This document appears to be an attachment that details the scope of work for providing a generator, automatic transfer switch (ATS), and diesel fuel tank for Building 7301 under Solicitation FA301024R0013 for the Repair Well #10 project.

The key requirements include: installing the ATS inside Building 7301, wiring the generator to the ATS and existing electrical source, plumbing the diesel tank to the generator, and testing the generator. The generator is specified as a 150 kW standby diesel unit with redundant fuel pumps, sensors, filters, and other components. The ATS is required to be 480 VAC wye mounted outside in a NEMA 4X enclosure. A 1,350-gallon diesel fuel tank is also to be provided and plumbed to the day tank. The work is to be accomplished per the drawings and specifications in the Statement of Work for this solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Well #10, newest first.
File Type Posted
Solicitation Amendment FA301024R00130004 SF 30.pdf PDF
Solicitation Amendment FA301024R00130003 SF 30.pdf PDF
Attachment 17 - Additional Questions and Answers (2).pdf PDF
Solicitation Amendment - FA301024R00130003.pdf PDF
Solicitation Amendment - FA301024R00130002.pdf PDF
Solicitation Amendment FA301024R00130002 SF 30.pdf PDF
Attachment 16 - Electrical Drawings E2.0 - Rev2.pdf PDF
Attachment 15 - Additional Question and Answer 26Aug.pdf PDF
Solicitation Amendment - FA301024R00130001.pdf PDF
Solicitation Amendment FA301024R00130001 SF 30.pdf PDF
Attachment 13- Addendum 1.pdf PDF
Attachment 4 - Generator Scope Details Rev.1, 19Aug2024.pdf PDF
Attachment 3 - Electrical Drawings Rev1- 19Aug2024.pdf PDF
Attachment 14- Questions and Answers.pdf PDF
Sign In Sheet 12 August 2024.pdf PDF
Attachment 11- Past Performance Questionnaire.pdf PDF
Attachment 3 - Electrical Drawings.pdf PDF
Attachment 8 - Wage Determination.pdf PDF
Attachment 5- As Built Well.pdf PDF
Attachment 6 - AFI 32-1065.pdf PDF
Attachment 10 - Past Performance Reference List.pdf PDF
Attachment 7 - MSS.xlsx XLSX spreadsheet
Attachment 1- SOW.pdf PDF
Attachment 12 - Brand Name Justification.pdf PDF
Attachment 9 - Submittal Procedure.pdf PDF
Attachment 2 - Specifications.pdf PDF
Solicitation - FA301024R0013.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 2

Generator Scope Details

MAHG 231035 Repair Well #10

1. SCOPE: Provide Generator, ATS, & Diesel Fuel Tank for Bldg 7301.

Notes:

A. Contractor shall provide and maintain filters, temporary dust barriers, etc. to prevent construction dust and debris from spreading throughout Bldg 7301, adjacent areas, Fire System Devices, and IT equipment, and other spaces.

B. Contractor shall provide constant daily cleaning of the work area.

C. Contractor is responsible for the repair/replacement of items damaged during construction at their own cost.

1.1 CONTRACTOR TO REMOVE & INSTALL:

Bldg 7301surrounding area

A. Install ATS inside Bldg 7301

B. Wire Generator to ATS and from existing electrical source, at Bldg 7301.

C. Wire ATS to existing electrical system.

D. Plumb Diesel Tank to generator.

E. Test run generator following manufacturer’s instructions, with manufacturer’s representative as a witness.

Mechanical / Electrical Demolition work shall be accomplished per drawings and specifications given in the SOW.

1.2 CONTRACTOR TO MODIFY EXISTING:

Mechanical / Electrical work to modify existing building components.

shall be accomplished per drawings and specifications given in the

SOW.

1.2.1 CONTRACTOR TO PROVIDE AND INSTALL NEW:

Building 7301 –

A. Generator

B. ATS, outside bldg. 7301.

C. Diesel tank immediately north of the generator

Mechanical / Electrical Installation work shall be accomplished per drawings and specifications given in the SOW.

FA301024R0013

Attachment 4

Attachment 2

Generator Scope Details

MAHG 231035 Repair Well #10

4.1 SPECIAL GENERATOR CONSIDERATIONS

4.1.1 150 KW STANDY; 480 VAC WYE OUTPUT, 60 HERTZ, DIESEL FUEL WITH

DAY TANK AND 1350 GALLON MAIN TANK PLUMBED TO DAY TANK.

4.1.2 TWO OF EACH OF THE FOLLOWING SUB EQUIPMENT: FUEL PUMPS

WITH DIFFERENT INJECTION LOCATIONS; EACH PUMP WITH ITS OWN

FUEL LINE; OIL SENSORS AT SEPARATE LOCATIONS; SPARK PLUGS AT

SEPARATE LOCATIONS; FUEL GAUGES AT SEPARATE LOCATIONS;

FUEL PRESSURE INDICATION AT SEPARATE BUT NEAR EQUAL

LOCATIONS; FUEL FILTERS AT SEPARATE LOCATIONS IN PARALLEL

FUEL LINES; FUEL VALVES FOR ALL FUEL LINES IN PARALLEL; OIL

LEVEL SENSORS AT SEPARATE LOCATIONS; ENGINE BLOCK HEATERS

AT SEPARATE LOCATIONS; BLOWBY STACKS AT SEPARATE

LOCATIONS; VOLTAGE REGULATORS AT SEPARATE LOCATIONS

AUTOMATICALLY SWITCHED BETWEEN EACH OTHER AS NEEDED;

AIR FILTERS AT SEPARATE LOCATIONS; ANTI CONDENSATION

HEATERS AT SEPARATE LOCATIONS; VIBRATION MEASUREMENT

NEAR BEARINGS AT SEPARATE LOCATIONS; DIODES CONDITION

REPORTING; GENERATOR WINDINGS REPORTING FROM TWO

SEPARATE LOCATONS INCLUDING CURRENT, RESISTANCE, AND

VOLTAGE. SENSORS FOR ALL OF THE ABOVE TO REPORT TO TWO

SEPARATE CONTROLLERS.

4.1.3 AUTOMATIC TRANSFER SWITCH (ATS) 480 VAC WYE MOUNTED

OUTSIDE; NEMA 4X; WIRED FOR POWER TRANSFER

4.1.4 1350 GALLON DIESEL TANK NEXT TO DAY TANK WITH PLUMBING TO

DAY TANK.