EXHIBIT L - Contract for Design-Build Services with Guaranteed Maximum Price 08.2026.pdf

PDF 725 KB Posted

Attached to
Maaske and APSC Remodel RFP
Solicitation number
S-580200-00018488
Issued by
Multnomah County, Mission CDP, Oregon

About this file

This is a Design/Build Contract for Guaranteed Maximum Price services between Western Oregon University (WOU) Facilities Services and a Design/Builder for the Computer Solutions Hub project (WOU Contract # 2026-0501-FAC-GE). The Design/Builder will provide integrated architectural, engineering, and construction services on a design-build delivery basis with a guaranteed maximum price range of $10.9 to $12.2 million. The project scope includes design phases (Program Verification and Conceptual Design, Schematic Design, Design Development, and Construction Documents) followed by construction services. The Design/Builder must submit the Guaranteed Maximum Price proposal upon completion of 100% Design Development, with detailed construction documents to follow at the 95% stage. The contract establishes a preliminary overall project schedule (Exhibit B) with specific milestones for design submittals and construction completion. Key personnel include the Design/Builder's Architect of Record, Project Manager, and on-site Job Superintendent, all subject to Owner approval and not replaceable without written consent. The Design/Builder must conduct bi-weekly meetings during design phases and weekly meetings during construction, maintaining comprehensive project documentation and status reporting. Owner's authorized representative is Gabriela Eyster (eysterg@wou.edu, 971-341-9398).

Compensation for Design Services is paid upon achievement of design milestones listed in Exhibit G, with Design/Builder entitled to reimbursable expenses for authorized transportation, meal and lodging costs, reproduction of documents, and other specified items. Construction Services compensation is limited to the guaranteed maximum price covering subcontractor payments, direct labor wages, supervisory and administrative personnel staffing costs, materials and equipment, general conditions costs, and overhead and profit. The Design/Builder's Contingency is capped at 5% of the cost of work and may be utilized only with Owner's written approval for specific purposes including design errors and omissions, schedule recovery, or compliance with building codes. Buyout savings from subcontract bidding are first applied to offset shortfalls, with any remaining savings added to the construction contingency. The Design/Builder must comply with Oregon prevailing wage requirements (ORS 279C.800-870) and apprenticeship requirements under Section 12, Chapter 630, Oregon Laws 2025, including employing apprentices for 15% of work hours, establishing outreach and recruitment plans for women and minorities, and providing health insurance and retirement benefits. Professional Liability Insurance is required at $1,000,000 per claim/$3,000,000 annual aggregate for the Design/Builder's consultants. The Owner retains audit rights for three years after final payment and may audit Design/Builder and subcontractor records; overcharges exceeding 1% of total payment or $50,000 trigger Owner reimbursement for audit costs. Any savings realized upon project completion are split 50/50 between Owner and Design/Builder.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WOU Design/Build Contract REV 07/01/2026 Page 1

CONTRACT FOR DESIGN/BUILD SERVICES WITH GUARANTEED MAXIMUM PRICE

(“Contract” or “Design/Build Contract”)

THIS CONTRACT IS BETWEEN:

OWNER: Western Oregon University

Facilities Services

345 N Monmouth Ave.

Monmouth, OR 9761 and

DESIGN/BUILDER: ______________________________________

(Referred to as Contractor in the

WOU General Conditions and herein referred to as the “Design/Builder”): _______________________________________

Phone: ( ) - E-mail: ________________

Oregon CCB# ____________________________

Project: Computer Solutions Hub

WOU Contract # 2026-0501-FAC-GE

Design/Builder’s Representative: ________________________________________

Phone: ( ) - E-mail: ________________

Owner’s Authorized Representatives: Gabriela Eyster

Phone: (971) 341-9398 / E-mail: eysterg@wou.edu

The Owner's Target GMP Range: $10.9 to $12.2 Million

Date: Date

WOU Design/Build Contract REV 07/01/2026 Page 2

WESTERN OREGON UNIVERSITY

DESIGN/BUILD CONTRACT

Table of Contents

ARTICLE PAGE

1 Definitions p. 3

2 General Description of Services p. 4

3 Duties, Obligations and Responsibilities of the Parties p. 6

4 Design Services Requirement and Standards p. 8

5 Design / Preconstruction Services p. 9

6 Additional Design Services p. 14

7 Construction Services p. 15

8 Compensation p. 22

9 Insurance and Bonds p. 27

10 Audit Rights p. 27

11 Use of Design/Builder’s Drawings, Specifications and Other Documents p. 28

12 Miscellaneous p. 28

Exhibit A Project Description, Project Budget and Documents and Guidelines p. 32

Exhibit B Preliminary Project Schedule p. 33

Exhibit C Schedule of Services, Consultants and Personnel p. 34

Exhibit D Requirements for Design Document Submittal to Owner p. 36

Exhibit E Form of Early Work Amendment, GMP Amendment, Final Amendment p. 38

Exhibit F Performance and Payment Bonds p. 39

Exhibit G Schedules of Payment for Design Services and Reimbursable Expenses p. 40

Exhibit H WOU General Conditions & Supplemental General Conditions p. 42

WOU Design/Build Contract REV 07/01/2026 Page 3

RECITALS

WHEREAS, Owner issued a Request for Proposals (the “RFP”) on July 1, 2026, to solicit bids from interested Design/Builders for the design and construction of the project described as part of Exhibit A

(the “Project”); and

WHEREAS, Owner has selected Design/Builder to perform the Project; and

WHEREAS, Owner and Design/Builder desire to enter into this Contract.

