Attachment 3 Schedule B

Text of this file

Sheppard

BASICSHEPPARD AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
0001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD AFB for the period 01 AUGUST 2010 to 30 JUNE 2011 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
0002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)11MO$0
0003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.11MO$0
0004RESERVED
0005RESERVED
0006RESERVED
0007RESERVED
0008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.11MO$0
0009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.11MO$0
0010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
0011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
0012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)11MO$0
0013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)11MO$0
0014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.11MO$0
0015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)11MO$0
0016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.11MO$0
0017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
0018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
0019Mobilization (FFP) (5 July - 31 July 2010)1LS$0
0020ISWM Kick-Off Conference (FFP)1EA$1,500

TOTAL RECYCLING PROGRAM COSTS: BASIC (CLINS 0003, 0008, 0009, 0010*, 0011*, 0014 & 0016) $10,000

TOTAL PRICE: BASIC $19,000

TOTAL EVALUATED PRICE: BASIC $0

OPTION 1SHEPPARD AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
1001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD AFB for the period 01 JULY 2011 to 30 JUNE 2012 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
1002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
1003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
1004RESERVED
1005RESERVED
1006RESERVED
1007RESERVED
1008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
1009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
1010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
1011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
1012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
1013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
1014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
1015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
1016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
1017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
1018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
1019RESERVED
1020RESERVED

TOTAL RECYCLING PROGRAM COSTS: BASIC (CLINS 1003, 1008, 1009, 1010*, 1011*, 1014 & 1016) $10,000

TOTAL PRICE: OPTION 1 $17,500

TOTAL EVALUATED PRICE: OPTION 1 $0

OPTION 2SHEPPARD AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
2001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD AFB for the period 01 JULY 2012 to 30 JUNE 2013 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
2002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
2003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
2004RESERVED
2005RESERVED
2006RESERVED
2007RESERVED
2008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
2009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
2010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
2011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
2012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
2013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
2014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
2015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
2016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
2017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
2018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
2019RESERVED
2020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 2 (CLINS 2003, 2008, 2009, 2010*, 2011*, 2014 & 2016) $10,000

TOTAL PRICE: OPTION 2 $17,500

TOTAL EVALUATED PRICE: OPTION 2 $0

OPTION 3SHEPPARD AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
3001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD AFB for the period 01 JULY 2013 to 30 JUNE 2014 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
3002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
3003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
3004RESERVED
3005RESERVED
3006RESERVED
3007RESERVED
3008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
3009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
3010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
3011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
3012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
3013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
3014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
3015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
3016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
3017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
3018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
3019RESERVED
3020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 3 (CLINS 3003, 3008, 3009, 3010*, 3011*, 3014 & 3016) $10,000

TOTAL PRICE: OPTION 3 $17,500

TOTAL EVALUATED PRICE: OPTION 3 $0

OPTION 4SHEPPARD AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
4001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD AFB for the period 01 JULY 2014 to 30 JUNE 2015 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
4002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
4003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
4004RESERVED
4005RESERVED
4006RESERVED
4007RESERVED
4008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
4009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
4010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
4011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

*Portion or all may be identified as recycling costs.1EANTE$2,500
4012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
4013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
4014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
4015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
4016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
4017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
4018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
4019RESERVED
4020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 4 (CLINS 4003, 4008, 4009, 4010*, 4011*, 4014 & 4016) $10,000

TOTAL PRICE: OPTION 4 $17,500

TOTAL EVALUATED PRICE: OPTION 4 $0

TOTAL PRICE: BASIC PLUS ALL OPTIONS - SHEPPARD $89,000

TOTAL EVALUATED PRICE: BASIC PLUS ALL OPTIONS - SHEPPARD (IF AWARDED BASIC CONTRACT, WILL BE UTILIZED TO DETERMINE SHEPPARD TASK ORDER AWARD) $0

&"Times New Roman,Regular"ISWM SERVICES

FA3002-09-R-0035

ATTACHMENT 3 - SCHEDULE B

(SHEPPARD AFB)

&"Times New Roman,Regular"FOR OFFICIAL USE ONLY &P &"Times New Roman,Regular"1 MAR 2010

