This is a Solicitation, Offer, and Award document (Standard Form 1442) for a construction project titled CDC Playground Refresh (Project MAHG22-5001) at Keesler Air Force Base, Mississippi.

The requirement consists of architecture and engineering (A&E) design services (CLIN 0001) with a maximum not to exceed ten percent of construction costs, plus construction for a Preschool Playground (CLIN 0002). Optional line items include construction for an Infant Playground (CLIN 0003), Pretoddler Playground (CLIN 0004), Toddler Playground (CLIN 0005), and School-Age Care/Youth Program Playground (CLIN 0006). The contract will be funded by Non-Appropriated Funds (NAF), making FAR and DFARS regulations inapplicable. The base period of performance is 180 calendar days with option CLINs available. All work must be completed within 180 calendar days after award, with design services due within 120 calendar days of award and construction within 60 calendar days of notice to proceed. The solicitation is issued as a Request for Quote on an unrestricted, full and open competition basis. Performance and payment bonds are required within 10 calendar days of award. Sealed offers are due by 10:00 AM CST on January 5, 2027, at Keesler AFB. An organized site visit is scheduled for December 9, 2026, at 9:00 AM CST, and questions must be submitted by December 16, 2026, at 10:00 AM CST. Award will be made on an all, some, or none basis to the lowest price technically acceptable offer. Evaluation will consider price, technical proposal, and past performance information from the last five years.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION

NUMBER

FA301027Q0002

2. TYPE OF SOLICITATION

SEALED BID (IFB) INVITATION

FOR BID

NEGOTIATED (RFP) REQUEST

FOR PROPOSAL

3. DATE ISSUED

20 Nov 2026

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

MAHG22-5001

7. ISSUED BY CODE: FA3010

FA3010 81 CONS CC

310 M ST BLDG 4605, CP 228 377 3230

KEESLER AFB, MS 39534-2701

UNITED STATES

Zachary Willard, Email: zachary.willard.1@us.af.mil Telephone: 2283770510 Tiffany Aultman, Email: tiffany.aultman@us.af.mil Telephone: 228-377-1807

8. ADDRESS OFFER TO

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

9. FOR

INFORMATION

CALL:

a. NAME Zachary Willard

b. TELEPHONE NUMBER (include area code) (NO COLLECT CALLS) 2283770510

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

10.THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

Project Title: CDC Playground Refresh Project Location: Keesler AFB, MS

Project Title: MAHG22-5001 CDC Playground Refresh Project Location: Keesler AFB, MS

This requirement is being competed as a Request for Quote unrestricted/full and open competition.

Enter price in Section B. All Amendments to this solicitation (if any) must be acknowledged.

An organized site visit has been set for 9 December 2026 at 9:00 AM CST. In order to gain access to the base to attend the site visit, you must have a valid driver's license/identification card, valid registration for any vehicle you will be operating, and proof of insurance. Questions regarding this solicitation and the site visit must be submitted via email to the two personnel specified in block seven of this document no later than 16 December 2026 at 10:00 A.M. CST.

This contract will be funded by Non-Appropriated Funds (NAF) and will adhere to NAF guidance, regulations, and clauses. FAR and DFARS regulations are not applicable. The base period of performance is 180 days (CLIN 0001 and 0002) with the option of awarding CLIN0003 - 0006. This requirement will be awarded on an all, some or none basis. The contractor shall perform all work as specified in the statement of work, specifications, and drawings for the project.

Your attention is directed to Section L for Proposal Preparation and Section M for Evaluation Factors for Award.

The Government reserves the right to cancel this solicitation, either before or after the closing date for receipt of proposals. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs.

11. The contractor shall begin performance within calendar days and complete it within calendar days after receiving 10 180 award, notice to proceed. This performance period is mandatory negotiable. (See ). FAR 52.211-10

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

YES NO

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) 1 10:00 AM local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes 05 Jan 2027 containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected. 90

Computer generated. STANDARD FORM 1442 (REV. 12/2022) Prescribed by GSA-FAR (48CFR) 53.236-1(d)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED

STATES CODE AT

10 U.S.C 3204(a) ( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document

Contractor agrees to furnish and return copies to issuing office.)

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

Computer generated. STANDARD FORM 1442 (REV. 12/2022) BACK

Section A - Solicitation/Contract Form CDC Playground Refresh (Project MAHG22-5001)

NAICS: 238990

Size Standard: USD 19,000,000.00 Annual receipts

Product Service Code: Y1PA

FA301027Q0002

Section B - Supplies or Services & Prices or Costs Additional Information/Notes

Item Supplies / Services Quantity Unit Unit Price Amount

A&E Design Services in accordance with MAHG22-5001 attachments (See Section J).

