This document is a technical specification section for Sanitary Waste and Vent Piping (Section 221316), detailing requirements for PVC piping installation in plumbing systems. The specification covers performance requirements, product specifications, and installation guidelines for PVC drainage piping. Approved manufacturers include Apollo Valves, Charlotte Pipe and Foundry Company, National Pipe and Plastic, North America Pipe Corporation, Rocky Mountain Colby Pipe Company, and Silver-line Plastics.
Key technical requirements include using solid-wall PVC pipe meeting ASTM D2665 standards, PVC socket fittings compliant with ASTM D2665 and ASTM D3311, and solvent-cemented joints. Installation specifications mandate a two percent downward slope for horizontal sanitary waste piping, installation of piping in concealed locations or equipment rooms, and proper support using carbon-steel hangers. The document also outlines joint construction methods, connection procedures, identification requirements, field quality control processes, and cleaning and protection guidelines for the piping system.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SANITARY WASTE AND VENT PIPING 221316 - 1
SECTION 221316 - SANITARY WASTE AND VENT PIPING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. PVC pipe and fittings.
1.2 ACTION SUBMITTALS
A. Product Data: For each type of product.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Components and installation are capable of withstanding the following minimum working pressure unless otherwise indicated:
1. Soil, Waste, and Vent Piping: 10 ft. head of water.
2. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified."
2.2 PIPING MATERIALS
A. Piping materials to bear label, stamp, or other markings of specified testing agency.
B. Comply with requirements in "Piping Schedule" Article for applications of pipe, tube, fitting materials, and joining methods for specific services, service locations, and pipe sizes.
2.3 PVC PIPE AND FITTINGS
A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:
1. Apollo Valves
2. Charlotte Pipe and Foundry Company
3. National Pipe and Plastic, Inc. (Oldcastle)
4. North America Pipe Corporation
5. Rocky Mountain Colby Pipe Company
SANITARY WASTE AND VENT PIPING 221316 - 2
6. Silver-line Plastics
B. Solid-Wall PVC Pipe: ASTM D2665 drain, waste, and vent.
C. PVC Socket Fittings: ASTM D2665, made in accordance with ASTM D3311, drain, waste, and vent patterns and to fit Schedule 40 pipe.
D. Adhesive Primer: ASTM F656.
PART 3 - EXECUTION
3.1 INSTALLATION OF PIPING
A. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems.
1. Indicated locations and arrangements were used to size pipe and calculate friction loss, expansion, pump sizing, and other design considerations.
2. Install piping as indicated unless deviations to layout are approved on coordination drawings.
B. Install piping in concealed locations unless otherwise indicated and except in equipment rooms and service areas.
C. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise.
D. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.
E. Install piping to permit valve servicing.
F. Install piping at indicated slopes.
G. Install piping free of sags and bends.
H. Install fittings for changes in direction and branch connections.
I. Install piping to allow application of insulation.
J. Install soil and waste and vent piping at the following minimum slopes unless otherwise indicated:
1. Horizontal Sanitary Waste Piping: Two percent downward in direction of flow.
K. Install aboveground PVC piping in accordance with ASTM D2665.
L. Do not enclose, cover, or put piping into operation until it is inspected and approved by authorities having jurisdiction.
SANITARY WASTE AND VENT PIPING 221316 - 3
M. Install escutcheons for piping penetrations of walls, ceilings, and floors.
1. Comply with requirements for escutcheons specified in Section 220500 "Common Work Results for Plumbing."
3.2 JOINT CONSTRUCTION
A. Plastic, Nonpressure-Piping, Solvent-Cement Joints: Clean and dry joining surfaces.
Join pipe and fittings in accordance with the following:
1. Comply with ASTM F402 for safe-handling practice of cleaners, primers, and solvent cements.
2. ABS Piping: Join in accordance with ASTM D2235 and ASTM D2661 appendixes.
3. PVC Piping: Join in accordance with ASTM D2855 and ASTM D2665 appendixes.
3.3 INSTALLATION OF HANGERS AND SUPPORTS
A. Comply with requirements for pipe hanger and support devices and installation specified in Section 220529 "Hangers and Supports for Plumbing Piping and Equipment”.
1. Install carbon-steel pipe hangers for horizontal piping in noncorrosive environments.
2. Install carbon-steel pipe support clamps for vertical piping in noncorrosive environments.
3. Vertical Piping: MSS Type 8 or Type 42 clamps.
4. Install individual, straight, horizontal piping runs:
a. 100 Ft. (30 m) and Less: MSS Type 1, adjustable, steel clevis hangers.
b. Longer Than 100 Ft. (30 m): MSS Type 43, adjustable roller hangers.
c. Longer Than 100 Ft. (30 m) if Indicated: MSS Type 49, spring cushion rolls.
5. Multiple, Straight, Horizontal Piping Runs 100 Ft. (30 m) or Longer: MSS Type 44 pipe rolls. Support pipe rolls on trapeze.
6. Base of Vertical Piping: MSS Type 52 spring hangers.
B. Install hangers for PVC piping, with maximum horizontal spacing and minimum rod diameters, to comply with manufacturer's written instructions, locally enforced codes, and authorities having jurisdiction requirements, whichever are most stringent.
C. Support horizontal piping and tubing within 12 inches of each fitting, valve, and coupling.
D. Support vertical runs of PVC piping to comply with manufacturer's written instructions, locally enforced codes, and authorities having jurisdiction requirements, whichever are most stringent.
SANITARY WASTE AND VENT PIPING 221316 - 4
3.4 CONNECTIONS
A. Drawings indicate general arrangement of piping, fittings, and specialties.
B. Connect waste and vent piping to the following:
1. Equipment: Connect waste piping as indicated.
C. Where installing piping adjacent to equipment, allow space for service and maintenance of equipment.
3.5 IDENTIFICATION
A. Identify exposed sanitary waste and vent piping.
B. Comply with requirements for identification specified in Section 220553 "Identification for Plumbing Piping and Equipment."
3.6 FIELD QUALITY CONTROL
A. During installation, notify authorities having jurisdiction at least 24 hours before inspection must be made. Perform tests specified below in presence of authorities having jurisdiction.
1. Roughing-in Inspection: Arrange for inspection of piping before concealing or closing-in after roughing-in and before setting fixtures.
2. Final Inspection: Arrange for final inspection by authorities having jurisdiction to observe tests specified below and to ensure compliance with requirements.
B. Reinspection: If authorities having jurisdiction find that piping will not pass test or inspection, make required corrections and arrange for reinspection.
C. Reports: Prepare inspection reports and have them signed by authorities having jurisdiction.
3.7 CLEANING AND PROTECTION
A. Clean interior of piping. Remove dirt and debris as work progresses.
B. Protect sanitary waste and vent piping during remainder of construction period to avoid clogging with dirt and debris and to prevent damage from traffic and construction work.
C. Place plugs in ends of uncompleted piping at end of day and when work stops.
D. Repair damage to adjacent materials caused by waste and vent piping installation.
SANITARY WASTE AND VENT PIPING 221316 - 5
3.8 PIPING SCHEDULE
A. Flanges and unions may be used on aboveground pressure piping unless otherwise indicated.
B. Aboveground, soil and waste piping NPS 4 (DN 100) and smaller are to be the following:
1. Solid-wall PVC pipe, PVC socket fittings, and solvent-cemented joints.
2. Dissimilar Pipe-Material Couplings: Unshielded, nonpressure transition couplings.
END OF SECTION 221316