Goodfellow

BASICGOODFELLOW AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
0001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at GOODFELLOW AFB for the period 01 AUGUST 2010 to 30 JUNE 2011 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
0002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)11MO$0
0003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.11MO$0
0004RESERVED
0005RESERVED
0006RESERVED
0007RESERVED
0008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.11MO$0
0009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.11MO$0
0010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
0011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

*Portion or all may be identified as recycling costs.1EANTE$2,500
0012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)11MO$0
0013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)11MO$0
0014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.11MO$0
0015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)11MO$0
0016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.11MO$0
0017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
0018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
0019Mobilization (FFP) (5 July - 31 July 2010)1LS$0
0020ISWM Kick-Off Conference (FFP)1EA$1,500

TOTAL RECYCLING PROGRAM COSTS: BASIC (CLINS 0003, 0008, 0009, 0010*, 0011*, 0014 & 0016) $10,000

TOTAL PRICE: BASIC $19,000

TOTAL EVALUATED PRICE: BASIC $0

OPTION 1GOODFELLOW AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
1001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at GOODFELLOW AFB for the period 01 JULY 2011 to 30 JUNE 2012 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
1002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
1003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
1004RESERVED
1005RESERVED
1006RESERVED
1007RESERVED
1008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
1009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
1010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
1011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

*Portion or all may be identified as recycling costs.1EANTE$2,500
1012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
1013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
1014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
1015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
1016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
1017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
1018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
1019RESERVED
1020RESERVED

TOTAL RECYCLING PROGRAM COSTS: BASIC (CLINS 1003, 1008, 1009, 1010*, 1011*, 1014 & 1016) $10,000

TOTAL PRICE: OPTION 1 $17,500

TOTAL EVALUATED PRICE: OPTION 1 $0

OPTION 2GOODFELLOW AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
2001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at GOODFELLOW AFB for the period 01 JULY 2012 to 30 JUNE 2013 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
2002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
2003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
2004RESERVED
2005RESERVED
2006RESERVED
2007RESERVED
2008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
2009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
2010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
2011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

*Portion or all may be identified as recycling costs.1EANTE$2,500
2012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
2013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
2014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
2015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
2016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
2017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
2018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
2019RESERVED
2020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 2 (CLINS 2003, 2008, 2009, 2010*, 2011*, 2014 & 2016) $10,000

TOTAL PRICE: OPTION 2 $17,500

TOTAL EVALUATED PRICE: OPTION 2 $0

OPTION 3GOODFELLOW AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
3001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at GOODFELLOW AFB for the period 01 JULY 2013 to 30 JUNE 2014 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
3002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
3003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
3004RESERVED
3005RESERVED
3006RESERVED
3007RESERVED
3008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
3009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
3010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
3011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
3012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
3013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
3014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
3015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
3016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
3017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
3018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
3019RESERVED
3020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 3 (CLINS 3003, 3008, 3009, 3010*, 3011*, 3014 & 3016) $10,000

TOTAL PRICE: OPTION 3 $17,500

TOTAL EVALUATED PRICE: OPTION 3 $0

OPTION 4GOODFELLOW AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
4001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at GOODFELLOW AFB for the period 01 JULY 2014 to 30 JUNE 2015 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
4002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
4003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
4004RESERVED
4005RESERVED
4006RESERVED
4007RESERVED
4008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
4009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
4010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
4011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

*Portion or all may be identified as recycling costs.1EANTE$2,500
4012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
4013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
4014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
4015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
4016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
4017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
4018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
4019RESERVED
4020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 4 (CLINS 4003, 4008, 4009, 4010*, 4011*, 4014 & 4016) $10,000

TOTAL PRICE: OPTION 4 $17,500

TOTAL EVALUATED PRICE: OPTION 4 $0

TOTAL PRICE: BASIC PLUS ALL OPTIONS - GOODFELLOW $89,000

TOTAL EVALUATED PRICE: BASIC PLUS ALL OPTIONS - GOODFELLOW (IF AWARDED BASIC CONTRACT, WILL BE UTILIZED TO DETERMINE GOODFELLOW TASK ORDER AWARD) $0

ATTACHMENT 3 - SCHEDULE B

(GOODFELLOW AFB)