NOTE: Design (CLIN 0001) shall not exceed ten percent of the project's construction costs (CLIN's 0002, 0003, 0004, 0005, 0006) in accordance with 10 U.S.C. 7540, 8612, and 9540 limitations as of 30 October 2026.

Product Service Code: C211 Pricing Arrangement: Firm Fixed Price

1 Lot

Construction in accordance with MAHG22-5001 Statement of Work paragraph 3.2., Preschool Playground.

Product Service Code: C211 Pricing Arrangement: Firm Fixed Price

1 Lot

Option Line Item 0003

Construction in accordance with MAHG22-5001 Statement of Work paragraph 3.3.1., Infant Playground.

Product Service Code: C211 Pricing Arrangement: Firm Fixed Price

1 Lot

Option Line Item 0004

Construction in accordance with MAHG22-5001 Statement of Work paragraph 3.3.2., Pretoddler Playground.

Product Service Code: C211 Pricing Arrangement: Firm Fixed Price

1 Lot

Option Line Item 0005

Construction in accordance with MAHG22-5001 Statement of Work paragraph 3.3.3., Toddler Playground.

Product Service Code: C211 Pricing Arrangement: Firm Fixed Price

1 Lot

Option Line Item 0006

Construction in accordance with MAHG22-5001 Statement of Work paragraph 3.3.4., School-Age Care / Youth Program Playground.

Product Service Code: C211 Pricing Arrangement: Firm Fixed Price

1 Lot

Section C - Description/Specifications/Statement of Work

Requirements CDC Playground Refresh (Project MAHG225001)

Section D - Packaging and Marking

Section E - Inspection and Acceptance Overall Contract Inspection/Acceptance Locations

Inspection and Acceptance Location

Both Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.

DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.

DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Option Line Item 0003

Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.

DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil Telephone: 2283778555

Option Line Item 0004

Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.

DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil

Option Line Item 0005

Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.

DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil

Option Line Item 0006

Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.

DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil Telephone: 2283778555

Section F - Deliveries or Performance Overall Contract Delivery Period

Line Item Delivery Schedule Quantity Address and POC

Delivery Schedule From date of lead time event to completion of performance 120 Calendar Days Date of Award

1 Lot Place of Performance DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil Telephone: 2283778555

Delivery Schedule From date of lead time event to completion of performance 60 Calendar Days Date of Notice to Proceed Receipt

1 Lot Place of Performance DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil Telephone: 2283778555

Option Line Item 0003

Delivery Schedule From date of lead time event to completion of performance 45 Calendar Days Date of Notice to Proceed Receipt

1 Lot Place of Performance DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil Telephone: 2283778555

Option Line Item 0004

Delivery Schedule From date of lead time event to completion of performance 45 Calendar Days Date of Notice to Proceed Receipt

1 Lot Place of Performance DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil Telephone: 2283778555

Option Line Item 0005

Delivery Schedule From date of lead time event to completion of performance 45 Calendar Days Date of Notice to Proceed Receipt

1 Lot Place of Performance DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil Telephone: 2283778555

Option Line Item 0006

Delivery Schedule From date of lead time event to completion of performance 75 Calendar Days Date of Notice to Proceed Receipt

1 Lot Place of Performance DoDAAC: FA3010 CountryCode: USA

FA3010 81 CONS

BLDG 701 CP 228-377-1852, 500 FISHER ST

KEESLER AFB, MS 39534-2701

UNITED STATES

Phillip Steffen Email: phillip.steffen.2@us.af.mil Telephone: 2283778555

Section G - Contract Administration Data

INVOICES

An addendum to the Section I Invoice Section:

a. An invoice is a written request for payment under the contract for supplies delivered or for services rendered. In order to be proper, an invoice should include (and in order to support the payment of interest penalties, must include) the following:

(1) Invoice date;

(2) Name of Contractor;

(3) Contract number (including order number, if any), contract line item number, contract description of supplies or services, quantity, contract unit of measure and unit price, and extended total;

(4) Shipment number and date of shipment (Bill of Lading number and weight of shipment will be shown for shipments on NAFI Bills of Lading);

(5) Name and address to which payment is to be sent (which must be the same as that in the contract or on a proper notice of assignment);

(6) Name (where practicable), title, phone number and mailing address of person to be notified in event of a defective invoice; and

(7) Any other information or documentation required by other clauses of the contract (such as evidence of shipment). Invoices shall be prepared and submitted in duplicate (one copy shall be marked "Original") unless otherwise specified.

(8) Progress report(s);

(9) Certification information from invoices, in accordance with FAR 52.232-5;

(10) Subcontractor breakout;

b. For purposes of determining if interest begins to accrue under the Prompt Payment Act (Public Law 97-177):

(1) A proper invoice will be deemed to have been received when it is received by the office designated in the contract for receipt of invoices and acceptance of the supplies delivered or services rendered has occurred.

(2) Payment shall be considered made on the date on which a check for such payment is dated.

(3) Payment terms (e.g., "Net 20") offered by the contractor will not be deemed required payment dates.

(4) The following periods of time will not be included:

(a) After receipt of improper invoice and prior to notice of any defect or impropriety, but not to exceed three days for meat and meat food products, five days for perishable agricultural commodities, and 15 days in all other cases, and

(b) Between the date of a notice of any defect or impropriety and the date a proper invoice is received. When the notice is in writing, it shall be considered made on the date shown on the notice.

(End of clause)

Section H - Special Contract Requirements Ombudsman:

An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the interested party to another official who can resolve the concern.

Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).

If resolution cannot be made by the contracting officer, the interested party may contact the ombudsman, Juan Martinez, Director of Staff, AFICC/KT, 2035 First Street West, JBSA Randolph TX 78150-4304, telephone 210-487-1722, juan.martinez.2@us.af.mil. Concerns, issues, disagreements, and recommendations that cannot be resolved at the AETC ombudsman level, may be brought by the interested party for further consideration to the Department of the Air Force ombudsman, Associate Deputy Assistant Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330-1060, phone number (571) 256-2395, facsimile number (571) 256-2431.

The ombudsman has no authority to render a decision that binds the agency.

Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the contracting officer.

(a) Contractors shall not: (1) Provide any service or product with any specification, standard, drawing, or other document that requires the Ozone Depleting Substances:

use of a Class I ODS in the test, operation, or maintenance of any system, subsystem, item, component, or process; or (2) Provide any specification, standard, drawing, or other document that establishes a test, operation, or maintenance requirement that can only be met by use of a Class I ODS as part of this contract/order. [Note: This prohibition does not apply to manufacturing.] (b) For the purposes of Air Force policy, the following products that are pure (i.e., they meet the relevant product specification identified in AFI 32- 7086) are Class I ODSs: (1) Halons: 1011, 1202, 1211, 1301, and 2402; (2) Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114, CFC-115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC-217, and the blends R-500, R-501, R-502, and R-503;

and (3) Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide. [NOTE: Material that uses one or more of these Class I ODSs as minor constituents do not meet the Air Force definition of a Class I ODS.]

(a) Contractors shall incorporate inclement weather delays into their schedules with reference to historic data as shown at the below link. Jan: Inclement Weather Impacts:

9; Feb: 8; Mar: 8; Apr: 2; May: 11; Jun: 14; Jul 11; Aug: 8; Sep: 1; Oct: 7; Nov: 1; Dec: 10.

https://weatherspark.com/h/m/146441/2025/1/Historical-Weather-in-January-2025-at-Biloxi-Keesler-Air-Force-Base-Navu;-Mississippi;-United-States#Figures- PrecipitationProbability

DOD Antiterrorism Awareness Training for Contractors

Contractors and their employees requiring routine physical access to a Federally controlled facility or military installation are required to complete the computer-based Level 1 Anti-Terrorism Training found at .https://jkodirect.jten.mil/Atlas2/page/login/login.jsf

Contractor shall submit a report on completed training to the Contracting Officer at the start of the contract, and on an annual basis thereafter when applicable, for all prime and subcontractor employees who will routinely work on Keesler AFB for the duration of the contract period of performance.

Government Property

(a) Definitions. As used in this clause

Cannibalize means to remove parts from Government property for use or for installation on other Government property.

Contractor-acquired property means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract, and to which the Government has title.

