AD-101 DEMOLITION PLAN.pdf
PDF 343 KB Posted
- Attached to
- Renovation of 3rd floor building 13A
- Solicitation number
- FA282325R0008
About this file
The document is an Existing/Demolition Plan (drawing AD101) for a renovation project at Eglin Air Force Base, specifically targeting the 3rd floor of Building 13A. The plan details comprehensive interior demolition work, including removal of existing wall construction, floor finishes, ceiling tiles, lighting fixtures, systems furniture, demountable partitions, and mechanical/electrical components. Specific areas to be demolished include open office spaces, conference rooms, restrooms, storage areas, reception, and corridors. Key demolition notes indicate sawcutting window sills, removing existing studs and gypsum board, and preparing surfaces for new construction. The drawing is scaled at 3/16" = 1'-0" and is dated 23 October 2024, with a revision note for RFI adjustments on 05/22/25. The project will be executed in accordance with ICD/IDS 705 and UFC-4-010-05 standards, covering approximately 6,800 square feet of interior renovation space.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 04 20 00.pdf | ||
| 08 71 00.pdf | ||
| 06 41 16.00 10.pdf | ||
| A-110 NEW WORK REFLECTED CEILING PLAN.pdf | ||
| DTRA 13A 3rd Floor RFIs_all_Contracting_FINAL.docx | DOCX document | |
| A-311 WALL SECTIONS.pdf | ||
| EGLIN EMCS AND-OR DDC SYSTEM REQUIREMENTS.pdf | ||
| A-312 WALL SECTIONS.pdf | ||
| 22 00 00.pdf | ||
| A-310 WALL SECTION.pdf | ||
| Addendum 1 _DTRA Renovation 3rd Floor Bldg 13a.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LEGEND:
EXISTING CONSTRUCTION TO REMAIN.
EXISTING CONSTRUCTION TO BE REMOVED.
D
987654321
C
B
A
EXISTING / DEMOLITION PLAN
SCALE: 3/16" = 1'-0"
PROJECT
NORTH
EXIST. MECH
E383
EXIST. MENS
E390
EXIST.
STAIR #2
E388
EXIST.
WOMENS
E389
EXIST. COMM.
E382A
EXIST. SHARED
CONFERENCE
E380
EXIST. CORR.
E378
EXIST. SCIF
E396
EXIST.
SHARED VAULT
E397
EXIST.
STAIR #1
E398
EXIST. CORR.
E379
EXIST. BREAK
E380A
EXIST. A / V
E380B
EXIST. ENTRY
E380C
EXIST.
DIV. CHIEF
381A
EXIST.
OFFICE #2
E396B
EXIST.
OFFICE #1
E396A
EXIST.
CHASE
KEY NOTES:
EXIST. OPEN
OFFICE SPACE NORTH
EXIST. OPEN
OFFICE SPACE SOUTH
EXIST.
UPS
382B
EXIST.
STOR.
EXIST. WAITING
EXIST. RECEPT.
EXIST. CONF.
EXIST.
BRANCH CHIEF
EXIST. STOR.
EXIST. CORR.
EXIST. DEPUTY
DIRECTOR
EXIST. VISITOR
EXIST. BRANCH
CHIEF
REMOVE EXISTING DOOR & FRAME, CLEAN, PATCH, REPAIR AND PREP OPENING FOR
NEW STC 50 RATED HOLLOW METAL DOOR AND FRAME.
REMOVE EXISTING ACOUSTICAL CEILING TILE AND GRID SYSTEM, LIGHTING FIXTURES
AND ALL CEILING MOUNTED EQUIPMENT IN IT'S ENTIRETY.
REMOVE AND DISPOSE OF EXISTING SYSTEMS FURNITURE, DEMOUNTABLE PARTITIONS
AND ALL OTHER FURNITURE IN THEIR ENTIRETY.
REMOVE EXISTING FURRING AROUND COLUMN. COLUMN TO REMAIN (TYPICAL AS INDICATED).
REMOVE EXISTING WALL CONSTRUCTION AND FLOOR FINISH IN ITS ENTIRETY.
PREPARE FLOOR SLAB TO RECEIVE NEW FINISHES.
REMOVE EXISTING DOOR AND FRAME IN THEIR ENTIRETY.6
REMOVE AND DISPOSE OF EXISTING RECEPTIONIST COUNTER.7
REMOVE EXISTING CABINETRY AND REFRIGERATOR.8
REMOVE EXISTING WALL CONSTRUCTION BACK TO EXISTING CMU WALL.9
REMOVE EXISTING FLOOR FINISH AND BASE. CLEAN AND PREP SURFACE TO RECEIVE
NEW FINISH. REMOVE EXISTING ACOUSTICAL CEILING TILE AND GRID SYSTEM AND ALL
CEILING MOUNTED EQUIPMENT.
10 2
REMOVE EXISTING STUDS, GYPSUM BOARD, FURRING AROUND
COLUMNS AND ALL EXISTING FINISHES FROM INTERIOR FACE OF
EXISTING EXTERIOR WALLS. SAWCUT EXISTING WINDOW SILL FLUSH
WITH FACE OF EXISTING CMU WALL.
10 2
9 9
1111111111 11 11
4 4
11111111111111
NO WORK THIS AREA.12
5 5 5
555555
5 5 5 5 5
REMOVE EXISTING GYPSUM BOARD CEILING, LIGHTING FIXTURES
AND ALL CEILING MOUNTED EQUIPMENT IN IT'S ENTIRETY.
X
KEY PLAN
NOT TO SCALE
CONSTRUCTION WILL BE IAW
ICD/IDS 705 AND UFC-4-010-05
NOTE:
96 CEG, OFFICE FORM 002, FY2013
AS-BUILT
PDM
REVISION DATE DESCRIPTION BY APPR'D
23AJ FTFA23-VH79 23AJ
23 OCT. 2024
AS SHOWN
DTRA RENOVATION
3RD FLOOR BLDG 13A
BASE CIVIL ENGINEER EGLIN
AIR FORCE BASE, FLORIDA
BWA
AD101
EXISTING / DEMOLITION PLAN
SCALE: 3/16" = 1'-0"
2'-8" 5'-4"0 10'-8"
1 05/22/25 RFI ADJUSTMENTS KRW PDM
AutoCAD SHX Text
DATE
AutoCAD SHX Text
SIGNATURE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
CENM
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
PROJ. ENGR.
AutoCAD SHX Text
CONTENTS
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
SPEC. NO.
AutoCAD SHX Text
INDEX NO.
AutoCAD SHX Text
PROJ. NO.
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
96 CEG/CEN
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
BASE CIVIL ENGINEER
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
FILE NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
SHEET OF
| Sheets and Views |
| AD-101 |
File details come from the government source that posted it. Updated .