&P &"Times New Roman,Regular"1 MAR 2010

Keesler

BASICKEESLER AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
0001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at KEESLER AFB for the period 01 AUGUST 2010 to 30 JUNE 2011 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
0002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)11MO$0
0003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.11MO$0
0004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)8MO$0
0005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.8MO$0
0006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.8MO$0
0007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.8EA$0
0008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.11MO$0
0009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.11MO$0
0010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
0011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
0012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)11MO$0
0013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)11MO$0
0014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.11MO$0
0015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)11MO$0
0016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.11MO$0
0017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
0018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
0019Mobilization (FFP) (5 July - 31 July 2010)1LS$0
0020ISWM Kick-Off Conference (FFP)1EA$1,500

TOTAL RECYCLING PROGRAM COSTS: BASIC (CLINS 0003, 0005, 0006, 0007, 0008, 0009, 0010*, 0011*, 0014 & 0016) $10,000

TOTAL PRICE: BASIC $19,000

TOTAL EVALUATED PRICE: BASIC $0

OPTION 1KEESLER AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
1001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at KEESLER AFB for the period 01 JULY 2011 to 30 JUNE 2012 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
1002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
1003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
1004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)0MO$0
1005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.0MO$0
1006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.0MO$0
1007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.0EA$0
1008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
1009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
1010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
1011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
1012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
1013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
1014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
1015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
1016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
1017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
1018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
1019RESERVED
1020RESERVED

TOTAL RECYCLING PROGRAM COSTS: BASIC (CLINS 1003, 1005, 1006, 1007, 1008, 1009, 1010*, 1011*, 1014 & 1016) $10,000

TOTAL PRICE: OPTION 1 $17,500

TOTAL EVALUATED PRICE: OPTION 1 $0

OPTION 2KEESLER AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
2001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at KEESLER AFB for the period 01 JULY 2012 to 30 JUNE 2013 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
2002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
2003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
2004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)0MO$0
2005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.0MO$0
2006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.0MO$0
2007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.0EA$0
2008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
2009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
2010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
2011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
2012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
2013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
2014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
2015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
2016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
2017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
2018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
2019RESERVED
2020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 2 (CLINS 2003, 2005, 2006, 2007, 2008, 2009, 2010*, 2011*, 2014 & 2016) $10,000

TOTAL PRICE: OPTION 2 $17,500

TOTAL EVALUATED PRICE: OPTION 2 $0

OPTION 3KEESLER AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
3001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at KEESLER AFB for the period 01 JULY 2013 to 30 JUNE 2014 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
3002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
3003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
3004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)0MO$0
3005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.0MO$0
3006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.0MO$0
3007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.0EA$0
3008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
3009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
3010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
3011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
3012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
3013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
3014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
3015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
3016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
3017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
3018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
3019RESERVED
3020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 3 (CLINS 3003, 3005, 3006, 3007, 3008, 3009, 3010*, 3011*, 3014 & 3016) $10,000

TOTAL PRICE: OPTION 3 $17,500

TOTAL EVALUATED PRICE: OPTION 3 $0

OPTION 4KEESLER AFB
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
4001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at KEESLER AFB for the period 01 JULY 2014 to 30 JUNE 2015 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
4002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
4003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
4004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)0MO$0
4005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.0MO$0
4006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.0MO$0
4007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.0EA$0
4008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
4009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
4010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$7,500
4011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$2,500
4012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
4013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
4014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
4015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
4016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
4017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$7,500
4018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
4019RESERVED
4020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 4 (CLINS 4003, 4005, 4006, 4007, 4008, 4009, 4010*, 4011*, 4014 & 4016) $10,000

TOTAL PRICE: OPTION 4 $17,500

TOTAL EVALUATED PRICE: OPTION 4 $0

TOTAL PRICE: BASIC PLUS ALL OPTIONS - KEESLER $89,000

TOTAL EVALUATED PRICE: BASIC PLUS ALL OPTIONS - KEESLER (IF AWARDED BASIC CONTRACT, WILL BE UTILIZED TO DETERMINE KEESLER TASK ORDER AWARD) $0

ATTACHMENT 3 - SCHEDULE B

(KEESLER AFB)