NOW THEREFORE, the Owner and Design/Builder agree as follows:

ARTICLE 1. DEFINITIONS

Except as expressly defined or modified below or elsewhere in this Contract, all capitalized terms shall have the meanings set forth in Section A of the WOU General Conditions for Design/Build Services

Contracts, attached as Exhibit H hereto (the “WOU General Conditions”). The terms below are expressly defined as follows:

1.1 Construction Services. “Construction Services” has the same meaning as “Work” as defined in the

WOU General Conditions.

1.2 Design / Preconstruction Services. “Design / Preconstruction Services” means services performed by the Design/Builder as described in Articles 5 and 6 as well as those portions of Sections 7.9 and 7.10 reasonably

1.3 Early Work. “Early Work” means Construction Services authorized by Amendment that the parties agree should be performed in advance of establishment of the GMP. Permissible Early Work shall be limited to: early procurement of materials and supplies; early release of bid or proposal packages for site development and related activities; and any other advance work related to critical components of the

Project for which performance prior to establishment of the GMP will materially affect the critical path schedule of the Project.

1.4 Early Work Amendment. “Early Work Amendment” means an Amendment to this Design/Build

Contract executed by the parties to authorize Early Work. Included as part of Exhibit E.

1.5 GMP Amendment. “GMP Amendment” means an Amendment to the Contract, issued in the form of GMP Amendment included in Exhibit E and executed by and between the parties, to establish the

GMP and identify the GMP Supporting Documents for Construction Services.

1.6 GMP Supporting Documents. “GMP Supporting Documents” means the documents referenced in the GMP Amendment as the basis for establishing the GMP. The GMP Supporting Documents shall expressly identify the Plans and Specifications, assumptions, qualifications, exclusions, conditions, unit prices, and alternates that form the basis for the GMP.

1.7 Scope Change. “Scope Change” means only (i) changed site conditions not reasonably inferable from information available to Design/Builder at the time of execution of the GMP Amendment, and

(ii) significant Work modifications (including additions, substitutions, and deletions), application of

Allowances, and selection of alternates, all as approved by the Owner under the Contract beyond that identified or inferable from the GMP Supporting Documents.

WOU Design/Build Contract REV 07/01/2026 Page 4

ARTICLE 2. GENERAL DESCRIPTION OF SERVICES

2.1 The Services. The Design/Builder agrees to furnish or arrange for the architectural, engineering and construction services set forth herein and required for completion of the Project on a Guaranteed

Maximum Price (hereinafter defined) basis. Design/Builder represents that it is thoroughly familiar with and understands the requirements of the Project scope and is experienced in the design, administration and construction of building projects of the type and scope contemplated by the Owner’s Facilities

Program for the Project. Design/Builder represents to Owner that Design/Builder has all necessary architectural, engineering and construction education, skill, knowledge and experience required for the

Project and will maintain at all times during the term of this Agreement, such personnel on its staff to provide the services contemplated hereby within the time periods required hereby. In addition, Design/Builder represents that it or Owner-approved subcontractors performing services under this

Agreement have all applicable licenses required by the State of Oregon to perform such services.

2.1.1 All services constituting the practice of architecture shall be provided by the

Design/Builder’s Architect of Record, identified in Exhibit C to this Agreement. No substitution of

Design/Builder’s Architect of Record shall occur except with the prior written consent of Owner.

Design/Builder agrees to support Owner’s efforts to create a collaborative and cooperative team among the Architect of Record, Design/Builder and Owner’s Representative, and Design/Builder agrees that the

Architect of Record shall attend all Project team meetings between the representatives of the Owner and the Design/Builder, and at other Project meetings as requested by the Owner. Nevertheless, Design/Builder remains solely liable to Owner for completion and delivery of all Design Services required under this Agreement.

The Owner's review or acceptance of documents, or authorization to continue to the next phase of design or construction, shall not be deemed as approval of the adequacy of the plans, drawings, specifications, or other documents. Any review or acceptance by the Owner will not relieve the

Design/Builder of any responsibility for complying with the standard of care set forth herein. The

Design/Builder is responsible for all Services to be performed under this Agreement, and agrees that it will be liable for all its negligent acts, errors, or omissions, if any, relative to the Services;

2.1.2 Design/Builder agrees that this Agreement, the Design Development Documents and the

Construction Documents prepared by Design-Builder and approved by Owner shall serve as the basis for the Work.

2.1.3 Design/Builder shall appoint a representative who will be available to Owner and who shall have the expertise and experience required to supervise the Work (the “Design/Builder’s

Representative”) for the duration of the Project. Design/Builder’s Representative shall communicate regularly with Owner and shall have the authority to act on behalf of Design/Builder. Design/Builder’s

Representative may be replaced during the Project only with Owner’s prior written consent in accordance with Article 3.6 of this Agreement.

2.1.4 Design/Builder shall conduct meetings with Owner and the Design/Builder’s Architect of

Record at least once every two (2) weeks during the design phase and weekly meetings during the construction phase of the Work. At the meetings, the Design/Builder shall provide to Owner a status report detailing the progress of the Work and other information as required by the Project documents.

The status report shall include not less than the following items: 1) a schedule update, with a detailed 3 week look-ahead schedule and an overall schedule with any modifications to the original schedule identified. With this update provide a list of any matters that have a potential impact to the schedule including but not limited to changes in scope, unforeseen conditions, weather conditions, labor issues, etc.

