This is a specification document for the extension of a perimeter fence and installation of swing gates at Keesler Air Force Base in Biloxi, Mississippi (Project MAHG261006). The scope of work includes furnishing all equipment, labor, supervision, and materials to extend approximately 376 linear feet of perimeter fence and install two 24-foot steel swing gates at the Division Street Gate location. The period of performance is 120 calendar days following the Notice to Proceed, with work to be performed Monday through Friday between 7 a.m. and 5 p.m., excluding federal holidays, unless approved otherwise by the Contracting Officer. No work shall commence until all related submittals have been received and approved, with the government providing responses within 10 calendar days for standard submittals and 14 calendar days for submittals requesting deviations.
The specification document establishes comprehensive administrative, scheduling, and quality control requirements for the contractor. Key requirements include: designating a project superintendent with minimum 10 years construction experience and at least 5 years as superintendent on similar projects; developing a Critical Path Method schedule with activities not exceeding 20 workdays; obtaining all required permits (dig permits, confined entry permits, and FAA notices for crane operations); compliance with asbestos and lead-based paint management procedures if encountered; maintaining jobsite cleanliness and 6-foot chain link fencing around lay-down areas; submitting detailed preconstruction documentation including quality control plans, environmental protection plans, and schedules of values; and conducting Red Zone meetings beginning at 75 percent project completion. The contractor must provide minimum insurance coverage per FAR 28.307-2 and maintain a Material Submittal Schedule throughout the project. All submittals requiring government approval (marked "G" classification) must be processed before corresponding work begins. Salvage material designated by the Contracting Officer remains government property and must be segregated and delivered to designated storage areas within 2 miles of the construction site.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAHG261006
CUI
CUI
PROJECT:
Extend Perimeter Fence at Division St. Gate
PROJECT NUMBER:
MAHG261006
KEESLER AIR FORCE BASE
BILOXI, MISSISSIPPI
508 L Street
Keesler AFB, MS
39534
Attachment 1
SECTION 01 11 00 Page 2
INDEX
SECTION DESCRIPTION
01 11 00 Summary of Work
01 14 00 Work Restrictions
01 30 00 Administrative Requirements
01 32 01.00 10 Project Schedule
01 33 00 Submittal Procedures
01 35 26 Governmental Safety Requirements
01 42 00 Sources for Reference Publications
01 45 00 Quality Control
01 58 00 Project Identification
01 78 00 Closeout Submittals
01 78 23 Operation and Maintenance Data
03 30 00 Cast-In-Place Concrete
31 00 00 Earthwork
32 16 19 Concrete Curbs Gutters and Sidewalks
32 31 13.53 High Security Fences and Gates
32 92 23 Sodding
SECTION 01 11 00 Page 3
SECTION 01 11 00
SUMMARY OF WORK 02/2024
CHG 1: 05/25
PART 1 GENERAL
1.1 ACRONYMS/DEFINITIONS
ACM Asbestos Containing Material
AF Air Force
AFB Air Force Base
AFI Air Force Instruction
BMP Best Management Practice
BOS Base Operating Service
C&D Construction and Demolition
CE Civil Engineering
CES Civil Engineer Squadron
CEV Civil Engineering Environmental
CFR Code of Federal Regulations
CM Contract Monitor/Construction Manager
CO Contracting Officer
CUI Controlled Unclassified Information
DOD Department of Defense
DDC Direct Digital Control
EISA Energy Independence and Security Act
EPA Environmental Protection Agency
FPCON Force Protection Condition
FOIA Freedom of Information Act
FT Foot
IAW In Accordance With
IBC International Building Code
IN Inch
SECTION 01 11 00 Page 4
LF Linear Feet
MDEQ MS Department of Environmental Quality
MDOT Mississippi Department of Transportation
MSS Material Submittal Schedule
OSHA Occupational Safety and Health Act
PM Project Manager
POC Point of Contact
PPE Personal Protection Equipment
RAMS Random Antiterrorism Measures
RCRA Resource Conservation and Recovery Act
RFI Request for Information
SDS Safety Data Sheets
SF Square Foot
SOW Statement of Work
SWPPP Storm Water Pollution Prevention Plan
SY Square Yard
UFC United Facilities Criteria
WT Work Task
1.2 SUBMITTALS
1.2.1. Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval.
Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
1.2.2. SD-01 Preconstruction Submittals
Salvage Plan; G
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1. Project Description
The contractor shall furnish all equipment, labor, supervision and materials necessary to provide an extension to the perimeter fence of approximately 376 feet and install two 24 foot steel swing gates on Keesler AFB. All work is to be performed in accordance with all contract documents and is subject to the terms and conditions of the contract.
SECTION 01 11 00 Page 5
It is not anticipated that hazardous material will be encountered during the course of work. However, should such material be encountered, the Contractor is to immediately stop work and contact the CO. All hazardous material will be handled IAW paragraphs 1.8, 1.9, and 1.10 of this Section.
1.3.2. General Scope Notes
Contractor shall provide constant daily cleaning of the jobsite after area of work is completed for that day.
Contractor shall be responsible for disposing of all material and cleaning the area of work at the completion of the project.
1.3.3. Period of Performance
Performance will begin after receiving the Notice to Proceed and end one hundred and twenty (120) calendar days later.
No Work shall begin until all submittals related to that work have been received and approved. The government will provide a response to submittals within 10 calendar days of receipt of submittal required by the MSS and 14 calendar days for any submittal that requests or requires deviation from the contract drawings or specifications.
Punch list items noted during inspections shall be corrected and accepted prior to the end of the Period of Performance or the contract will be considered past due.
1.3.4. Location
The work is located at 1 Tingle Street near the Division Street Gate on Keesler AFB, Biloxi MS, approximately as indicated.
1.4 EXISTING WORK
1.4.1. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
1.4.2. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 LOCATION OF UNDERGROUND UTILITIES PERMITS:
1.5.1. Contractors will be required to obtain permits as required by Keesler in the performance of their work. Contractors shall post or have readily available all permits before work is commenced.
1.5.2. The following permits must be obtained anytime referenced work
SECTION 01 11 00 Page 6 is required:
DIG PERMIT – BOS/CE Customer Service
BURN PERMIT – Keesler AFB Fire Department (certified personnel only)
CONFINED ENTRY PERMIT – BOS/CE CM; Notification to Fire Department of actual day and time work is accomplished.
CRANE PERMIT - Coordinate crane usage with the Subcontract Technical Monitor (STM). Submit notice with the Federal Aviation Administration (FAA) at least 45 days before the start of the proposed construction or the date an application for a construction permit is filed, whichever is earliest.
1.5.3. INTERRUPTION OF SERVICES:
If interruption of any building utility services such as but not limited to the following: chilled water, electrical power, domestic water, fire protection water supply, or communications etc. are required, the Contractor shall perform the work on normal work week hours after receiving approval, during the weekend or on non-training Fridays. The Contractor shall coordinate the interruption of the utilities 14 days in advance with the CM and user regardless of the option chosen.
The Contractor shall include any additional cost of performing the work in their original bid.
The Contractor shall submit Utility Service Outage Request to the Contracting Officer. The Contracting Officer may require the Contractor to attend a coordination meeting to assess the purpose, intent, and impact of the outage request with the facility and any or all operations departments. Contractors shall not shutdown or start-up any mechanical, electrical and/or plumbing system without the coordination and/or permission of the CO.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with dual frequency Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.6 SALVAGE MATERIAL AND EQUIPMENT
1.6.1. Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government
SECTION 01 11 00 Page 7 designated storage area located within 2 miles of the construction site.
1.6.2. Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
1.7 REQUIRED ASBESTOS ABATEMENT AND MANAGEMENT PROCEDURES:
1.7.1. These steps are in accordance with Air Force Instruction (AFI), EPA, and MDEQ. OSHA regulations govern all worker safety requirements and must be complied with at all times by the Contractors and sub-Contractors. These requirements are summarized in the Keesler Air Force Base Asbestos Operations and Management Plan.