&P 1 MAR 2010

CLIN Total All Bases-No Fill-In

BASICGOODFELLOW KEESLER SHEPPARD
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
0001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD, GOODFELLOW, AND KEESLER AFBs for the period 01 AUGUST 2010 to 30 JUNE 2011 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
0002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)11MO$0
0003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.11MO$0
0004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)8MO$0
0005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.8MO$0
0006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.8MO$0
0007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.8EA$0
0008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.11MO$0
0009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.11MO$0
0010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$22,500
0011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$7,500
0012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)11MO$0
0013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)11MO$0
0014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.11MO$0
0015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)11MO$0
0016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.11MO$0
0017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$22,500
0018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
0019Mobilization (FFP) (5 July - 31 July 2010)1LS$0
0020ISWM Kick-Off Conference (FFP)1EA$4,500

TOTAL RECYCLING PROGRAM COSTS: BASIC (CLINS 0003, (0005, 0006 & 0007 KEESLER ONLY), 0008, 0009, 0010*, 0011*, 0014 & 0016) $30,000

TOTAL PRICE: BASIC $57,000

TOTAL EVALUATED PRICE: BASIC $0

OPTION 1GOODFELLOW KEESLER SHEPPARD
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
1001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD, GOODFELLOW, AND KEESLER AFBs for the period 01 JULY 2011 to 30 JUNE 2012 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
1002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
1003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
1004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)12MO$0
1005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.12MO$0
1006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.12MO$0
1007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.8EA$0
1008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
1009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
1010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$22,500
1011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$7,500
1012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
1013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
1014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
1015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
1016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
1017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$22,500
1018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
1019RESERVED
1020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 1 (CLINS 1003, (1005, 1006 & 1007 KEESLER ONLY), 1008, 1009, 1010*, 1011*, 1014 & 1016) $30,000

TOTAL PRICE: OPTION 1 $52,500

TOTAL EVALUATED PRICE: OPTION 1 $0

OPTION 2GOODFELLOW KEESLER SHEPPARD
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
2001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD, GOODFELLOW, AND KEESLER AFBs for the period 01 JULY 2012 to 30 JUNE 2013 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
2002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
2003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
2004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)12MO$0
2005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.12MO$0
2006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.12MO$0
2007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.8EA$0
2008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
2009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
2010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$22,500
2011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$7,500
2012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
2013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
2014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
2015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
2016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
2017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$22,500
2018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
2019RESERVED
2020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 2 (CLINS 2003, (2005, 2006 & 2007 KEESLER ONLY), 2008, 2009, 2010*, 2011*, 2014 & 2016) $30,000

TOTAL PRICE: OPTION 2 $52,500

TOTAL EVALUATED PRICE: OPTION 2 $0

OPTION 3GOODFELLOW KEESLER SHEPPARD
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
3001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD, GOODFELLOW, AND KEESLER AFBs for the period 01 JULY 2013 to 30 JUNE 2014 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
3002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
3003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
3004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)12MO$0
3005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.12MO$0
3006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.12MO$0
3007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.8EA$0
3008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
3009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
3010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$22,500
3011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$7,500
3012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
3013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
3014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
3015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
3016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
3017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$22,500
3018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
3019RESERVED
3020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 3 (CLINS 3003, (3005, 3006 & 3007 KEESLER ONLY), 3008, 3009, 3010*, 3011*, 3014 & 3016) $30,000

TOTAL PRICE: OPTION 3 $52,500

TOTAL EVALUATED PRICE: OPTION 3 $0

OPTION 4GOODFELLOW KEESLER SHEPPARD
CONTRACT LINE ITEM NO. (CLIN)SUPPLIES/SERVICEQTYUNITUNIT PRICEAMOUNT
4001NON-PERSONAL SERVICES:
Provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform Integrated Solid Waste Management services at SHEPPARD, GOODFELLOW, AND KEESLER AFBs for the period 01 JULY 2014 to 30 JUNE 2015 in accordance with the Performance-based Work Statement (PWS). This CLIN is not separately priced; the requirement of this CLIN applies to all subsequent CLINS.NSP
4002Municipal Solid Waste / Food Waste Collection -Base
(PWS 2.1.1, 2.1.3-2.1.9, 5.0) (FFP)12MO$0
4003Recyclable Collection - Base
(PWS 2.2.2, 2.2.5-2.2.8, 5.0)(FFP) Identified as recycling costs.12MO$0
4004Municipal Solid Waste Collection - MFH (Non-privatized)
(PWS 2.1.2.1, 5.0)(FFP)12MO$0
4005Yard (Organic) Waste Collection -