Describe how these issues are impacting both the critical path and anticipated float within the schedule; 2)

WOU Design/Build Contract REV 07/01/2026 Page 5 any discrepancies, conflicts, or ambiguities in the Contract Documents that require resolution. Review all items that have cost or schedule impacts as part of a tracked log that is updated continually over the course of the project; 3) any safety issues related to the Work; 4) any other matters that require resolution to ensure timely and cost-effective completion of the Work. At least two Business Days prior to the scheduled meeting, Design/Builder shall submit to Owner a list of identified matters that will require resolution, any matters that require Owner’s approval, and any proposed deviations from the Project schedule. The Design/Builder shall take meeting notes and within three (3) Days following each meeting provide the Owner’s Representative and attendees with minutes of the meeting.

2.1.5 The Design/Builder shall work within the Owner’s design guidelines, attached as part of

Exhibit A, to incorporate processes, patterns and frameworks established for development and to incorporate defined strategies during the construction process.

2.1.6 Owner’s review of, and response to, any of the matters presented above shall not relieve

Design/Builder of its obligation to complete the Work within the Contract Time and shall not be construed as relieving Design/Builder of its complete and exclusive control over the means, methods, sequences and techniques for executing the Work. Owner bears no financial liabilities for the project due to schedule delays related to site mobilization and/or demolition, or review processes by local jurisdiction.

2.2 Project Schedule. Design/Builder has provided Owner with a preliminary overall Project schedule covering the planning, design and construction of the Project which is attached hereto as Exhibit B. This preliminary schedule shall serve as the framework for the subsequent development of all detailed construction schedules described in the WOU General Conditions. The Design/Builder shall at all times carry out its duties and responsibilities as expeditiously as possible and in accordance with the Project schedule. As the schedule should be optimized to efficiently deliver a cost-effective project, the

Design/Builder shall consider time to be of the essence in the performance of this Contract. Modifications to the proposed schedule attached as Exhibit B must be agreed upon by both the Design/Builder and the

Owner prior to modifying the contract time.

2.3 Work Hours. The Design/Builder shall maintain work hours to be between 7am and 5pm local time unless previously authorized in writing by the Owner.

2.4 Cooperation. Endeavor to develop, implement and maintain, a spirit of cooperation, collegiality, and open communication with Owner so that the goals and objectives of each are clearly understood, potential problems are resolved promptly, and, upon completion, the Project is deemed a success.

2.5 Interactive Design Process. The Design/Builder shall engage the Owner in an interactive, informational, collaborative user group-oriented design process similar to that described by the 2018

WOU Master Plan (Link: https://wou.edu/vpgc) during each stage of the design process described in

Article 5 of this Contract. This process should contain consistent meetings to discuss, develop and review concepts, diagrams, plans and details as they develop on the project.

2.6 Preparation/Sufficiency of Site. Before commencing the design and construction work, the

Design/Builder shall (i) visit and thoroughly inspect the Project site and any structure(s) or other manmade features to be modified and become familiar with local conditions under which the Project will be constructed and operated; (ii) familiarize itself with the survey, including the location of all existing buildings, utilities, conditions, streets, equipment, components and other attributes having or likely to have an impact on the Project; (iii) familiarize itself with the Owner’s layout and design requirements, conceptual design objectives, and budget for the Project; (iv) familiarize itself with pertinent Project dates and programming needs, including the Project schedule; (v) review and analyze all Project geotechnical, Hazardous Substances structural, chemical, electrical, mechanical and construction

WOU Design/Build Contract REV 07/01/2026 Page 6 materials tests, investigations and recommendations; and (vi) gather any other information necessary for a thorough understanding of the Project. If the Project involves modifications to any existing structure(s) or other man-made feature(s) on the Project site, the Design/Builder shall also review all as-built and record drawings, plans and specifications of which Design/Builder has been informed by Owner about and thoroughly inspect the existing structure(s) and man-made feature(s) to identify existing deficiencies and ascertain the specific locations of pertinent structural components. Claims by Design/Builder resulting from Design/Builder’s failure to familiarize itself with the site or pertinent documents shall be deemed waived.

2.7 Project Team. Design/Builder will use the Project Team identified on Exhibit C.

Design/Builder will not remove or replace any members of the Project Team except with the written approval of Owner based upon good cause shown or as directed by Owner as provided hereunder.

Further, if any member of the Project Team discontinues service on the Project for any reason whatsoever, Design/Builder shall promptly replace such team member with a qualified individual approved by Owner, in writing, which approval will not be unreasonably withheld.

2.8 Contract for Design/Build Construction. The “Contract for Design/Build Construction,” which constitutes the entire agreement between Owner and Design/Builder, consists of: this Agreement and all exhibits hereto; WOU General Conditions; supplemental general conditions, if any; proposal(s) submitted by Design/Builder and accepted by Owner, if any; the Construction Documents; any Change Orders or addenda executed by the Owner and the Design/Builder hereafter; Owner-approved change order(s) or field orders; and the additional documents listed as part of Exhibit A, if any. Documents not included or expressly contemplated in this Article 2.7 do not, and shall not, form any part of the Contract for

Design/Build Construction. Without limiting the generality of the foregoing, shop drawings and other submittals from the Design/Builder or its subcontractors and suppliers do not constitute a part of the

Contract for Design/Build Construction.

2.9 Third Party Quality Assurance. The Design/Builder shall participate in, and cooperate with, design-phase, construction-phase, and post-occupancy energy analysis, commissioning (including peer review), testing, validation, and other third-party quality assurance and quality control processes as established by the Owner.