1.7.2. The following steps are required by all personnel or
Contractors doing work on Keesler AFB:
If the personnel or Contractor encounters what they think may be asbestos, they are required to stop and call the KAFB Asbestos Point of Contact (APOC) for the Keesler Environmental Section (BOS/CEV) at 228-377-1262 or EMCS (228- 377-4179) after hours.
Once it is determined by the APOC that asbestos is present, the following actions described below are required (Only the APOC and Bioenvironmental are certified to make that determination).
1.8 NO ABATEMENT WORK IS TO BEGIN WITHOUT WRITTEN APPROVAL FROM
THE APOC:
1.8.1. A Mississippi State certified asbestos abatement Contractor must be used to conduct the abatement. Please note that non-friable asbestos can easily be made friable and become regulated.
1.8.2. Before: The following documents must be submitted to the CO and approved in writing before abatement can begin:
10 Day MDEQ notification and return acknowledgment letter.
Asbestos Hazard Abatement Plan (to be certified by a Mississippi Certified Management Planner and/or Certified Industrial Hygienist).
Asbestos Work Plan (scope of work, removal procedures, worker protection, air monitoring, disposal location, containment procedures).
MDEQ Asbestos Abatement Certification for the Company.
Supervisor’s qualifications and state certification.
SECTION 01 11 00 Page 8
CURRENT State Certifications (applications will not be accepted) for all individuals working on site.
Respirator fit tests for all individuals.
Physicals for all individuals.
1.8.3. During: Once the submittals are approved in writing, the following actions are required:
The Contractor is required to set up their containment areas, negative air machine, and critical barriers and obtain approval from the Asbestos POC to begin work.
The Asbestos POC routinely checks the abatement work to ensure the containment area and critical barriers are secure, the workers are wearing the appropriate personal protective equipment, the asbestos-containing material is being bagged appropriately, and air monitoring is being conducted on the workers and outside the abatement area. This also includes reviewing the daily log maintained on site to assure no uncertified individuals are performing abatement work.
Upon completion of the abatement work, the Contractor contacts the Asbestos POC to conduct a walk-through of the area and approve all abatement has been completed and the area has been cleaned of asbestos fibers. This action will require at least a 24-hour period. Please reference cleaning procedures in the Asbestos Management and Operations Plan.
Air sampling results are required to be collected and submitted for approval by the Asbestos POC before the containment area, negative air machine, and critical barriers can be removed.
All asbestos waste must be handled and disposed of in accordance with State law. The Asbestos POC must review the waste prior to leaving the base and the manifest will be signed by a designated Keesler government representative.
Contractors will not sign manifests for asbestos containing material (ACM).
1.8.4. After: After the abatement has been complete and approved by the Asbestos POC, the Contractor shall submit the following items in a post-job submittal to be maintained in the Asbestos Abatement Files:
Air sampling results.
Daily report logs.
Daily workers sign in/out sheets.
Waste manifest (Generator Copy)
1.8.5. The Asbestos POC and Environmental Section (BOS/CEV) are available at any time to provide asbestos awareness training
SECTION 01 11 00 Page 9 and consultation to CM’s, PM’s, Contractors and Sub- Contractors prior to beginning the project.
1.9 REQUIRED LEAD-BASED PAINT MANAGEMENT PROCEDURES:
1.9.1. Appropriate OSHA worker protection is the responsibility of the employer. All projects will be monitored and inspected by BOS/CEV. The purpose of these instructions is to provide guidance to safely remove or encapsulate lead-based paint without causing a hazard. All work must be performed in accordance with OSHA, MDEQ and any local regulations for all work and disposal. The regulations are divided into two parts; a) lead-based paint on non-child occupied/non-target housing buildings and b) child occupied/target housing buildings.
