Exhibit J - Transition Schedule Requirements - Moore Haven.pdf

PDF 231 KB Posted

Attached to
Operation and Management of Contractor-Operated Correctional Facilities – Moore Haven CF
Solicitation number
ITN-12041
Issued by
Glades County, Florida

About this file

Exhibit J is a Transition Schedule Requirements document from the Florida Department of Corrections (FDC) for Invitation to Negotiate (ITN-25-068) related to the operation and management of contractor-operated correctional facilities. The document provides comprehensive guidelines for project scheduling, specifically detailing requirements for developing and managing project schedules using Microsoft Project. Key scheduling requirements include implementing a rolling wave planning approach, maintaining detailed task relationships, establishing specific task duration parameters (following the 8/80 rule), managing resources effectively, and creating a structured Work Breakdown Structure (WBS). The document mandates that schedules should be developed with at least six months of detailed planning, include continuous task logic, and be baselined before applying status values.

The scheduling standard emphasizes precise technical requirements for project management, such as limiting manual tasks, avoiding date constraints, ensuring all subtasks have predecessors and successors, and maintaining resource allocations at 100% for full-time equivalent resources. The document includes a sample Work Breakdown Structure that demonstrates how projects should be organized across different levels, from project summary to specific tasks and sprints. Critical scheduling recommendations include using recurring tasks for routine administrative activities, setting milestone durations to zero, and following a strict change management process when updating baselines. The guidelines are designed to improve project schedule confidence, reduce guesswork in project management, and align with Project Management Institute (PMI) principles.

View the file

Other files

File Type Posted
Attachment F - 2024-2025 4-Week Master Menu Spreadsheets 10.1 Final.pdf PDF
ITN-25-068 Contractor Operated CF MH Final.pdf PDF
Attachment L - Reference Questionnaire.pdf PDF
Exhibit J - Transition Schedule Requirements - Moore Haven.pdf PDF
Attachment G - December 2024 Alphabetical State Drug Formulary.pdf PDF
FORM 2 - Notice of Conflict of Interest.pdf PDF
FORM 12 - REPLY BOND FORM.docx DOCX document
Attachment A Draft Moore Haven OM Contract Revised Final.pdf PDF
FORM 9 - PUR 7801 (Vendor Certification Form).docx DOCX document
FORM 1 - Contact Information.pdf PDF
Attachment A Draft Moore Haven OM Contract Final.pdf PDF
Exhibit I - Transition Plan Requirements - Moore Haven.pdf PDF
Attachment M - Business Associate Agreement for HIPPA.pdf PDF
Attachment C Price Sheet - Moore Haven.xlsx XLSX spreadsheet
Exhibit M - 2026-27FY IWTF Program Request and Budget Narrative Request Template.xlsx XLSX spreadsheet
FDC ITB-25-068 Addendum 1 QA Final.pdf PDF
Attachment B Inventory - Moore Haven - Feb 2025.pdf PDF
FORM 3 - Statement of No involvement.pdf PDF
Attachment J - Confidentiality and Non-Disclosure Agreement.pdf PDF
FORM 7 - Pass Fail Requirement Certification and Non-Collusion Certification.pdf PDF
FORM 5 - Subcontracting.pdf PDF
Attachment E - Operating Per Diem Revised.pdf PDF
FORM 4 - Business Experience.pdf PDF
FORM 10 - pur 2024 use of coercion forced labor combined final.docx DOCX document
Attachment E - Operating Per Diem.pdf PDF
FORM 8 - PUR1355 Foreign Country of Concern Attestation.docx DOCX document
FORM 11 - DRUG FREE WORKPLACE.pdf PDF
Exhibit K - Quarterly Performance Measures and Deliverables - Moore Haven.xls XLS spreadsheet
Attachment H - Current Facility Program Plan - Moore Haven.pdf PDF
FORM 6 - Mandatory Responsiveness Requiements.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit J

FDC ITN-25-068

TRANSITION SCHEDULE REQUIREMENTS

FDC-ITN-25-068

Operation and Management of Contractor-Operated Correctional Facilities Page 1 of 6

BASED THE STANDARD ESTABLISHED BY RULE 74-1, F.A.C.