ARTICLE 3. DUTIES, OBLIGATIONS AND RESPONSIBILITIES OF THE PARTIES

3.1 Project Information. Design/Builder acknowledges that Owner has provided Design/Builder with information regarding Owner’s requirements for the Project as set forth in the Space Program, Narrative

Specification and Equipment List, provided as part of Exhibit A.

3.2 Independent Contractor. The Design/Builder is an independent contractor and not an officer, employee, or agent of Owner as those terms are used in ORS 30.265.

3.3 Performance of Work. The Design/Builder covenants with Owner to cooperate with the Owner’s

Authorized Representative and utilize the Design/Builder’s professional skill, efforts and judgment in furthering the interests of Owner; to furnish efficient design services, business administration and supervision; to furnish at all times an adequate supply of workers and materials; and to perform the Work in conformance with the terms and conditions of the Contract Documents and in an expeditious and economical manner consistent with the interests of Owner.

3.4 Forms and Procedures. The Owner may develop procedures and forms for the administration and tracking of the Contract. The Design/Builder agrees to abide by those procedures and use those forms.

WOU Design/Build Contract REV 07/01/2026 Page 7

3.5 Design/Builder’s Project Staff. The Design/Builder's Project staff shall consist of the following personnel:

3.5.1 Project Architect: ______________ shall be the Design/Builder’s Project Architect and will supervise and coordinate all Design / Preconstruction Services, participate in all meetings, and perform Construction Administration Services as defined in this Contract.

3.5.2 Project Manager: __________ shall be the Design/Builder’s Project Manager and will supervise and coordinate all Construction Services of Design/Builder and participate in all meetings throughout the Project term unless otherwise directed by Owner. Design/Builder represents that the

Project Manager has authority to execute Change Orders and Contract Amendments on behalf of

Design/Builder.

3.5.3 Job Superintendent: If Construction Services are requested and accepted by Owner, __________ shall be the Design/Builder’s on-site job superintendent throughout the Project term.

3.6 Key Persons. The Design/Builder’s personnel identified in Article 3.5, any other personnel identified by name in Design/Builder's Proposal and any other personnel identified in Exhibit C to this

Design/Build Contract shall be considered Key Persons and shall not be replaced during the Project without the written permission of Owner, which shall not be unreasonably withheld. If the

Design/Builder intends to substitute personnel, a request must be given to Owner at least 30 Days (or such shorter period as permitted by Owner) prior to the intended time of substitution. When replacements have been approved by Owner, the Design/Builder shall provide a transition period of at least 10 Business

Days during which the original and replacement personnel shall be working on the Project concurrently.

This transition period will not constitute any additional cost to the Owner. All cost for the duplicated staff shall be borne by the Design/Builder. Once a replacement for any of these staff members is authorized, further replacement shall not occur without the written permission of Owner.

3.7 Owner’s Budget. The Owner shall establish and update an overall budget for the Project, including amounts allocated for design and construction, the Owner's other costs and reasonable contingencies related to these costs as appropriate. Owner shall distribute all budget updates to the Design/Builder on a monthly basis.

3.8 Owner’s Representative. The Owner shall designate a representative(s) authorized to act on the

Owner's behalf with respect to the Project.

3.9 Time for Performance. The Owner shall review and approve or take other appropriate action on all design submittals of the Design/Builder within the timeframes set forth in Exhibit B.

3.10 Property Survey. The Owner has furnished a property survey of the project site, as part of Exhibit

A. If required, the Owner shall furnish additional survey information, or direct the Design/Builder to obtain, at the Owner's expense, surveys describing additional physical characteristics, legal limitations and utility locations for the Project site, and a written legal description of the Project site. The surveys and legal information shall include, as applicable, grades and lines of streets, alleys, pavements and adjoining property and structures; adjacent drainage; rights-of-way, restrictions, easements, encroachments, zoning, deed restrictions, boundaries and contours of the site; locations, dimensions and necessary data pertaining to existing buildings, other improvements and trees; and information concerning available utility services and lines, both public and private, above and below grade, including inverts and depths. If the Design/Builder desires additional property surveys, the Owner must be consulted on any missing requirements prior to the acquisition of any additional survey information.

WOU Design/Build Contract REV 07/01/2026 Page 8

3.11 Geotechnical Testing. The Owner has furnished a geotechnical report of the project site, as part of

Exhibit A. If the Design/Builder desires additional testing, the Owner must be consulted on any missing requirements. If required, the Owner shall furnish additional testing information, or direct the

Design/Builder to obtain, at the Owner's expense, the services of geotechnical engineers as necessary for the Project. Such services may include, but are not limited to, test borings, test pits, sub-surface imaging, determinations of soil bearing values, percolation tests, evaluations of hazardous materials, ground corrosion and resistivity tests, including necessary operations for anticipating subsoil conditions, with reports and appropriate Design/Builder recommendations.

3.12 Hazardous Materials. The Owner has included complete documentation associated with the removal of Asbestos containing materials from the site as part of Exhibit A. Existing structures may contain lead paint. The containment of or removal of lead paint shall be the responsibility of the

Design/Builder. The Design/Builder must follow all local regulations associated with the handling of these materials.