MFH (Non-privatized)

(PWS 2.1.2.3, 5.0)(FFP)Identified as recycling costs.12MO$0
4006Recyclable Collection - MFH (Non-

privatized)

(PWS 2.1.2.2, 5.0)(FFP) Identified as recycling costs.12MO$0
4007Bulk Item Pickup - MFH (Non-

privatized)

(PWS 2.1.2.4, 5.0)(FFP) Identified as recycling costs.8EA$0
4008Base Operating Recycling Center
(PWS 2.2.1, 2.2.3-2.2.7, 2.2.9, 5.0)(FFP) Identified as recycling costs.12MO$0
4009Composting
(PWS 2.2.10, 5.0)(FFP) Identified as recycling costs.12MO$0
4010Unscheduled Items Pick-up and

Special Events

(PWS 2.1.1.2, 5.0) (Cost Reimbursable) *Portion or all may be identified as recycling costs.1EANTE$22,500
4011Construction and Demolition Debris

Pick-up (PWS 2.1.1.3, 2.5, 5.0) (Cost Reimbursable)

* Portion or all may be identified as recycling costs.1EANTE$7,500
4012Common Use Trash Receptacle

Collection

(PWS 2.1.1.4, 2.5, 5.0)(FFP)12MO$0
4013Ash Collection
(PWS 2.1.1.6, 2.5, 5.0)(FFP)12MO$0
4014Recyclable Collection -

Public/Common Use

(PWS 2.1.1.5, 2.5, 5.0)(FFP) Identified as recycling costs.12MO$0
4015Disposal
(PWS 2.3., 2.5, 5.0)(FFP)12MO$0
4016Gov't Furnished Equipment Maintenance (PWS 2.4, 5.0)(FFP) Identified as recycling costs.12MO$0
4017Gov't Furnished Equipment Repair (PWS 2.4.5, 5.0) (Cost Reimbursable)1EANTE$22,500
4018Revenue Reimbursement (PWS 2.2.4) (Cost Reimbursable)1LS
4019RESERVED
4020RESERVED

TOTAL RECYCLING PROGRAM COSTS: OPTION 4 (CLINS 4003, (4005, 4006 & 4007 KEESLER ONLY), 4008, 4009, 4010*, 4011*, 4014 & 4016) $30,000

TOTAL PRICE: OPTION 4 $52,500

TOTAL EVALUATED PRICE: OPTION 4 $0

TOTAL PRICE: BASIC PLUS ALL OPTIONS - GOODFELLOW, KEESLER & SHEPPARD $267,000

TOTAL EVALUATED PRICE: BASIC PLUS ALL OPTIONS - GOODFELLOW (IF AWARDED BASIC CONTRACT, WILL BE UTILIZED TO DETERMINE GOODFELLOW TASK ORDER AWARD) $0

ISWM FA3002-09-R-0035 ATTACHMENT 3 - SCHEDULE B CLIN TOTALS FOR GOODFELLOW, SHEPPARD AND KEESLER. FOR REFERENCE ONLY.

CELLS ARE AUTOMATICALLY TALLIED FROM INFORMATION INPUT INTO THE GOODFELLOW, SHEPPARD AND KEESLER SPREADSHEETS. NO FILL-IN REQUIRED.