This standard assumes the reader is proficient in the use of Microsoft Project as well as with generally-accepted scheduling terminology and practices. This standard is provided to facilitate dynamic scheduling techniques, which align with proven principles and practices promoted by the Project Management Institute (PMI®). The purpose of this document is to assist in the development of project schedules that contain a clearly-defined critical path, accurately represent project progress and performance, and provide credible project end dates. This standard should not only improve confidence levels in the project schedule, they should also take some of the guesswork out of managing the actual work of the project.

GENERAL PROJECT SETUP

General Project Setup

1. Ensure the Master Project Schedule includes all tasks required to complete the entire scope of work.

2. Ensure state holidays are identified in the Standard Calendar.

R

ROLLING WAVE AND DETAILED PLANNING

1. The schedule should be detailed for all activities that fall within six (6) months of the status date in a continuous rolling wave. For example, at the start of January, tasks for the months of January through June shall be detailed; at the start of February, tasks for the months of February through July shall be detailed, and so forth.

2. Using a custom text field entitled “Detail Level” is recommended to distinguish Rolling

Wave activities from the detailed part of the schedule. Use the following labels: Detailed, Inside Rolling Wave, and Outside Rolling Wave. Tasks should be elaborated as follows within each planning window:

a. Detailed Planning Window: Within the six (6) month, detailed planning window, subtask durations should follow the 8/80 rule (see Task Durations section).

b. Inside Rolling Wave Planning Window: Within the six (6) month to twelve (12) month Rolling Wave planning window, subtask durations should not exceed twenty

(20) days.

c. Outside Rolling Wave Planning Window: Beyond twelve (12) months (including future fiscal years), subtask durations should not exceed sixty (60) days.

REMAINDER OF PAGE INTENTIONALLY LEFT BLANK.

Operation and Management of Contractor-Operated Correctional Facilities Page 2 of 6

SCHEDULE ACTIVITIES

1. Manual Tasks and Auto-Scheduled Tasks

a. Set the default for new tasks to Auto-Scheduled. Limit the use of Manual Tasks, as these are not driven by the scheduling engine.

2. Summary Tasks

a. No resources should be assigned to summary tasks.

b. No costs should be assigned to summary tasks.

c. No predecessors or successors should be assigned to summary tasks.

d. No date constraints should be applied to summary tasks (keep the default “As

Soon As Possible”).

3. Subtasks (i.e., tasks, detailed tasks, activities)

a. Subtasks should start with an action verb (e.g., prepare, review, configure, test).

b. Subtasks are not marked as milestones unless they are converted to a project milestone with zero (0) duration.

4. Milestones

a. All milestones should have zero (0) duration and be clearly identified as a milestone task type.

b. No resources should be assigned to milestones.

c. No costs should be assigned to milestones.

d. All milestones should have at least one (1) predecessor (unless it is the Project

Start milestone).

e. All milestones should have at least one (1) successor (unless it is the last line of the schedule).

f. No date constraints should be applied to milestones (keep the default “As Soon As

Possible”).

g. The Milestone checkbox should always be checked for milestones.

5. Recurring Tasks

a. The use of Recurring Tasks is recommended for routine project support and administration activities, such as status reports, team status meetings, invoice

Operation and Management of Contractor-Operated Correctional Facilities Page 3 of 6 processing, etc. Avoid using normal (non-recurring) subtasks and milestones for these types of activities.

TASK DURATIONS

1. Ensure the duration time unit is set to “days.” Avoid using partial day durations (e.g., 0.5 days).

2. Avoid manually entering start and finish dates; doing so places constraints on subtasks.

Start and finish dates should be determined by the schedule’s network logic and task durations.