3.13 Purpose of Owner’s Review. Owner’s review, inspection, or approval of any Work, Design

Documents, Applications for Payment or other submittals shall be solely for the purpose of determining whether the same are generally consistent with Owner’s Program and specifications, standards, policies and requirements. No review, inspection, or approval by Owner of such Work or documents shall relieve

Design/Builder of its responsibility for the performance of its obligations under the Contract for

Design/Build Construction or the accuracy, adequacy, fitness, suitability, or coordination of its Design

Services or the Work. Approval by any governmental or other regulatory agency or other governing body of any Work, Design Document, or the Construction Documents shall not relieve Design/Builder of responsibility for the performance of its obligations under this Agreement. Payment by Owner pursuant to the Contract for Design/Build Construction shall not constitute a waiver of any of Owner’s rights under the Contract for Design/Build Construction or at law, and Design/Builder expressly accepts the risk that defects in its performance, if any, may not be discovered until after payment, including final payment, is made by Owner. Notwithstanding the foregoing, prompt written notice shall be given by the Owner to the Design/Builder if the Owner becomes aware of any fault or defect in the Project or non-conformance with the Contract for Design/Build Construction.

3.14 Status of Owner. The Owner shall not have control or charge of construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, nor shall the Design/Builder, for any of the foregoing purposes, be deemed the agent of the Owner.

3.15 Owner’s Utilities. Owner has utilities (Electrical, Water, Steam, etc.) on this project site. Contractor is responsible for cost to make metered connection for temporary service during construction. Owner will pay for cost of consumption.

ARTICLE 4. DESIGN SERVICES REQUIREMENTS AND STANDARDS

4.1 Quality of Design Services. Design/Builder shall be responsible for the quality, completeness, accuracy, and coordination of Design and Construction Documents. Design/Builder shall provide Design

Services that comply with all applicable statutes, rules, regulations, ordinances and other laws which are applicable to the design and construction of the Project, and shall be complete and functional for the purposes intended. Design/Builder shall provide for all testing and inspections required by sound architectural and engineering practices and by governmental authorities having jurisdiction over the

Project.

WOU Design/Build Contract REV 07/01/2026 Page 9

4.2 Errors and Omissions. The Design/Builder shall, at no additional cost to the Owner, immediately make additions, changes and corrections to any documents prepared by Design/Builder necessitated by errors and omissions in the Design/Builder’s performance of its services. In addition, Design/Builder shall not be entitled to any compensation or adjustment in the GMP for additional work required as a result thereof, provided, upon Owner’s written approval, Design/Builder may use contingency funds to pay for Work not included in the Construction Documents which add value to the Project (but expressly excluding any demolition or other costs related to the substitution of such Work for previously installed

Work and associated design fees). The foregoing shall not relieve Design/Builder for liability to Owner for any damages, including costs incurred by Owner after termination in whole or in part of this

Agreement, resulting from any error or omissions by Design/Builder in the course of its duties under this

Agreement.

4.3 Standard of Care. By execution of this Contract, the Consultant agrees that all Design Services and

Construction services performed by the Design/Builder, any other persons, subcontractors, suppliers, or entities for whom Design/Builder is responsible shall be held to the highest standard of care, diligence, skill and judgment in the rendition of all services, which shall be no less than that exercised by consultants of similar reputation performing work for projects of a size, scope and complexity similar to the work for which the Design/Builder or it’s consultants are retained.

4.4 Design Standards. The Design/Builder shall perform all services in accordance with requirements of governmental agencies having jurisdiction over the Project, Owner guidelines, and any other guidelines described as part of Exhibit A. In addition, the Design/Builder’s design shall comply with all applicable building codes, accessibility laws and regulations, Owner design standards, and other standards in effect at the time of the design work. To the extent Owner’s standards exceed applicable legal requirements;

such standards shall be met unless Design/Builder obtains a variance from Owner in writing.

4.5 Permits. The Owner shall be responsible for the cost of the main building permit and costs associated with City plan review. The Design/Builder shall be responsible for a timely coordination of all review meetings and applications with city staff necessary to acquire the permit and initiate the inspection process. Owner’s representative shall be invited to all meetings with city staff. Design/Builder shall submit all documents and applications required for plan review and obtaining the building permit.

Design/Builder responsible for all aspects of obtaining all necessary trade specific permits and other governmental approvals necessary for the development of the Project and shall obtain the same at the times necessary to meet the Project schedule.

4.6 Design Software. The design and construction drawings shall be developed using AutoCAD or

REVIT (BIM) software. See Exhibit A.

4.7 Notice of Non-Compliance with Law. If Design/Builder believes or is advised by another design professional retained to provide services on the Project that implementation of any instruction received from Owner would cause a violation of any applicable law, Design/Builder shall promptly so notify

Owner in writing.

ARTICLE 5. DESIGN / PRECONSTRUCTION SERVICES

5.1 Project Requirements. The Design/Builder shall meet with the Owner to ascertain the requirements of the Project. The approved Space Program, Narrative Specification & Equipment List

(ATTACHMENT A-1) shall serve as the basic planning document for the development of plans and specifications.

WOU Design/Build Contract REV 07/01/2026 Page 10

5.2 Program Evaluation. The Design/Builder shall provide a preliminary evaluation of the Owner's

Facilities Program, schedule and construction budget requirements, each in terms of the other. This project has established a priority for the development of the project with the budget being the predominant determining element guiding the development of the project. Maximizing the achievable program within the given project budget is the primary objective. The schedule for the project is of secondary importance and should be optimized for the most cost effective approach to the delivery of the project.

5.3 Project Alternatives. The Design/Builder shall review with the Owner alternative approaches to design, project documentation and construction of the Project.

5.4 Submittal Requirements. When the Design/Builder makes submittals to the Owner at the various phases of design, the Design/Builder shall comply with the requirements for the type and quantity of such submittals set forth on Exhibit D.