FA301027Q0002

https://weatherspark.com/h/m/146441/2025/1/Historical-Weather-in-January-2025-at-Biloxi-Keesler-Air-Force-Base-Navu;-Mississippi;-United-States#Figures-PrecipitationProbability https://weatherspark.com/h/m/146441/2025/1/Historical-Weather-in-January-2025-at-Biloxi-Keesler-Air-Force-Base-Navu;-Mississippi;-United-States#Figures-PrecipitationProbability https://jkodirect.jten.mil/Atlas2/page/login/login.jsf

Contractor inventory means-

(1) Any property acquired by and in the possession of a Contractor or subcontractor under a contract for which title is vested in the Government and which exceeds the amounts needed to complete full performance under the entire contract;

(2) Any property that the Government is obligated or has the option to take over under any type of contract, e.g., as a result either of any changes in the specifications or plans thereunder or of the termination of the contract (or subcontract thereunder), before completion of the work, for the convenience or at the option of the Government; and

(3) Government-furnished property that exceeds the amounts needed to complete full performance under the entire contract.

Contractor's managerial personnel means the Contractor's directors, officers, managers, superintendents, or equivalent representatives who have supervision or direction of-

(1) All or substantially all of the Contractor's business;

(2) All or substantially all of the Contractor's operation at any one plant or separate location; or

(3) A separate and complete major industrial operation.

Demilitarization means rendering a product unusable for, and not restorable to, the purpose for which it was designed or is customarily used.

Discrepancies incident to shipment means any differences (e.g., count or condition) between the items documented to have been shipped and items actually received.

Equipment means a tangible item that is functionally complete for its intended purpose, durable, nonexpendable, and needed for the performance of a contract. Equipment is not intended for sale, and does not ordinarily lose its identity or become a component part of another article when put into use. Equipment does not include material, real property, special test equipment or special tooling.

Government-furnished property means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract.

Government property means all property owned or leased by the Government. Government property includes both Government- furnished and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.

Loss of Government property means unintended, unforeseen or accidental loss, damage or destruction to Government property that reduces the Government's expected economic benefits of the property. Loss of Government property does not include purposeful destructive testing, obsolescence, normal wear and tear or manufacturing defects. Loss of Government property includes, but is not limited to-

(1) Items that cannot be found after a reasonable search;

(2) Theft;

(3) Damage resulting in unexpected harm to property requiring repair to restore the item to usable condition; or

(4) Destruction resulting from incidents that render the item useless for its intended purpose or beyond economical repair.

Material means property that may be consumed or expended during the performance of a contract, component parts of a higher assembly, or items that lose their individual identity through incorporation into an end item. Material does not include equipment, special tooling, special test equipment or real property.

Nonseverable means property that cannot be removed after construction or installation without substantial loss of value or damage to the installed property or to the premises where installed.

Precious metals means silver, gold, platinum, palladium, iridium, osmium, rhodium, and ruthenium.

Production scrap means unusable material resulting from production, engineering, operations and maintenance, repair, and research and development contract activities. Production scrap may have value when re-melted or reprocessed, e.g., textile and metal clippings, borings, and faulty castings and forgings.

Property means all tangible property, both real and personal.

Property Administrator means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.

Property records means the records created and maintained by the contractor in support of its stewardship responsibilities for the management of Government property.

Provide means to furnish, as in Government-furnished property, or to acquire, as in contractor-acquired property.

Real property See Federal Management Regulation 102-71.20 (41 CFR 102-71.20).

Sensitive property means property potentially dangerous to the public safety or security if stolen, lost, or misplaced, or that shall be subject to exceptional physical security, protection, control, and accountability. Examples include weapons, ammunition, explosives, controlled substances, radioactive materials, hazardous materials or wastes, or precious metals.

Unit acquisition cost means-

(1) For Government-furnished property, the dollar value assigned by the Government and identified in the contract; and

(2) For contractor-acquired property, the cost derived from the Contractor's records that reflect consistently applied generally accepted accounting principles.

(b) Property management. (1) The Contractor shall have a system of internal controls to manage (control, use, preserve, protect, repair, and maintain) Government property in its possession. The system shall be adequate to satisfy the requirements of this clause. In doing so, the Contractor shall initiate and maintain the processes, systems, procedures, records, and methodologies necessary for effective and efficient control of Government property. The Contractor shall disclose any significant changes to its property management system to the Property Administrator prior to implementation of the changes.

The Contractor may employ customary commercial practices, voluntary consensus standards, or industry-leading practices and standards that provide effective and efficient Government property management that are necessary and appropriate for the performance of this contract (except where inconsistent with law or regulation).

(2) The Contractor's responsibility extends from the initial acquisition and receipt of property, through stewardship, custody, and use until formally relieved of responsibility by authorized means, including delivery, consumption, expending, sale (as surplus property), or other disposition, or via a completed investigation, evaluation, and final determination for lost property. This requirement applies to all Government property under the Contractor's accountability, stewardship, possession or control, including its vendors or subcontractors (see paragraph (f)(1)(v) of this clause).

(3) The Contractor shall include the requirements of this clause in all subcontracts under which Government property is acquired or furnished for subcontract performance.

(4) The Contractor shall establish and maintain procedures necessary to assess its property management system effectiveness and shall perform periodic internal reviews, surveillances, self assessments, or audits. Significant findings or results of such reviews and audits pertaining to Government property shall be made available to the Property Administrator.

(c) Use of Government property. (1) The Contractor shall use Government property, either furnished or acquired under this contract, only for performing this contract, unless otherwise provided for in this contract or approved by the Contracting Officer.

(2) Modifications or alterations of Government property are prohibited, unless they are-

(i) Reasonable and necessary due to the scope of work under this contract or its terms and conditions;

(ii) Required for normal maintenance; or

(iii) Otherwise authorized by the Contracting Officer.

(3) The Contractor shall not cannibalize Government property unless otherwise provided for in this contract or approved by the Contracting Officer.

(d) Government-furnished property. (1) The Government shall deliver to the Contractor the Government-furnished property described in this contract. The Government shall furnish related data and information needed for the intended use of the property. The warranties of suitability of use and timely delivery of Government-furnished property do not apply to property acquired or fabricated by the Contractor as contractor-acquired property and subsequently transferred to another contract with this Contractor.

(2) The delivery and/or performance dates specified in this contract are based upon the expectation that the Government-furnished property will be suitable for contract performance and will be delivered to the Contractor by the dates stated in the contract.

(i) If the property is not delivered to the Contractor by the dates stated in the contract, the Contracting Officer shall, upon the Contractor's timely written request, consider an equitable adjustment to the contract.

(ii) In the event property is received by the Contractor, or for Government-furnished property after receipt and installation, in a condition not suitable for its intended use, the Contracting Officer shall, upon the Contractor's timely written request, advise the Contractor on a course of action to remedy the problem. Such action may include repairing, replacing, modifying, returning, or otherwise disposing of the property at the Government's expense. Upon completion of the required action(s), the Contracting Officer shall consider an equitable adjustment to the contract (see also paragraph (f)(1)(ii)(A) of this clause).

(iii) The Government may, at its option, furnish property in an "as-is" condition. The Contractor will be given the opportunity to inspect such property prior to the property being provided. In such cases, the Government makes no warranty with respect to the serviceability and/or suitability of the property for contract performance. Any repairs, replacement, and/or refurbishment shall be at the Contractor's expense.

(3) (i) The Contracting Officer may by written notice, at any time-

(A) Increase or decrease the amount of Government-furnished property under this contract;

(B) Substitute other Government-furnished property for the property previously furnished, to be furnished, or to be acquired by the Contractor for the Government under this contract; or

(C) Withdraw authority to use property.

(ii) Upon completion of any action(s) under paragraph (d)(3)(i) of this clause, and the Contractor's timely written request, the Contracting Officer shall consider an equitable adjustment to the contract.

(e) Title to Government property. (1) All Government-furnished property and all property acquired by the Contractor, title to which vests in the Government under this paragraph (collectively referred to as "Government property"), is subject to the provisions of this clause. The Government shall retain title to all Government-furnished property. Title to Government property shall not be affected by its incorporation into or attachment to any property not owned by the Government, nor shall Government property become a fixture or lose its identity as personal property by being attached to any real property.

(2) Title vests in the Government for all property acquired or fabricated by the Contractor in accordance with the financing provisions or other specific requirements for passage of title in the contract. Under fixed price type contracts, in the absence of financing provisions or other specific requirements for passage of title in the contract, the Contractor retains title to all property acquired by the Contractor for use on the contract, except for property identified as a deliverable end item. If a deliverable item is to be retained by the Contractor for use after inspection and acceptance by the Government, it shall be made accountable to the contract through a contract modification listing the item as Government-furnished property.

(3) Title under Cost-Reimbursement or Time-and-Material Contracts or Cost-Reimbursable line items under Fixed Price contracts. (i) Title to all property purchased by the Contractor for which the Contractor is entitled to be reimbursed as a direct item of cost under this contract shall pass to and vest in the Government upon the vendor's delivery of such property.

(ii) Title to all other property, the cost of which is reimbursable to the Contractor, shall pass to and vest in the Government upon-

(A) Issuance of the property for use in contract performance;

(B) Commencement of processing of the property for use in contract performance; or

(C) Reimbursement of the cost of the property by the Government, whichever occurs first.

(f) Contractor plans and systems. (1) Contractors shall establish and implement property management plans, systems, and procedures at the contract, program, site or entity level to enable the following outcomes:

(i) Acquisition of Property. The Contractor shall document that all property was acquired consistent with its engineering, production planning, and property control operations.

(ii) Receipt of Government Property. The Contractor shall receive Government property and document the receipt, record the information necessary to meet the record requirements of paragraph (f)(1)(iii)(A)(1) through (5) of this clause, identify as Government owned in a manner appropriate to the type of property (e.g., stamp, tag, mark, or other identification), and manage any discrepancies incident to shipment.

(A) Government-furnished property. The Contractor shall furnish a written statement to the Property Administrator containing all relevant facts, such as cause or condition and a recommended course(s) of action, if overages, shortages, or damages and/or other discrepancies are discovered upon receipt of Government-furnished property.

(B) Contractor-acquired property. The Contractor shall take all actions necessary to adjust for overages, shortages, damage and/or other discrepancies discovered upon receipt, in shipment of Contractor-acquired property from a vendor or supplier, so as to ensure the proper allocability and allowability of associated costs.

(iii) Records of Government property. The Contractor shall create and maintain records of all Government property accountable to the contract, including Government-furnished and Contractor-acquired property.

(A) Property records shall enable a complete, current, auditable record of all transactions and shall, unless otherwise approved by the Property Administrator, contain the following:

(1) The name, part number and description, National Stock Number (if needed for additional item identification tracking and/or disposition), and other data elements as necessary and required in accordance with the terms and conditions of the contract.

(2) Quantity received (or fabricated), issued, and balance-on-hand.

(3) Unit acquisition cost.

(4) Unique-item identifier or equivalent (if available and necessary for individual item tracking).

(5) Unit of measure.

(6) Accountable contract number or equivalent code designation.

(7) Location.

(8) Disposition.

(9) Posting reference and date of transaction.

(10) Date placed in service (if required in accordance with the terms and conditions of the contract).

(B) Use of a Receipt and Issue System for Government Material. When approved by the Property Administrator, the Contractor may maintain, in lieu of formal property records, a file of appropriately cross-referenced documents evidencing receipt, issue, and use of material that is issued for immediate consumption.

(iv) Physical inventory. The Contractor shall periodically perform, record, and disclose physical inventory results. A final physical inventory shall be performed upon contract completion or termination. The Property Administrator may waive this final inventory requirement, depending on the circumstances (e.g., overall reliability of the Contractor's system or the property is to be transferred to a follow-on contract).

(v) Subcontractor control. (A) The Contractor shall award subcontracts that clearly identify items to be provided and the extent of any restrictions or limitations on their use. The Contractor shall ensure appropriate flow down of contract terms and conditions (e.g., extent of liability for loss of Government property.

(B) The Contractor shall assure its subcontracts are properly administered and reviews are periodically performed to determine the adequacy of the subcontractor's property management system.

(vi) Reports. The Contractor shall have a process to create and provide reports of discrepancies, loss of Government property, physical inventory results, audits and self-assessments, corrective actions, and other property-related reports as directed by the Contracting Officer.

(vii) Relief of stewardship responsibility and liability. The Contractor shall have a process to enable the prompt recognition, investigation, disclosure and reporting of loss of Government property, including losses that occur at subcontractor or alternate site locations.

(A) This process shall include the corrective actions necessary to prevent recurrence.

(B) Unless otherwise directed by the Property Administrator, the Contractor shall investigate and report to the Government all incidents of property loss as soon as the facts become known. Such reports shall, at a minimum, contain the following information:

(1) Date of incident (if known).

(2) The data elements required under paragraph (f)(1)(iii)(A) of this clause.

(3) Quantity.

(4) Accountable contract number.

(5) A statement indicating current or future need.

(6) Unit acquisition cost, or if applicable, estimated sales proceeds, estimated repair or replacement costs.

(7) All known interests in commingled material of which includes Government material.

(8) Cause and corrective action taken or to be taken to prevent recurrence.

(9) A statement that the Government will receive compensation covering the loss of Government property, in the event the Contractor was or will be reimbursed or compensated.

(10) Copies of all supporting documentation.