1.9.2. Non-child occupied/ commercial buildings:
For non-child-occupied/commercial buildings, the minimum requirement for Contractors is to protect workers IAW OSHA requirements, use poly lay-down to collect paint chips, and turn into BOS/CEV for disposal. At minimum the supervisor of the project should be LBP trained and supply proof of certification before work begins. The Contractor shall notify BOS/CEV before start of any project. Contractor must place plastic on the ground sufficient to capture all loosened paint chips and control water run-off. Removal methods preferred at Keesler AFB are the use of an approved chemical stripper or wet sanding methods for better collection of LBP chips and waste. These processes minimize lead dust and allow for maximum collection of LBP chips.
The Contractor shall meet with BOS/CEV prior to beginning the project to discuss protective measures, best management practices (BMP’s), any landfill disposal, and maintenance of chips and their collection (until they are turned over to
BOS/CEV).
Any buildings with lead-based paint, if bead blasted to remove old paint, shall be supervised by a Contractor with proper training. Bead blasting upon prior approval only (see preferred method above).
The Contractor, under OSHA rules, must comply with the lead-based paint rules (including notification to BOS/CEV, if the job is abatement), certify appropriate training, and maintain personal monitors on workers until it is demonstrated there is no airborne lead risk.
BOS/CEV will inspect all projects involving Lead Based Paint removal and any required documentation must be provided to BOS/CEV prior to beginning work.
1.9.3. Child-occupied/target housing buildings:
Any child-occupied/target housing building older than 1978 must be painted using Lead Paint Protocol, including poly-lay-
SECTION 01 11 00 Page 10 down, collection of paint chips, and the Contractor must always have a minimum of lead hazard training for all workers.
The Contractor shall notify BOS/CEV before start of any project.
A paint Contractor must collect paint chips in their own clean buckets and have BOS/CEV dispose (if contract requires BOS/CEV dispose). Contractor must place plastic on the ground sufficient to capture all loosened paint chips and control water run-off.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
-- End of Section --
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
SD-07 Certificates
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, including delivery vehicles, are clearly identified with their company name.
a. Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
b. No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
SECTION 01 14 00 Page 2
c. Working Hours
Regular working hours will consist of an 9 hour period established by the Contracting Officer, between 7 a.m. and 5 p.m., Monday through Friday excluding Government holidays.
d. Work Outside Regular Hours The Contractor will not normally be permitted to work on weekends or on the following federal holidays (or the day the Federal Government observes these holidays) unless approved by the CO.
(Sundays will generally not be approved for weekend work.) To be approved by the CO, the Contractor shall provide documentation showing work performed outside the hours of work will benefit the project’s mission. If approved by the CO, the Contractor shall coordinate such work with the CM at least seven (7) calendar days in advance:
New Year’s Day
Martin Luther King Jr.’s Birthday
Washington’s Birthday
Memorial Day
Juneteenth
Independence Day
Labor Day
Columbus Day
Veteran’s Day
Thanksgiving Day
Christmas Day
The following days are not federal holidays but may require work stoppage: Special Olympics- Thursday through Sunday of First NON-Training weekend in May
1.3.3 Utility Cutovers and Interruptions
d. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays.
Conform to procedures required in paragraph WORK OUTSIDE
REGULAR HOURS.
e. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
f. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and data are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
Such interruptions are further limited to 48 hours. This time limit includes time for deactivation and reactivation.
g. Operation of Station Utilities: Do not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. Notify the Contracting Officer within 7 calendar days giving reasonable advance notice when such operation is required.
SECTION 01 14 00 Page 3
1.4 SECURITY REQUIREMENTS
1.4.1 Passes:
a. Passes for Contractor employees may be requested through the 81st Civil
Engineer Squadron. Requests shall include full name of employees as it appears on their identification, length of pass needed (up to 30 days), and days needed (if other than standard working hours). The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract.
Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
b. The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate, to obtain a vehicle pass.
c. During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
d. When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with [insert any additional requirements to comply with DAFI 31-101, Integrated Defense, and DODMAN5200.02_DAFMAN 16-1405 , Air Force Personnel Security Program] citing the appropriate paragraphs as applicable.
e. Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
f. The contractor shall provide an after-hours contact number or after-hours email in the Emergency Mass Notification System (EMNS) for each of their personnel, whose normal place of duty is on a DoD installation or within a DoD facility. The contractor shall comply with any additional requirements in DAFMAN 10-206 for emergency operational reporting. Foreign Nationals may participate and may remove themselves from the Emergency Mass Notification System at any time. To update information, personnel can access the globe icon on their system desktop screens and choose the “Access Self-Service” option. Failure to comply with these requirements may result in withholding of final payment.
g. Upon contract award, Superintendents will complete a Keesler AFB (KAFB) Form 299, Application for KAFB Identification Card. After issuance of a DBIDS identification card, the Superintendent will submit a KAFB Form 298, Appointment/Termination Record - Signature Card which will grant the Superintendent the role of a Pass and ID Alternate Issuing Official. This role will enable the designated superintendent to function as a sponsor and request passes for all contractor and sub-contractor personnel
SECTION 01 14 00 Page 4 performing work on the installation cited in the contract. Contractor personnel who are non-US citizens must be approved and vetted through the Air Force Office of Special Investigations (AFOSI) before a pass is issued.
h. Paperwork required for passes: Only documents meeting the security standards set by the REAL ID Act of 2005 will be accepted.
For vehicle operators: Current driver license for each employee in support of work on Keesler AFB. Vehicle Registration and Proof of Insurance.
For non-vehicle operators: Current driver license, official ID card, or passport.
1.4.2 Reporting Requirements:
The Contractor shall comply with AFI 71-l0l, Volume¬1, Criminal Investigations and Volume-2, Protective Service Matters, requirements.
Contractor personnel shall report to an appropriate authority, any information or circumstances of which they are aware may pose a threat to the security of DOD personnel, Contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment and as required thereafter.
1.4.3 Physical Security:
a. Areas controlled by Contractor employees shall comply with Base Operations Plans/instructions for FPCON procedures, Random Antiterrorism Measures (RAMS) and local search/identification requirements. The Contractor shall safeguard all government property, including controlled forms, provided for Contractor use. At the close of each work period, government training equipment, ground aerospace vehicles, facilities, support equipment, and other valuable materials shall be secured.
b. The Contractor shall not employ persons for work on this contract if such employee is identified by the government or BOS Contract officials as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population.
1.4.4 Vehicle Safety And Traffic Laws:
a. The Contractor and its employees shall comply with base traffic laws and regulations.
b. The Contractor shall ensure employees have a current and valid driver’s license and commercial permits/licenses for the type of vehicle operated, before allowing the employee to operate a Contractor-owned or rental vehicle on Keesler AFB.
c. The Contractor shall provide all vehicles to perform the requirements of the contract. All vehicles shall be in operable condition and meet local, state and federal safety requirements, and be specifically designed for the purpose intended for use. Vehicles shall have, clearly visible on each side, the Contractor company name, a unique vehicle identification number, in addition to all required Department of Transportation (DOT) markings and information.
d. Airfield Driving: All Contractors must have an escort or receive airfield drivers training prior to driving on the airfield IAW (AFI 13-213, SECTION 01 14 00 Page 5
2.1.3.39.7). This training will be provided by Airfield Management at
B0233 PH:228-377-2215.
e. Cellular Phones: The use of cellular phones while operating a vehicle is prohibited while on Keesler AFB property.
SECTION 01 14 00 Page 6
1.4.5 Controlled Unclassified Information (CUI):
The Contractor shall comply with Executive Order 13556, “Controlled Unclassified Information”, regarding Controlled Unclassified Information (CUI), and requirements. The DoD Instruction (DoDI) 5200.48, “Controlled Unclassified Information”, sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding CUI material.
PART 3 EXECUTION
-- End of Section
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 5: 02/25
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
15 CFR 772 Definition of Terms
15 CFR 773 Special Licensing Procedures
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map; G
Progress and Completion Pictures; G
SD-02 Schedule of Values (SOV); G
1.3 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.4 SUPERVISION
1.4.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project.
