Exhibit_G_-_Bid_Price_Sheet_26-B-39IF.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
Florida Shores Boulevard Vehicular Beach Access Ramp
Solicitation number
26-B-39IF
Issued by
Volusia County, Florida

About this file

This Bid Price Sheet (Exhibit G) is associated with Volusia County, Florida's Invitation to Bid No. 26-B-39IF for the reconstruction of the Florida Shores Boulevard Vehicular Beach Access Ramp in Daytona Beach Shores. The project encompasses demolition of existing damaged structures, excavation and grading, construction of a concrete sheet-pile seawall with gravity wall, reinforced concrete vehicular ramp, curbing, pedestrian sidewalk, landscaping, pavement markings and signage, site restoration, and as-built survey certification. The scope includes 16 line items with quantities ranging from lump sum (LS) amounts for mobilization/demobilization, demolition, and sheet-pile seawall work to unit-based pricing for materials such as sand fill (600 tons), heavy-duty concrete (200 square yards), FDOT Type "D" curb (150 linear feet), and sidewalk (13 square yards). The non-mandatory pre-bid meeting is scheduled for March 16, 2026, at 10:30 a.m., with questions due by March 26, 2026, at 11:59 p.m., and sealed bids due April 9, 2026, at 3:00 p.m. through the County's eProcurement Portal. The project requires substantial completion within 120 days and final completion within 150 days from Notice to Proceed, with award anticipated in May 2026 to the lowest responsive and responsible bidder.

The estimated project cost totals $2,041,339, inclusive of a 20 percent contingency of $340,223. Key cost components include sheet-pile seawall at $924,000, reinforced concrete ramp at $131,556, mobilization/demobilization at $130,000, flood insurance at $100,000, site restoration at $60,000, bond costs at $76,244, and various smaller line items. Unit pricing includes sand fill at $50 per ton, heavy-duty concrete at $250 per square yard, FDOT Type "D" curb at $80 per linear foot, and sidewalk at $217 per square yard. The project is funded through a combination of state and federal sources, with the State of Florida Department of Environmental Protection as a partner, and benefits from FEMA funding subject to Davis-Bacon Act prevailing wage requirements. Volusia County holds a Consumer's Certificate of Exemption from Florida sales and use tax, providing approximately 6 percent savings on material costs through deductive change orders. Payment terms are 20 to 25 business days from invoice receipt in accordance with Florida Statutes Section 218.735, with liquidated damages assessed at $1,000 per day for construction delays and $27 per calendar day for Contract Work Hours and Safety Standards Act violations.

View the file

Other files

File Type Posted
Florida_Shores_Boulevard_Vehicular_Beach_Access_Ramp_(Addendum_#3_Revision).pdf PDF
Exhibit_D_-_Construction_Plans_26-B-39IF_-_REVISED_04.07.2026_-_REPLACES_ALL_PREVIOUS_VERSIONS.pdf PDF
Exhibit_G_-_Bid_Price_Sheet_26-B-39IF_-_REVISION_1_-_REPLACES_ALL_PREVIOUS_VERSIONS_-_USE_THIS_FORM_ONLY.xlsx XLSX spreadsheet
Exhibit_E_-_Technical_Specifications_26-B-39IF_-_REVISED_03.23.2026_-_REPLACES_ALL_PREVIOUS_VERSIONS.docx DOCX document
Florida_Shores_Boulevard_Vehicular_Beach_Access_Ramp_(Addendum_#1_Revision).pdf PDF
Exhibit_B_-_Prime_SubContractor_Form_26-B-39IF.xls XLS spreadsheet
Exhibit_G_-_Bid_Price_Sheet_26-B-39IF.xlsx XLSX spreadsheet
Exhibit_L_-_Installation_Floater_Affidavit_26-B-39IF.docx DOCX document
Exhibit_K_-_Federal_Contract_Provisions_26-B-39IF.pdf PDF
Exhibit_J_-_Survey_26-B-39IF.pdf PDF
Exhibit_I_-_Geotechnical_Data_26-B-39IF.pdf PDF
Exhibit_H_-_FDEP_Permit_26-B-39IF.pdf PDF
Exhibit_F_-_Sales_Tax_Exemption_Procedures.pdf PDF
Exhibit_E_-_Technical_Specifications_26-B-39IF.pdf PDF
Exhibit_D_-_Construction_Plans_26-B-39IF.pdf PDF
Exhibit_C_-_Draft_Contract_26-B-39IF.pdf PDF
Exhibit_A_-_Insurance_Requirements_26-B-39IF.pdf PDF
FLORIDA_SHORES.pdf PDF
FDEP_Permit_VO002371_AR_FO_SECURED.pdf PDF
Tech_Specs_2025-05-19_Final_Design_-_Tech_Specs_-_Florida_Shores.pdf PDF
Survey_240601_LB.pdf PDF
Geotech_G23215_Report_of_Geotechnical_Data_DSS_07-30-24.pdf PDF
2025-05-19_Bid_Schedule.xlsx XLSX spreadsheet
PRIME-SUB_FORM_Florida_Shores_Vehicular_Beach_Ramp.xls XLS spreadsheet
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OPC