5.5 On-Site Program and Budget Verification. During the design phases, Design/Builder agrees to provide, as part of Basic Services, on-site program and budget verification, development and review workshops necessary or desirable to develop a design, acceptable to Owner and its user groups, which is within Owner’s budget. Such workshop(s) will be conducted with representatives of Owner’s user groups and the Owner’s Representatives. Without limitation of the foregoing, at the Program Verification and

Conceptual Design phase, Schematic Design phase, and Design Development phase, the Design/Builder shall support and attend presentations and shall include drawings, models, renderings, animations, and other tools as necessary to illustrate and convey information on particulars of the design intent. This shall include site plans with building footprint, landscape and tree removal plans, building elevations, and architectural details as needed. At such presentation the Design/Builder shall also address all issues and concerns previously identified but not yet addressed by the Design/Builder to the Owner’s user groups’ satisfaction.

5.6 Quality Control Programs. The Design/Builder shall establish and submit for Owner review within thirty (30) calendar days of the Owner’s execution of this Agreement:

(i) Project reporting procedures;

(ii) Quality Control and Testing Program; and

(iii) Safety program.

5.7 Jobsite Management & Logistics Plan. The Design/Builder shall develop a comprehensive jobsite management and logistics plan for the Owner’s review. This plan shall be submitted with 100% Design

Development submittal and shall be included in GMP supporting documentation.

5.8 LEED Certification. All services relating to LEED certification as necessary to support the role of the Architect and the Contractor as they pertain to the requirements of LEED certification during design, construction and post construction. The Design/Builder shall work with Owner to work diligently toward the stated target budget to pursue the highest possible performance of the building in association with the

Owner’s stated goals including; the Oregon Model of Sustainable Development, the Advanced Energy

Threshold, and Leadership in Energy and Environmental Design (LEED) certification for the Project, at the level of GOLD.

5.9 Program Verification and Conceptual Design (PV&CD). Based on the approved Program and

Narrative Specification, schedule and construction budget requirements, the Design/Builder shall prepare several alternative design solutions. The Design/Builder shall present these alternatives to the Owner, making submittals of studies, consisting of sketches and initial concepts in accordance with schedule requirements. After receiving the Owner's comments, the Design/Builder shall prepare, for approval by

WOU Design/Build Contract REV 07/01/2026 Page 11 the Owner, Conceptual Design Studies which shall represent one or more recommended solutions. The submittal shall consist of documents, including sketches, initial concepts, orientation, and relationships to existing and future programmed projects.

5.10 Schematic Design (SD). Based upon the approved Conceptual Design studies, the Design/Builder shall prepare, for approval by the Owner, Schematic Design Documents consisting of drawings, or three-dimensional renderings, outline narrative specifications and other documents illustrating the scale and relationship of Project components, energy conservation approach and building systems parameters. The

Design/Builder shall submit to the Owner the Schematic Design Documents for review in accordance with schedule requirements. See Design Documentation Requirements, included as part of Exhibit A. In coordination with the Campus Planning Office, meet with Owner's Campus Planning Committee and

Design Advisory Group as often as required during the Schematic Design Phase and upon completion of the Schematic Design Phase to obtain a positive recommendation to the Western Oregon University president that the schematic design, based upon the final schematic design documents, be accepted.

5.11 Design Development Phase. Based on the approved Schematic Design Documents and any adjustments authorized by the Owner in the Facilities Program, schedule or construction budget, the

Design/Builder shall prepare, for approval by the Owner, Design Development Documents consisting of drawings, three dimensional renderings, full format specifications and other documents to fix and describe the size and character of the Project as to architectural, structural, mechanical, plumbing, fire protection and electrical systems, materials and such other elements as may be appropriate. The

Design/Builder shall submit the Design Development Documents to the Owner for review in accordance with schedule requirements. These submittals will be required at two points during the Design

Development Phase; the first at 50% Design Development; the second review is required at 100% Design

Development. The Owner will provide comments to the 100% Design Development set. The

Design/Builder shall establish a conformed set of documents based upon the 100% Design Development documentation and the Owner’s comments. This conformed set shall be the record document that establishes the design basis for the GMP. See Design Documentation Requirements as part of Exhibit D.

5.12 Construction Documents Phase. Based on the conformed Design Development Documents and any further adjustments in the scope or quality of the Project or in the construction budget authorized by the Owner, the Design/Builder shall prepare and submit to Owner Construction Documents consisting of

Drawings and Specifications setting forth in detail the requirements for the construction of the Project.

Construction Documents shall be provided to Owner at the 95% stage in accordance with schedule requirements.

5.13 Construction Reports. At each phase of preliminary design, the Design/Builder shall provide, in addition to design drawings, a report detailing construction issues and concerns relating to the design, in light of Owner’s goals and the Space Program for the Project, with detail appropriate to the level of design. Without limitation of the foregoing, the construction report shall:

(i) include an estimate of overall construction cost, with Design/Builder’s contingency associated with the Cost of the Work specifically identified as a line item;

(ii) identify conceptual decisions that were made or will need to be made which are necessary to prepare accurate cost reports with the fewest assumptions, qualifications and exclusions;

(iii) provide an analysis and evaluation of jobsite management, site logistics, budget and schedule considerations considered in preparation of the design drawings;

(iv) provide an analysis and evaluation of the constructability issues which were addressed in preparing the design drawings or which need to be addressed during future design phases; and

(v) provide an analysis and evaluation of the design drawings in regard to the completeness of intended bid categories, conflicts or overlaps in the divisions of the Work, design details affecting

WOU Design/Build Contract REV 07/01/2026 Page 12 construction, value engineering, identification of long-lead materials affecting the Construction

Schedule, availability of labor and other factors affecting construction. Explain how the completeness level impacted the establishment of the contingency levels defined in your cost estimate.