SECTION 01 30 00 Page 2
The superintendent is not permitted to also serve as the Quality Control (QC) Manager, as established in Section 01 45 00 QUALITY CONTROL, However, the Site Safety and Health Officer (SSHO) may serve dual roles as the SSHO and QC Manager. The QC Manager must have qualifications in accordance with Section 01 45 00.
1.4.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.4.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.4.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time or excess costs or damages by the Contractor.
1.5 PRECONSTRUCTION
Immediately after award, Contractor may coordinate with the Contracting Officer a time and place to meet for the Preconstruction meeting. The purpose of this is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to:
daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out.
Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
Contractor must provide preliminary Schedule of Values (SOV) for Contracting Officer review and approval (See Section 01 33 00 for additional information).
1.5.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
SECTION 01 30 00 Page 3
1.6 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process prior to start of construction and convene at regularly scheduled Red Zone Meetings beginning at approximately 75 percent of project completion. Include the following in the facility Turnover effort:
1.6.1 Red Zone Checklist
1.6.1.1. Contracting Officer's Technical Representative (COTR) or CM will provide the Contractor a copy of the Red Zone Checklist template.
1.6.1.2. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.
1.6.2 Meetings
1.6.2.1. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
1.6.2.2. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer. At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.
1.6.2.3. Using the Red Zone Checklist as a Plan of Action and Milestones
(POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
1.6.2.4. During the Red Zone Meetings discuss with the COTR or CM any upcoming activities that require Government involvement.
1.6.2.5. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.
1.7 MOBILIZATION
Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.
1.8 JOBSITE MAINTENANCE AND STORAGE AREAS:
The Contractor shall maintain the jobsite and staging areas in conformance with the standards below and as directed by the CO.
1.8.1 Lay down/staging areas shall be kept neat and free of loose debris at all times. Grass shall be cut and maintained regularly. Height and maintenance shall be consistent with Base standards and consistent with the immediate area.
1.8.2 Parking on the grass is not permitted.
SECTION 01 30 00 Page 4
1.8.3 Jobsites and lay down/staging areas shall be enclosed with a 6’ chain link fence with brown fabric screening unless otherwise noted.
Materials and equipment may be stored inside storage units. Items stored in the lay down area shall be arranged neatly.
1.8.4 All temporary storage trailers and storage containers shall present a neat and clean appearance and shall be in a state of good repair and shall be located within the fenced area described in paragraph above.
1.8.5 If allowed by the contract and if approved by the CO, an office mobile unit may be located outside of a fenced area. At a minimum, this unit shall be in a paved area and shall present a neat, professional appearance. Unit shall be of Keesler standard colors, shall have presentable skirting and access stairs. Ancillary items, such as porches and canopies, shall be neat and painted Keesler brown.
Contractor shall submit a picture of the proposed unit for approval and before unit is moved to Base.
1.8.6 Execution of work may require excavation or other type of work both at and away from primary work area. These areas shall be secured, and work times shall be kept to a minimum. Open excavations shall be directly in progress or shall be covered directly after work complete.
Open excavations requiring extended period of inactivity shall be temporarily backfilled. In no case shall an excavation be open for more than 72 hours. Barricades, fences and other warning devices shall be maintained neatly at all times.
1.8.7 The Contractor shall maintain the premises, including any staging area or storage areas, free from accumulations of waste, debris, and rubbish caused by the Contractor’s work and shall minimize the spread of dust and flying particles. As work is completed, or at the end of each day, the site shall be cleaned, and all waste material shall be properly disposed of properly.
1.8.8 Should warnings of winds of gale force or stronger be issued, the Contractor shall take every practical precaution to minimize danger to persons and damage to property. These precautions shall be coordinated through the CO and shall include closing all openings; removing all loose materials, tools, and equipment from exposed locations; securing all material, tools, equipment and construction work; as well as removing or securing scaffolding and other temporary work. The Contractor shall also coordinate all efforts with the CO and follow the Base Commander’s direction in the event of an upcoming storm or hurricane which may range from securing sites to complete demobilization of all equipment and material from the base.