Volusia County
Florida Shores Boulevard
Vehicular Beach Access Ramp
May 19, 2025
OPC
ItemDescriptionQuantityUnit PriceCost
1Mobilization/Demobilization1LS$130,000LS$130,000
2Demolition1LS$60,000LS$60,000
3Excavation, Grading, and Compaction1LS$50,000LS$50,000
4Sand Fill600Ton$50Ton$30,000
5Sheet-Pile Seawall1LS$924,000LS$924,000
6Gravity Wall1LS$32,500LS$32,500
7Reinforced Concrete Ramp1LS$131,556LS$131,556
8Heavy Duty Concrete200SY$250SY$50,000
9FDOT Type "D" Curb150LF$80LF$12,000
10Sidewalk13SY$217SY$2,817
11Landscaping1LS$20,000LS$20,000
12Pavement Markings & Signage1LS$10,000LS$10,000
13As-Built Survey1LS$12,000LS$12,000
14Site Restoration1LS$60,000LS$60,000
15Bond1LS$76,244LS$76,244
16Flood Insurance1LS$100,000LS$100,000
Contingency 20%$340,223
Total Cost:$2,041,339
Contract Time:120 days

Bid Schedule

Exhibit G - Bid Price Sheet 26-B-39IF
Florida Shores Boulevard
Vehicular Beach Access Ramp
Company Name:
ItemDescriptionQuantity0Unit Price0Cost
1Mobilization/Demobilization1LS$ - 0LS$ - 0
2Demolition1LS$ - 0LS$ - 0
3Excavation, Grading, and Compaction1LS$ - 0LS$ - 0
4Sand Fill600Ton$ - 0Ton$ - 0
5Sheet-Pile Seawall1LS$ - 0LS$ - 0
6Gravity Wall1LS$ - 0LS$ - 0
7Reinforced Concrete Ramp1LS$ - 0LS$ - 0
8Heavy Duty Concrete200SY$ - 0SY$ - 0
9FDOT Type "D" Curb150LF$ - 0LF$ - 0
10Sidewalk13SY$ - 0SY$ - 0
11Landscaping1LS$ - 0LS$ - 0
12Pavement Markings & Signage1LS$ - 0LS$ - 0
13As-Built Survey1LS$ - 0LS$ - 0
14Site Restoration1LS$ - 0LS$ - 0
Subtotal$ - 0
Payment and Performance Bond$ - 0
Total Project Cost (inclusive of payment and performance bond)$ - 0
Award of this project will be determined based on the lowest responsive and responsible bidder using the combined pricing submitted for Florida Shores Boulevard Vehicular Beach Ramp Reconstruction.
Flood Insurance Policy Pricing*$ - 0
*Pricing for Flood Insurance is required for this project; however, it will not be included as part of the evaluation.