3. Subtask durations should generally follow the 8/80 rule, where detailed planning subtasks do not have durations less than one (1) day (eight (8) hours duration) or greater than ten

(10) days (eighty (80) hours duration).

4. Estimated durations (e.g., “ten (10) days?”) should only be used within the Rolling Wave Planning Windows. Avoid using estimated durations in the Detailed Planning Window of the schedule.

RESOURCES

1. In the Resource sheet, Maximum Units should not exceed one hundred percent (100%) for each full-time equivalent (FTE) resource.

2. Avoid overstating resource availability (e.g., by setting Maximum Units at one thousand percent (1,000%) for an individual or for a small team of two (2) or three (3) people); doing so bypasses MS Project’s ability to detect and display over-allocated resources, thus leaving that risk undetected.

3. Resources should be assigned to subtasks only (not to summary tasks or milestones). All subtasks should have at least one (1) resource assigned.

4. Each resource should only appear once in the Resource Sheet. Make sure individually-listed resources are not duplicated by also being a member of a resource group.

5. It is recommended that individual resource calendars reflect when a team member is out for three (3) days or more.

Operation and Management of Contractor-Operated Correctional Facilities Page 4 of 6

BASELINING THE SCHEDULE

1. The schedule should be baselined before applying any status values (e.g., %Complete) to any activities.

2. Before creating the initial baseline, it is recommended that:

a. The schedule should be developed at a detail level at least six (6) months out from the status date (see Rolling Wave and Detailed Planning section).

b. All subtasks and milestones have predecessor and successor logic, and the schedule logic is continuous with no interruption to the logical sequence of activities, including the activities in the Rolling Wave Planning Windows of the schedule.

c. All subtasks have resource assignments (see Resources section).

3. The initial baseline should be set when the project team (with its vendor, if applicable) agrees to the work to be performed, and the resourcing and timing of the work.

4. For each monthly Rolling Wave iteration, add the newly detailed tasks to the current baseline by baselining only those new or updated tasks. The project’s approved Change Management process should be followed.

5. The current baseline should always be “Baseline.” When rebaselining the entire schedule, save the current baseline to Baseline 1 – 10, accordingly.

6. Avoid rebaselining simply because initial estimates were a little off. Rebaseline only if parameters of the project have changed, such as when the addition or removal of scope or resources (human or financial) impacts the work; and then, only rebaseline using proper change management practices which include documentation of the reason(s) for updating the current baseline or rebaselining the schedule and the associated impacts to the schedule, cost, and benefits realization.

TASK RELATIONSHIPS & CONSTRAINTS

1. All subtasks (except the first (1st) one(1)) should have at least one (1) predecessor.

2. All subtasks should have at least one (1) successor (unless it is the last subtask in the schedule). Routine project administration tasks (e.g., status meetings, invoice processing) do not necessarily need a successor relationship if no other task has a dependency on that administrative activity; however, it is recommended such tasks link to the phase or project completion milestone (or a similar termination point).

3. Task relationships (network logic) should be continuous and unbroken from the beginning to the end of the schedule.

Operation and Management of Contractor-Operated Correctional Facilities Page 5 of 6

4. Tasks associated with the creation of the project’s product or solution should be linked to preserve the continuity of the schedule’s overall network logic. See Figure 2 - Continuous Task Relationships among Product Development Activities.

5. Avoid using date constraints on subtasks (keep the default “As Soon As Possible”). If necessary, use MS Project’s “Deadline” field to tag tasks with specific target dates.

Operation and Management of Contractor-Operated Correctional Facilities Page 6 of 6

WORK BREADKOWN STRUCTURE (WBS)

Work Breakdown Structure (WBS)

based the standard established by rule 74-1, F.A.C.
General project setup
Rolling Wave and Detailed Planning
Schedule Activities
Task Durations
Resources
Baselining the Schedule
Task Relationships & Constraints
work breadkown structure (WBS)