EXHIBIT G - MaaskeForensicLabPLBG.pdf
PDF 149 KB Posted
- Attached to
- Maaske and APSC Remodel RFP
- Solicitation number
- S-580200-00018488
- Issued by
- Multnomah County, Mission CDP, Oregon
About this file
This document is a plumbing scope of work and fixture specifications for the Maaske Forensic Lab Retrofit project. The scope outlines comprehensive plumbing work across multiple rooms, including installation of new fixtures in Room 117 (drop-in stainless steel sink with pre-rinse faucet and Schier Solids interceptor), Room 116 (new floor drain), Room 115 (reconnection of existing floor drains), reconfiguration and demolition work in the 117 and 115 closets, complete bathroom demolition in the existing bathroom, and retrofit of hallway plumbing for a new Murdock bottle filler station. The project involves both new installation and demolition activities with specific routing and securing requirements for plumbing lines. Detailed fixture specifications are provided, including a Kohler lavatory sink with Chicago Faucet (1 GPM), a Kohler Kingston Ultra Top Spud toilet with Zurn flush valve (1.6 GPF) and Bemis seat, a Mustee mop sink with Chicago Faucet, and a Schier SI-1 solids interceptor.
The document does not contain information regarding pricing terms, set-asides, incumbent contractors, funding sources, response dates, or contract award timelines. No specific budget amounts, bidding procedures, or contract term details are included in this plumbing scope and fixture specification exhibit.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maaske Forensic Lab Retrofit: Plumbing Scope
● RM 117: Install new drop-in deep, stainless steel sink, pre-rinse faucet with spout and a Schier Solids interceptor.
● RM 116: Add a new floor drain, positioned dead center in the room.
● RM 115: Reconnect the plumbing to the four (4 typ.) existing floor drains.
● 117 Closet: Reconfigure the existing plumbing to allow for the architectural demolition of the closet. Route and secure all plumbing as high as possible, tucked tightly against the west-facing wall so it can be furred in.
● RR 118: Demo existing plumbing. Cut and cap the water closet below the finished floor.
● 115 Closet: Demo the existing floor sink. Cap the plumbing from below in the basement.
● Existing Bathroom: Demo the existing bathroom entirely. Cap all plumbing either below the finished floor or inside the wall.
● Hallway: Remove the existing porcelain drinking fountain. Retrofit the existing plumbing to rough-in and set the new bottle filler station (MURDOCK BFEZS168-BF12S). (Note: A new electrical rough-in will be required for this unit).
Maaske Forensic Lab Retrofit: Fixture Specifications
● Bottle Filler:
○ Murdock BFEZS168-BF12S
● Lavatory:
○ Sink: Kohler K-2007-0 (White) Kingston
○ Faucet: Chicago Faucet CHI-FCT 2201-E74ABCP 1 GPM
● Water Closet:
○ Carrier: JR Smith 0542FY 4" Single No-Hub Floor Mount
○ Toilet: Kohler K-84325-0 Kingston Ultra Top Spud
○ Flush Valve: Zurn ZER6000AV-WS1-TM 1.6 GPF
○ Seat: Bemis 1955SSCT-000 Elongated Open Front, STA-TITE, Self-Sustaining (White)
● Mop Sink:
○ Basin: Mustee 63MX 24" x 24" x 10" Mop Service Basin (with 2" and 3" drain seals)
○ Faucet: Chicago Faucet CHI-FCT 897-CRCF
● Solids Interceptor:
○ SCHIER SI-1
| Maaske Forensic Lab Retrofit: Plumbing Scope |
| Maaske Forensic Lab Retrofit: Fixture Specifications |
File details come from the government source that posted it. Updated .