FOR OFFICIAL USE ONLY

&P 1 MAR 2010

TEP-Basic Contract - No Fill-In

TOTAL EVALUATED PRICE (GOODFELLOW, SHEPPARD, KEESLER): BASIC$0
TOTAL EVALUATED PRICE (GOODFELLOW, SHEPPARD, KEESLER): OPTION 1$0
TOTAL EVALUATED PRICE (GOODFELLOW, SHEPPARD, KEESLER): OPTION 2$0
TOTAL EVALUATED PRICE (GOODFELLOW, SHEPPARD, KEESLER): OPTION 3$0
TOTAL EVALUATED PRICE (GOODFELLOW, SHEPPARD, KEESLER): OPTION 4$0

TOTAL EVALUATED PRICE (GOODFELLOW, SHEPPARD, KEESLER): BASIC PLUS ALL OPTIONS (WILL BE UTILIZED FOR BASIC AWARD PER SECTION L&M) $0

ATTACHMENT 3 - SCHEDULE B (TOTAL EVALUATED PRICE FOR GOODFELLOW, SHEPPARD AND KEESLER)

&N 1 MAR 2010

TOTALS FOR GOODFELLOW,

SHEPPARD AND KEESLER.

FOR REFERENCE ONLY.

NO FILL-IN.

Other files for this federal contract opportunity

Other files attached to Integrated Solid Waste Management (ISWM), newest first.
File Type Posted
PWS Appendix A TBL A-1.pdf PDF
ISWM_RFP_FA3002-09-R-0035-0007(Conformed).doc DOC document
Amendment FA3002-09-R-0035-0007 20100316.pdf PDF
ISWM RFP FA3002-09-R-0035-0006(Conformed).doc DOC document
Amendment FA3002-09-R-0035-0005 20100303.docm DOCM document
Attachment 3 - Container Price List —
Q A's 2 Nov 09.xls XLS spreadsheet
FA3002-09-R-0035 Q A's 20091021.xls XLS spreadsheet
ISWM RFP FA3002-09-R-0035-0003 _Conformed_ 20091021.pdf PDF
Attachment 1 - Performance Work Statement 20 Oct 2009.docm DOCM document
Copy of Q A's 20091016.xls XLS spreadsheet
Tech Library Information.zip ZIP file
ISWM RFP--Amendment 0002 —
Keesler QRP Business Plan —
Q A's 25 Sep 09 v1.xls XLS spreadsheet
Goodfellow QRP Business Plan —
ISWM Pre-Proposal Conference Attendance Sheet.pdf PDF
Teaming Presentation ISWM 18 Sep 09.pdf PDF
Amendment FA3002-09-R-0035-0001 —
FA3002-09-R-0035 - ISWM Solicitation.zip ZIP file
DRAFT ISWM PWS Posted to FedBiz Opps 21 Aug 09.pdf PDF
RFP Working Draft 21 Aug 09 Posted to FedBizOpps.pdf PDF
Goodfellow WD-05-2517.TIF TIF image
Appendices WinZipped.zip ZIP file
DRAFT ISWM PWS 24 July 09.pdf PDF
Unit Costs for Scheduled and Unscheduled Pick-ups.xls XLS spreadsheet
Comment Question Submission Form.xls XLS spreadsheet
Agenda - Goodfellow 2 Jun 09 and Sheppard 4 Jun 09.pdf PDF
ISWM Site Visit Registration Form.pdf PDF
Fort Sam Houston Workload Data.zip ZIP file
Altus Table A2-Recy Supp Data PDF.pdf PDF
Altus Table A1 PDF2.pdf PDF
Altus Table A1- Recy Supp Data PDF2.pdf PDF
Altus Table A1-SW Supp DATA PDF.pdf PDF
Goodfellow Workload Data.zip ZIP file
ISWM Site Visit Registration Form.pdf PDF
Altus Workload Data.zip ZIP file
Altus Table A2 PDF.pdf PDF
Fort Sam Houston Workload Data.zip ZIP file
ISWM Notice to Offeror - Tentative Site Visit Dates.pdf PDF
Altus Appendix C-GFE PDF.pdf PDF
Columbus-Table A2 PDF.pdf PDF
Altus Table A1-SW Supp DATA PDF.pdf PDF
Columbus Appendix C-GFE PDF.pdf PDF
Tyndall Workload Data.zip ZIP file
Columbus-Table A1-Recycling Supp Data PDF.pdf PDF
Columbus-Table A2 PDF.pdf PDF
ISWM PWS —
Industry Day Questionaire.pdf PDF
DoD ISWM Policy dated 1 Feb 08.pdf PDF
Show all 50

Integrated Solid Waste Management (ISWM) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .