This document contains Questions and Answers related to the Repair Well #10 federal contract opportunity, Solicitation Number FA301024R0013. The key details are:
Both Phase 1 and Phase 2 of the project will be awarded under one contract with one Period of Performance, if the project is funded. The solicitation is a total small business set-aside, with a magnitude between $250,000 and $500,000. The generator scope includes removing and installing a new Automatic Transfer Switch (ATS) in the same outside location. The existing 500-gallon fuel tank may be reused if it can adequately supply the new generator for 72 hours, otherwise it must be replaced. The exterior equipment must be NEMA 3R rated. A site visit is scheduled for August 12, 2024, and the solicitation will not be awarded until funds are available. The document also references related electrical drawings and contract clauses.
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAHG231035 Repair Well #10 Pre-Bid Questions and Answers
15 August 2024
1. Are both Phase 1 and Phase 2 being awarded?
Both Phase 1 and Phase 2 will be awarded under one contract and one Period of Performance (PoP) if the project is funded.
2. Generator Scope Detail 1.1 A calls to remove and install the ATS inside Bldg 7310 and
1.2.1 B Calls to provide and install new ATS outside of the building is this correct?
The ATS is located outside the building 7301.
Remove existing ATS and install new ATS in same location outside.
Please see the Addendum #1.
3. The Generator Scope Detail 4.1.1 calls out a 1350 Gallon Main Tank are there any other requirements for the tank other than the size
Contractor to verify existing 500-gallon tank is sufficient to supply new generator with diesel to run for approximately 72 hours. If re-using tank, provide any hardware, plumbing, or pumps for fully functional tank and fuel delivery system. If tank is too small, replace in kind with tank with adequate capacity.
Please see the Addendum #1.
4. Will the exterior equipment be 4x or NEMA 3R rated?
NEMA 3R.
5. Will you incorporate one line field drawing attached on your E2.0 to meet NEC and KAFB requirements?
See Attachment 3 - Electrical Drawings Rev. 1, 19 Aug 2024.
6. With the given tank size in the RFP is there a requirement to calculate 72 hr. run time?
Yes, to calculating 72 hour run time. See answer to question #3.
7. Will the generator require a pad for the new enclosure?
No.
Attachment 14
FA301024R0013
MAHG23-1035 Repair Well #10