5.14 Construction Schedules. Design/Builder shall supplement the overall Project Schedule attached as

Exhibit B with a detailed Construction Schedule. The submission of the initial Construction Schedule shall be submitted as part of the 100% Schematic Design Submittal described in this Article 5; a final

Construction Schedule shall be submitted with the Guaranteed Maximum Price proposal; and revised

Construction Schedules in accordance with the WOU General Conditions.

5.15 GMP Proposal.

5.15.1 At the completion of 100% Design Development, the Design/Builder shall prepare and deliver to the Owner, a Guaranteed Maximum Price (“GMP”) proposal. The cost prepared by the

Design/Builder shall include but not be limited to the following items in the GMP proposal:

(i) a recital of the specific Construction Documents, including drawings, specifications, and all addenda thereto, used in preparation of the GMP proposal;

(ii) any previously executed Early Work Amendments identified as part of item (iii) below;

(iii) the five (5) elements of the Guaranteed Maximum Price:

a. Guaranteed Maximum Cost of the Work (hereinafter defined), detailed by each subcontract, trade, or bid division;

b. the Design/Builder’s Contingency for the Work (5% shall be the maximum contingency acceptable by the Owner at the time of GMP);

c. Guaranteed Maximum Design/Builder’s Staffing Cost (hereinafter defined), detailed by expense category;

d. Guaranteed Maximum General Conditions Cost (includes bond & insurance costs)

(hereinafter defined), detailed by expense category; and

e. Guaranteed Maximum for Design/Builder’s Overhead and Profit.

(iv) a draft schedule of values;

(v) a description of all other inclusions to, or exclusions from, the GMP;

(vi) all assumptions and clarifications; and

(vii) the final Construction Schedule.

5.15.2 The Design/Builder acknowledges that the Construction Documents may be incomplete at the time the Design/Builder delivers the GMP proposal, and that the Construction Documents may not be completed until after commencement of the Work. Nevertheless, the GMP proposal shall include all costs for the Work required by the completed Construction Documents, and if the GMP proposal is accepted by the Owner, the Design/Builder shall be entitled to no increase in the GMP if the Work required by the completed Construction Documents (i) is required by the Contract for Design/Build

Construction, (ii) is reasonably inferable from the incomplete documents, (iii) is consistent with the

Owner’s programmatic goals and objectives, (iv) is consistent with the Owner’s Design and Construction

Standards and the general industry standards for completion of the Work, (v) is not a substantial enlargement of the scope of Work or (vi) substantially conforms to the nature, type, kind or quality of

Work depicted in the incomplete documents.

5.15.3 If the GMP proposal is unacceptable to the Owner, the Owner shall promptly notify the

Design/Builder in writing. Within fourteen (14) calendar days of such notification, the Owner, and

Design/Builder shall meet to discuss and resolve any differences, inconsistencies, or misunderstandings and to negotiate recommended adjustments to the Work and/or to the GMP.

WOU Design/Build Contract REV 07/01/2026 Page 13

5.15.4 The Owner may, at its sole discretion and based upon its sole judgment, (i) indicate its acceptance of a GMP proposal; (ii) reject a GMP proposal; (iii) terminate the Project; or (iv) proceed to establish a contract with another Design/Build proposer; or (v) proceed to establish a direct Contract with the Architect of Record within the Design/Build team for the purpose of developing Construction

Documents that could be used to solicit bids under a Design/Bid/Build delivery method.

5.15.5 If the Design/Builder does not furnish a GMP acceptable to Owner within Owner's Target

GMP Range, or if Owner determines at any time in its sole discretion that the parties may fail to reach a timely agreement on a GMP acceptable to Owner, Owner may terminate the Contract without liability, and the Design Builder shall not receive additional compensation beyond the portion of the Design Fee earned under the Contract and sums due under any Early Work Amendment. Termination under this provision shall proceed under Section J.5 and J.6 of the WOU General Conditions as a termination for

Owner's convenience. Design/Builder further agrees that Owner shall not be liable for any damages whether actual, consequential or otherwise for termination of the Contract under these provisions.

5.15.6 If the Owner accepts a GMP proposal, the parties shall complete and execute Exhibit F

(GMP Amendment), and the Owner shall issue a written Notice to Proceed to the Design/Builder establishing the date construction is to commence (the “Commencement Date”). The Design/Builder shall not expend any monies for construction prior to receipt of such Notice to Proceed without the written approval of the Owner.

5.15.7 Price Guarantees.

(i) Upon execution of Exhibit F the Design/Builder guarantees that the sum of the actual Cost of the Work, Design/Builder’s Contingency, Design/Builder’s Staffing Costs, General

Conditions Cost, and Design/Builder’s Overhead and Profit, shall not exceed the amount set forth in the agreed upon GMP. All costs or expenses that would cause this sum to exceed the

GMP shall be borne by the Design/Builder unless adjusted by Owner approved change order.

(ii) Upon execution of Exhibit F the Design/Builder guarantees that the actual Cost of the

Work, Design/Builder’s Staffing Costs, General Conditions Cost and Design/Builder’s

Overhead and Profit shall not exceed the guaranteed maximum for each such category and that all costs or expenses that would cause any of these individual categories to exceed the guaranteed maximum for each such category in the agreed upon GMP shall be borne by the

Design/Builder unless adjusted by Owner approved change order.

(iii) Upon execution of Exhibit F the Design/Builder certifies that all factual unit costs supporting the GMP proposal are accurate, complete and current at the time of negotiations;

and that any other factual unit costs that may be furnished to the Owner in the future to support any additional amounts that may be authorized will also be accurate and complete.

Payments to the Design/Builder shall be reduced if the Owner determines such amounts were originally included due to materially inaccurate, incomplete,

(iv) Upon execution of Exhibit F the Design/Builder guarantees that to the extent the accepted

GMP includes contingency, use of contingency shall be approved by Owner in writing prior to expenditure by the Design/Builder.

5.16 Corrected/Conformed Construction Documents Set. The Design/Builder shall submit to the

Owner a Corrected/Conformed Construction Documents Set incorporating all City of Monmouth design review comments, revisions or suggestions elicited during development of the Guaranteed Maximum

Price Proposal, pre-bid inquiries, and other modifications made to the 100% Construction Documents set. Submit to the Owner in accordance with schedule requirements.

WOU Design/Build Contract REV 07/01/2026 Page 14

ARTICLE 6. ADDITIONAL DESIGN SERVICES

6.1 Additional Services. If the services described in this Article 6 are not included in the basic Design /

Preconstruction Services or reasonably inferable therefrom, they shall be paid for by the Owner as

“Additional Services” as provided in this Agreement, in addition to the compensation for Design /

Preconstruction Services. The Additional Services shall be performed only if authorized in writing by the

Owner prior to their performance. Providing additional design services made necessary by defects or deficiencies in the Work performed by Design/Builder shall not entitle Design/Builder to compensation.

6.2 Additional Services Mark-up. For Additional Services being provided by consultants not included on the original Project Team, which require no work on the part of the Design/Builder other than administering the work thereof (i.e., securing the services, approving the work, and invoicing on behalf of the consultant), the Design/Builder may request a mark-up not to exceed the Overhead/Profit Mark-up submitted as part of the proposal submitted by the Design/Builder.

6.3 Fees. For Additional Services described in this Article 6, a lump sum or not-to-exceed amount which is satisfactory to both parties shall be negotiated on each occasion the Owner requests specific additional services. The Design/Builder’s staff costs associated therewith shall be based on the hourly rates set forth on Exhibit G.

6.4 Certain Traditional Additional Services Considered Basic Services. If Owner has determined that Owner requires certain services which are traditionally considered Additional Services for the purpose of calculating the Design/Builder’s fees, such services are described on Exhibit C and compensation for such services is included in the schedule set forth on Exhibit G. For purposes of this

Agreement, such services constitute Basic Services.

6.5 Additional Design Services.

6.5.1 Design professional representation at the Project site more extensive than that described in Article 5.

6.5.2 Making revisions in Drawings, Specifications or other documents but if, and only if, such revisions are:

6.5.2.1 inconsistent with approvals or instructions previously given by the Owner; or

6.5.2.2 required by the enactment or revision of codes, laws or regulations subsequent to the preparation of such documents and not reasonably foreseeable at the time of the preparation of such documents.

6.5.3 Providing consultation concerning replacement of Work damaged by fire or other cause during construction, and furnishing services required in connection with the replacement of such Work that is not the responsibility of the Design/Builder and/or not covered by Design/Builder’s insurance.

6.5.4 Providing services in connection with a public hearing or legal proceeding except where the Design/Builder is party thereto.

6.5.5 When required by the Owner, preparing documents for alternate, separate or sequential bids, except issuing early bid packages in support of fast-track construction delivery process.

6.5.6 Providing planning surveys, site evaluations or comparative studies of prospective sites.

WOU Design/Build Contract REV 07/01/2026 Page 15

6.5.7 Providing special surveys, environmental studies and submissions required for approvals of governmental authorities or others having jurisdiction over the Project.

6.5.8 Providing services relative to future facilities, systems and equipment, when not specifically included in the original Facilities Program for the Project.

6.5.9 Providing coordination of construction performed by separate contractors or by the

Owner's own forces and coordination of services required in connection with construction performed and equipment supplied by the Owner.

6.5.10 Providing interior design and other similar services required for, or in connection with, the selection, procurement or installation of furniture, furnishings and related equipment not included as part of the list provided as part of Exhibit A.

6.5.11 Making investigations, inventories of materials or equipment, or valuations and detailed appraisals of existing facilities.

6.5.12 Providing design services after issuance by the Owner of the final payment to the

Design/Builder, except for those services described in Article 7.

6.5.13 Providing services of consultants other than those described on Exhibit C.

6.5.14 Providing site surveys, geotechnical testing services or other special tests.

6.5.15 Providing prolonged contract administration and construction observation should the construction time specified for final completion be exceeded by more than 60 days through no fault of

Design/Builder or anyone under their hire.

6.5.16 Providing any other services not otherwise included in this Agreement. Notwithstanding anything to the contrary herein, Design/Builder shall not be entitled to additional design fees if the same are necessitated by the fault of Design/Builder.

ARTICLE 7. CONSTRUCTION SERVICES

7.1 General Intent. Design/Builder shall perform all Work and construction administration services necessary to construct the Project in accordance with the Contract for Design/Build Construction and to render the Project and all of its components operational and functionally and legally usable.

7.2 Notice to Proceed. If Construction Services are added to the Contract as set forth in Article 5.15.6, then a notice to proceed will be issued by Owner to begin the designated or full Construction Services

(“Notice to…