING MATERIAL

Prior to stockpiling of material, clear and level storage sites. Stockpile all materials, including approved material available from excavation and grading, in the manner and at the locations designated. Aggregates shall be stockpiled on the cleared and leveled areas designated by the Contracting Officer to prevent segregation. Materials obtained from different sources shall be stockpiled separately.

3.3 PREPARATION OF UNDERLYING MATERIAL

Prior to constructing the subbase or select-material subbase or rigid pavement base course, clean the underlying course or subgrade of all foreign substances. The surface of the underlying course or subgrade shall meet specified compaction and surface tolerances. Correct ruts, or soft yielding spots, in the underlying courses, subgrade areas having inadequate compaction, and deviations of the surface from the specified requirements, by loosening and removing soft or unsatisfactory material and by adding approved material, reshaping to line and grade, and recompacting to specified density requirements. For cohesionless underlying courses or subgrades containing sands or gravels, as defined in ASTM D 2487, the surface shall be stabilized prior to placement of the overlying course. Accomplish stabilization by mixing the overlying course material into the underlying course, and compacting by approved methods. The stabilized material shall be considered as part of the underlying course and shall meet all requirements for the underlying course. The finished underlying course shall not be disturbed by traffic or other operations and shall be maintained in a satisfactory condition until the overlying course is placed.

3.4 GRADE CONTROL

The finished and completed course shall conform to the lines, grades, and cross sections shown. The lines, grades, and cross sections shown shall be maintained by means of line and grade stakes placed by the Contractor at the work site.

3.5 MIXING AND PLACING MATERIALS

Mix and place the materials to obtain uniformity of the material at the water content specified. Make such adjustments in mixing or placing procedures or in equipment as may be directed to obtain the true grades, to minimize segregation and degradation, to reduce or accelerate loss or increase of water, and to insure a satisfactory subbase course.

3.6 LAYER THICKNESS

The compacted thickness of the completed course shall be as indicated. When a compacted layer of 6 inches is specified, the material may be placed in a single layer; when a compacted thickness of more than 6 inches is required, no layer shall be thicker than 6 inches nor be thinner than 3 inches when compacted.

3.7 COMPACTION

Compact each layer of the material, as specified, with approved compaction equipment. Maintain water content during the compaction procedure to within plus or minus 2 percent of optimum water content, as determined from laboratory tests, as specified in paragraph SAMPLING AND TESTING. In all places not accessible to the rollers, compact the mixture with hand-operated power tampers. Compaction of the subbase or select-material subbase shall continue until each layer is compacted through the full depth to at least 100 percent of laboratory maximum density. Compaction of the rigid base course shall continue until each layer is compacted through the full depth to at least 95 percent of laboratory maximum density. Make such adjustments in compacting or finishing procedures as may be directed to obtain true grades, to minimize segregation and degradation, to reduce or increase water content, and to ensure a satisfactory subbase course. Any materials that are found to be unsatisfactory shall be removed and replaced with satisfactory material or reworked, as directed, to meet the requirements of this specification.

3.8 PROOF ROLLING

Areas designated on the drawings to be proof rolled shall receive an application of 30 coverages with a heavy pneumatic-tired roller having four or more tires abreast, each tire loaded to a minimum of 30,000 pounds and inflated to a minimum of 125 psi. A coverage is defined as the application of one tire print over the designated area. In the areas designated, apply proof rolling to the top layer of the subbase course. Maintain water content of the top layer of the subbase course such that the water content is within plus or minus 2 percent of optimum water content, as determined from laboratory tests, as specified in paragraph SAMPLING AND TESTING. Any material in the subbase courses or underlying materials indicated to be unsatisfactory by the proof rolling shall be removed, dried, and recompacted, or removed and replaced with satisfactory materials.

3.9 EDGES

Place approved material along the edges of the subbase and select-material subbase course in such quantity as will compact to the thickness of the course being constructed. When the course is being constructed in two or more layers, at least a 1 foot width of the shoulder shall be rolled and compacted simultaneously with the rolling and compacting of each layer of the subbase course, as directed.

3.10 SMOOTHNESS TEST

The surface of the top layer shall show no deviations in excess of 3/8 inch when tested with a 12 foot straightedge. Take measurements in successive positions parallel to the centerline of the area to be paved. Measurements shall also be taken perpendicular to the centerline at 50 foot intervals. Correct deviations exceeding this amount by removing material and replacing with new material, or by reworking existing material and compacting it to meet these specifications.

3.11 THICKNESS CONTROL

The completed thickness of the course(s) shall be in accordance with the thickness and grade indicated on the drawings. The completed course shall not be more than 1/2 inch deficient in thickness nor more than 1/2 inch above or below the established grade. Where any of these tolerances are exceeded, correct such areas by scarifying, adding new material of proper gradation or removing material, and compacting, as directed. Where the measured thickness is 1/2 inch or more thicker than shown, the course will be considered as conforming with the specified thickness requirements plus 1/2 inch. The average job thickness shall be the average of the job measurements as specified above but within 1/4 inch of the thickness shown.

3.12 MAINTENANCE

Maintain the completed course in a satisfactory condition until accepted.

3.13 DISPOSITION OF MATERIAL

All waste materials demolished shall be removed from the government property to an approved landfill site.

-- End of Section --