Attachment 6 - MAHG261006 Questions and Answers.pdf
PDF 142 KB Posted
- Attached to
- Extend Perimeter Fence at Division St. Gate
- Solicitation number
- FA301026Q0032
About this file
This is a Questions and Answers document for the federal contract solicitation MAHG261006 "Extend Perimeter Fence at Division St. Gate" (Solicitation Number FA301026Q0032).
The project requires extension of perimeter fencing to match existing Ameristar fencing design, with gates matching the 8-foot high fencing specification. Key requirements include: installation of fence rails capable of accommodating steel and/or sensor cables (though no cabling will be installed); contractor responsibility for all fill, grading, and positive drainage; protection of existing storm drain infrastructure with potential fence realignment; sodding of all disturbed areas; and obtaining a dig permit. The contractor must provide a complete and useable system and is responsible for site traffic coordination with Security Forces (SFS) on commercial gate access plans. No asbestos or lead is anticipated on the project. No anti-ram cable rating applies to the fencing or gates. Site work begins 10 days after award, contingent upon submittal approval. Third-party inspections are governed by SOW Section 12.1. No additional drawings beyond Attachment 2 will be provided. Parking spaces adjacent to the project may be closed only during active work phases, not for the full project duration. Existing palm trees within project limits are not approved for removal.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions: Answers:
Will the Government be releasing any additional blueprints or drawings beyond what is included as Attachment 2 to the solicitation?
No additional drawings will be provided.
Can we get clarification on the Ameristar fence style. Fence line footages state the Impasse II design, but the fence and gate details appear to show the Stalwart IS Gauntlet design, which has 4 runners rather than the 3 runners on the Impasse II. Please confirm which style is required.
The design of the installed fence must match the existing fencing.
Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.
It is not anticipated that asbestos or lead that will be encountered during this project.
Is this project tax exempt? No, the project is not tax exempt.
When do you anticipate on site work starting?
Site work will begin once submittals are approved. Project start is 10 days after award.
Are third party inspections required?
See SOW Section 12.1 INSPECTION AND ACCEPTANCE for inspection information.
Is permitting required? A dig permit will be required for this project.
Is any landscaping restoration required for this project? For example; topsoil, seeding, and fertilizer.
All disturbed areas are to be sodded.
Will the contractor be required to maintain construction traffic access throughout the project duration?
The construction area will be closed for the duration of the project. The CM will coordinate with SFS on traffic plans for the commerical gate.
May parking spaces adjacent to/adjoining the project site be closed during construction?
The parking spaces can be closed when work is being completed near them. The parking spaces cannot be closed for the full duration of the project.
Are the existing palm trees within the project limits scheduled for removal? There are no trees approved for removal.
Please confirm the drainage design requirements/intent for this site. The contractor is responsible to provide positive drainage.
Is the contractor responsible for fill and grading work, or is this being handled separately?
The contractor is responsible for all work that is needed to provide the government with a complete and useable system.
Please confirm the location and treatment of the sanitary sewer manhole situated within the mow strip — is relocation, adjustment, or protection required?
The contractor is responsible for protection of the existing storm drain manhole. Realignment of the fencing maybe required.
For the fence extension at the Division St. gate, is a cable (anti-ram cable) system required?
Cabling will not be installed at this location.
If a cable system is required, which rating applies at this location — K-12 or K-8? Cabling will not be installed at this location.
Is an Ameristar system specified for this fence? If so, and if cable is required, please confirm the required rating, as bollard spacing and post footer dimensions will vary depending on the rating specified.
Cabling will not be installed at this location.
If a cable system is not required, please confirm that no anti-ram rating applies for this location.
Correct, no anti-ram rating applies for the fencing or gates.
The north side of the gate shows 8’ fencing. The south side shows 10’. Is this correct? If so, what size gates should we use?
The gates will match the 8' high fencing.
Can you please clarify the required fence cable rating. The drawings reference rails capable of accommodating steel and/or sensor cables, but no cable specifications or ratings are provided in the contract documents. Please identify the required cable type, size, tensile rating, and manufacturer requirements, if applicable.
Cabling will not be installed at this location but the rails will need to be installed.
MAHG261006 Extend Perimeter Fence at Division St. Gate - Questions and Answers
Attachment 6
FA301026Q0032