ODR Countertop and Cabinets_AF66_09102026.xlsx
XLSX spreadsheet 21 KB Posted
- Solicitation number
- FA254326R0012
About this file
This is an AF Form 66 Schedule of Material Submittals document for the ODR Countertop and Cabinets Replacement project at Buckley Space Force Base, dated 10 September 2026. The schedule outlines eight required contractor submittals with specific deadlines, reviewers, and approval requirements for the project managed by the Department of the Air Force Space Command.
The submittals include: (1) Project Work Schedule due 5 business days after kickoff meeting; (2) Counter and Cabinet Design Sketch due 10 calendar days after Notice to Proceed; (3) Countertop and Cabinet Color Samples due 15 calendar days after Notice to Proceed; (4) Ski Desk Product Details due 15 calendar days after Notice to Proceed; (5) Power and Internet Plug Layout due 15 calendar days after Notice to Proceed; (6) Final Walkthrough and "Fix-It" List due 3 business days after pre-final inspection; (7) 1-Year Warranty Letter due 5 business days after final inspection; and (8) Safety and Material Certificate due 5 business days after final inspection. All submittals require Project Manager review and approval/disapproval determination, with provisions for contractor resubmittal and final approval documentation. The form includes columns for submittal number, date received, civil engineering routing, return suspense dates, and remarks. This submittal schedule is associated with the single-phase installation of an ADA-compliant L-shaped front counter with three-tiered back-wall storage, two ski desks, electrical conduit routing, and plumbing hookups at the Buckley Space Force Base Outdoor Recreation Facility.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF66
| SCHEDULE OF MATERIAL SUBMITTALS | ODR Countertop & Cabinets Replacement | Date: 10 September 2026 | ||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||
| ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | NUMBER OF SUBITTALS | REQUIRED SUBMISSION DATE (No Later Than) | REVIEWER (PM/Insp) | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | AF3000 SUBMITTAL NUMBER | DATE CONTRACTOR NOTIFIED APPROVED / DISAPPROVED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| 1 | Project Work Schedule | 1 | 5 BD after Kickoff Meeting | PM | ||||||||
| 2 | Counter & Cabinet Design Sketch | 1 | 10 CD after NTP | PM | ||||||||
| 3 | Countertop & Cabinet Color Samples | 1 | 15 CD after NTP | PM | ||||||||
| 4 | Ski Desk Product Details | 1 | 15 CD after NTP | PM | ||||||||
| 5 | Power & Internet Plug Layout | 1 | 15 CD after NTP | PM | ||||||||
| 6 | Final Walkthrough & "Fix-It" List | 1 | 3 BD after pre-final inspection | PM | ||||||||
| Closeout Documents | ||||||||||||
| 7 | 1-Year Warranty Letter | 1 | 5 BD after final inspection | PM | ||||||||
| 8 | Safety & Material Certificate | 1 | 5 BD after final inspection | PM | ||||||||
| Additional Submittals | ||||||||||||
| 44 | ||||||||||||
| 45 | ||||||||||||
| 46 | ||||||||||||
| 47 | ||||||||||||
| AF FORM 66, OCT 89 |