(11) Last known location.

(12) A statement that the property did or did not contain sensitive, export controlled, hazardous, or toxic material, and that the appropriate agencies and authorities were notified.

(C) Unless the contract provides otherwise, the Contractor shall be relieved of stewardship responsibility and liability for property when-

(1) Such property is consumed or expended, reasonably and properly, or otherwise accounted for, in the performance of the contract, including reasonable inventory adjustments of material as determined by the Property Administrator;

(2) Property Administrator grants relief of responsibility and liability for loss of Government property;

(3) Property is delivered or shipped from the Contractor's plant, under Government instructions, except when shipment is to a subcontractor or other location of the Contractor; or

(4) Property is disposed of in accordance with paragraphs (j) and (k) of this clause.

(viii) Utilizing Government property. (A) The Contractor shall utilize, consume, move, and store Government Property only as authorized under this contract. The Contractor shall promptly disclose and report Government property in its possession that is excess to contract performance.

(B) Unless otherwise authorized in this contract or by the Property Administrator the Contractor shall not commingle Government material with material not owned by the Government.

(ix) Maintenance. The Contractor shall properly maintain Government property. The Contractor's maintenance program shall enable the identification, disclosure, and performance of normal and routine preventative maintenance and repair.

The Contractor shall disclose and report to the Property Administrator the need for replacement and/or capital rehabilitation.

(x) Property closeout. The Contractor shall promptly perform and report to the Property Administrator contract property closeout, to include reporting, investigating and securing closure of all loss of Government property cases; physically inventorying all property upon termination or completion of this contract; and disposing of items at the time they are determined to be excess to contractual needs.

(2) The Contractor shall establish and maintain Government accounting source data, as may be required by this contract, particularly in the areas of recognition of acquisitions, loss of Government property, and disposition of material and equipment.

(g) Systems analysis. (1) The Government shall have access to the Contractor's premises and all Government property, at reasonable times, for the purposes of reviewing, inspecting and evaluating the Contractor's property management plan(s), systems, procedures, records, and supporting documentation that pertains to Government property. This access includes all site locations and, with the Contractor's consent, all subcontractor premises.

(2) Records of Government property shall be readily available to authorized Government personnel and shall be appropriately safeguarded.

(3) Should it be determined by the Government that the Contractor's (or subcontractor's) property management practices are inadequate or not acceptable for the effective management and control of Government property under this contract, or present an undue risk to the Government, the Contractor shall prepare a corrective action plan when requested by the Property Administrator and take all necessary corrective actions as specified by the schedule within the corrective action plan.

(h) Contractor Liability for Government Property. (1) The Contractor assumes the risk of, and shall be responsible for, any loss of Government property upon its delivery to the Contractor as Government-furnished property. However, the Contractor is not responsible for reasonable wear and tear to Government property or for Government property properly consumed in performing this contract.

(2) The Contractor shall take all reasonable actions necessary to protect the property from further loss. The Contractor shall separate the damaged and undamaged property, place all the affected property in the best possible order, and take such other action as the Property Administrator directs.

(3) The Contractor shall do nothing to prejudice the Government's rights to recover against third parties for any loss of Government property.

(4) The Contractor shall reimburse the Government for loss of Government property, to the extent that the Contractor is financially liable for such loss, as directed by the Contracting Officer.

(5) Upon the request of the Contracting Officer, the Contractor shall, at the Government's expense, furnish to the Government all reasonable assistance and cooperation, including the prosecution of suit and the execution of instruments of assignment in favor of the Government in obtaining recovery.

(i) Equitable adjustment. Equitable adjustments under this clause shall be made in accordance with the procedures of the Changes clause. However, the Government shall not be liable for breach of contract for the following:

(1) Any delay in delivery of Government-furnished property.

(2) Delivery of Government-furnished property in a condition not suitable for its intended use.

(3) An increase, decrease, or substitution of Government-furnished property.

(4) Failure to repair or replace Government property for which the Government is responsible.

(j) Contractor inventory disposal. Except as otherwise provided for in this contract, the Contractor shall not dispose of Contractor inventory until authorized to do so by the Plant Clearance Officer or authorizing official.

(1) Predisposal requirements. (i) If the Contractor determines that the property has the potential to fulfill requirements under other contracts, the Contractor, in consultation with the Property Administrator, shall request that the Contracting Officer transfer the property to the contract in question, or provide authorization for use, as appropriate. In lieu of transferring the property, the Contracting Officer may authorize the Contractor to credit the costs of Contractor-acquired property (material only) to the losing contract, and debit the gaining contract with the corresponding cost, when such material is needed for use on another contract. Property no longer needed shall be considered contractor inventory.