SECTION 01 32 01.00 10 Page 1
SECTION 01 32 01.00 10
PROJECT SCHEDULE
08/23, CHG 1: 08/24
The publications listed below form a part of this specification to the
ASSOCIATION FOR THE ADVANCEMENT OF COST ENGINEERING,
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
AACE 84R-13 (2015) Planning and Accounting for Adverse
Weather
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 67-17 (2017) Schedule Delay Analysis
ER 1-1-11 (2017) Administration -- Project Schedules classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G
Preliminary Project Schedule; G
Initial Project Schedule; G
Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules for projects of similar size and complexity to this contract, using Primavera P6, Microsoft Project, or equivalent project management software.
Representative must have a comprehensive knowledge of CPM scheduling principles and application.
SECTION 01 32 01.00 10 Page 2
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available.
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM) in a Gantt Chart format.
3.1.1 Scheduling Expectations Kickoff Meeting (SEKO)
In conjunction with the post award conference or preconstruction conference the Government and the Contractor may hold a separate and distinct Scheduling Expectations Kickoff Meeting (SEKO). The intent of this meeting is for the Government to review with the contractor the requirements of the scheduling specification, communicate the Government’s expectations regarding schedule development and management, and answer any questions the Contractor may have regarding the schedule requirements.
This meeting can be held the same day as the post award conference or preconstruction conference.
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will have final project schedule approval.
3.2.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Non-procurement activities Original Durations (OD) are not to exceed 20 workdays or 30 calendar days.
SECTION 01 32 01.00 10 Page 3
3.2.3 Procurement Activities
Include in the schedule activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.2.4 Mandatory Activities
Include the following activities in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals
(individual activity for each).
b. Submission and approval of O & M manuals.
c. Submission and approval of as-built drawings.
d. Contractor's pre-final inspection.
e. Correction of punch list from Contractor's pre-final inspection.
f. Government's pre-final inspection.
g. Correction of punch list from Government's pre-final inspection.
h. Final inspection.
3.2.5 Government Activities
Show in schedule, Government and other agency activities that could impact progress. These activities include, but are not limited to approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.2.6 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.2.6.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to
SECTION 01 32 01.00 10 Page 4 the date that the NTP is acknowledged.
3.2.6.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.
3.2.6.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.2.6.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.2.6.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.2.7 Adverse Weather
Ensure anticipated adverse weather is accounted for in the Project Schedule. AACE 84R-13 provides methodologies for techniques in planning for adverse weather. The preferred methodology is the use of a weather calendar. If a method other than a weather calendar is proposed, discuss the reason during the SEKO meeting.
3.2.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs.
Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.
If a weather calendar is used its implementation and execution is to be in accordance with AACE 84R-13
3.2.9 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the
SECTION 01 32 01.00 10 Page 5
Contractor's schedule.
3.2.10 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.2.11 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.2.12 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.2.13 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb or create float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
3.2.14 Percent Complete
Update the percent complete for each activity started. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management, however, any progress reports shall reflect the actual percentage completed. Budgeted cost of activity is to be reduced by the amount needed to correct deficiency.
3.2.15 Remaining Duration
Update the remaining duration for each activity based on the number of estimated workdays it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete. The remaining duration for unstarted activities are not to be less than its original duration.
3.2.16 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and hours) and the
SECTION 01 32 01.00 10 Page 6
Government agreeing that the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
3.3 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data reports and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.3.1 Preliminary Project Schedule Submission
Within 15 calendar days after the NTP is acknowledged, submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities.
3.3.2 Initial Project Schedule Submission
Submit the Initial Project Schedule for approval within ten (10) calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period.
No payment will be made for work items not fully detailed in the Project Schedule.
3.3.3 Periodic Schedule Updates
Update the Project…