(ii) For any remaining Contractor-acquired property, the Contractor may purchase the property at the unit acquisition cost if desired or make reasonable efforts to return unused property to the appropriate supplier at fair market value (less, if applicable, a reasonable restocking fee that is consistent with the supplier's customary practices.)

(2) Inventory disposal schedules. (i) Absent separate contract terms and conditions for property disposition, and provided the property was not reutilized, transferred, or otherwise disposed of, the Contractor, as directed by the Plant Clearance Officer or authorizing official, shall use Standard Form 1428, Inventory Disposal Schedule or electronic equivalent, to identify and report-

(A) Government-furnished property that is no longer required for performance of this contract;

(B) Contractor-acquired property, to which the Government has obtained title under paragraph (e) of this clause, which is no longer required for performance of that contract; and

(C) Termination inventory.

(ii) The Contractor may annotate inventory disposal schedules to identify property the Contractor wishes to purchase from the Government, in the event that the property is offered for sale.

(iii) Separate inventory disposal schedules are required for aircraft in any condition, flight safety critical aircraft parts, and other items as directed by the Plant Clearance Officer.

(iv) The Contractor shall provide the information required by FAR 52.245-1(f)(1)(iii) along with the following:

(A) Any additional information that may facilitate understanding of the property's intended use.

(B) For work-in-progress, the estimated percentage of completion.

(C) For precious metals in raw or bulk form, the type of metal and estimated weight.

(D) For hazardous material or property contaminated with hazardous material, the type of hazardous material.

(E) For metals in mill product form, the form, shape, treatment, hardness, temper, specification (commercial or Government) and dimensions (thickness, width and length).

(v) Property with the same description, condition code, and reporting location may be grouped in a single line item.

(vi) Scrap should be reported by "lot" along with metal content, estimated weight and estimated value.

(3) Submission requirements. (i) The Contractor shall submit inventory disposal schedules to the Plant Clearance Officer no later than-

(A) 30 days following the Contractor's determination that a property item is no longer required for performance of this contract;

(B) 60 days, or such longer period as may be approved by the Plant Clearance Officer, following completion of contract deliveries or performance; or

(C) 120 days, or such longer period as may be approved by the Termination Contracting Officer, following contract termination in whole or in part.

(ii) Unless the Plant Clearance Officer determines otherwise, the Contractor need not identify or report production scrap on inventory disposal schedules, and may process and dispose of production scrap in accordance with its own internal scrap procedures. The processing and disposal of other types of Government-owned scrap will be conducted in accordance with the terms and conditions of the contract or Plant Clearance Officer direction, as appropriate.

(4) Corrections. The Plant Clearance Officer may-

(i) Reject a schedule for cause (e.g., contains errors, determined to be inaccurate); and

(ii) Require the Contractor to correct an inventory disposal schedule.

(5) Postsubmission adjustments. The Contractor shall notify the Plant Clearance Officer at least 10 working days in advance of its intent to remove an item from an approved inventory disposal schedule. Upon approval of the Plant Clearance Officer, or upon expiration of the notice period, the Contractor may make the necessary adjustments to the inventory schedule.

(6) Storage. (i) The Contractor shall store the property identified on an inventory disposal schedule pending receipt of disposal instructions. The Government's failure to furnish disposal instructions within 120 days following acceptance of an inventory disposal schedule may entitle the Contractor to an equitable adjustment for costs incurred to store such property on or after the 121st day.

(ii) The Contractor shall obtain the Plant Clearance Officer's approval to remove property from the premises where the property is currently located prior to receipt of final disposition instructions. If approval is granted, any costs incurred by the Contractor to transport or store the property shall not increase the price or fee of any Government contract. The storage area shall be appropriate for assuring the property's physical safety and suitability for use. Approval does not relieve the Contractor of any liability for such property under this contract.

(7) Disposition instructions. (i) The Contractor shall prepare for shipment, deliver f.o.b. origin, or dispose of Contractor inventory as directed by the Plant Clearance Officer. Unless otherwise directed by the Contracting Officer or by the Plant Clearance Officer, the Contractor shall remove and destroy any markings identifying the property as U.S. Government-owned property prior to its disposal.

(ii) The Contracting Officer may require the Contractor to demilitarize the property prior to…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .