This is a Bid Price Sheet (Exhibit G, Revision 1) for Volusia County, Florida's Invitation to Bid No. 26-B-39IF for the reconstruction of the Florida Shores Boulevard Vehicular Beach Access Ramp in Daytona Beach Shores. The project encompasses demolition of hurricane-damaged structures, excavation and grading, construction of a concrete sheet-pile seawall with gravity wall components, a reinforced concrete vehicular ramp, curbing, pedestrian sidewalk, landscaping, pavement markings, signage, site restoration, and as-built survey certification. The bid sheet itemizes 16 line items including mobilization/demobilization, sand fill (600 tons), heavy-duty concrete (200 square yards), FDOT Type "D" curb (150 linear feet), sidewalk (13 square yards), and bond costs. The non-mandatory pre-bid meeting was scheduled for March 16, 2026, at 10:30 a.m., with questions due by March 26, 2026, at 11:59 p.m., and sealed bids due April 9, 2026, at 3:00 p.m. through the County's eProcurement Portal. The project requires substantial completion within 120 days and final completion within 150 days from Notice to Proceed, with award anticipated in May 2026 to the lowest responsive and responsible bidder.
The estimated total project cost is $2,041,339, including a 20 percent contingency of $340,223. The estimated bid pricing reflects line items such as mobilization/demobilization at $130,000, sheet-pile seawall at $924,000, reinforced concrete ramp at $131,556, sand fill at $50 per ton, heavy-duty concrete at $250 per square yard, FDOT Type "D" curb at $80 per linear foot, sidewalk at $217 per square yard, and flood insurance at $100,000. A 5 percent bid bond and Payment and Performance Bond equal to 100 percent of the contract price are required. The project is funded through a partnership between Volusia County and the State of Florida Department of Environmental Protection and benefits from FEMA funding, requiring compliance with Davis-Bacon Act prevailing wage requirements and federal contract provisions. Contractors must hold current Florida-licensed general contractor status, enroll in E-Verify, and provide comprehensive insurance including Workers' Compensation, Commercial General Liability with $1,000,000 per occurrence limits, and Contractors' Pollution Liability coverage. Payment terms are 20 to 25 business days from invoice receipt under Florida Statutes Section 218.735, and liquidated damages are assessed at $1,000 per day for project delays.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OPC
| Volusia County | ||||||
| Florida Shores Boulevard | ||||||
| Vehicular Beach Access Ramp | ||||||
| May 19, 2025 | ||||||
| OPC | ||||||
| Item | Description | Quantity | Unit Price | Cost | ||
| 1 | Mobilization/Demobilization | 1 | LS | $130,000 | LS | $130,000 |
| 2 | Demolition | 1 | LS | $60,000 | LS | $60,000 |
| 3 | Excavation, Grading, and Compaction | 1 | LS | $50,000 | LS | $50,000 |
| 4 | Sand Fill | 600 | Ton | $50 | Ton | $30,000 |
| 5 | Sheet-Pile Seawall | 1 | LS | $924,000 | LS | $924,000 |
| 6 | Gravity Wall | 1 | LS | $32,500 | LS | $32,500 |
| 7 | Reinforced Concrete Ramp | 1 | LS | $131,556 | LS | $131,556 |
| 8 | Heavy Duty Concrete | 200 | SY | $250 | SY | $50,000 |
| 9 | FDOT Type "D" Curb | 150 | LF | $80 | LF | $12,000 |
| 10 | Sidewalk | 13 | SY | $217 | SY | $2,817 |
| 11 | Landscaping | 1 | LS | $20,000 | LS | $20,000 |
| 12 | Pavement Markings & Signage | 1 | LS | $10,000 | LS | $10,000 |
| 13 | As-Built Survey | 1 | LS | $12,000 | LS | $12,000 |
| 14 | Site Restoration | 1 | LS | $60,000 | LS | $60,000 |
| 15 | Bond | 1 | LS | $76,244 | LS | $76,244 |
| 16 | Flood Insurance | 1 | LS | $100,000 | LS | $100,000 |
| Contingency 20% | $340,223 | |||||
| Total Cost: | $2,041,339 | |||||
| Contract Time: | 120 days |
Bid Schedule
| Exhibit G - Bid Price Sheet 26-B-39IF - REVISION 1 | |
| Florida Shores Boulevard | |
| Vehicular Beach Access Ramp | |
| Company Name: |
| Item | Description | Quantity | 0 | Unit Price | 0 | Cost |
| 1 | Mobilization/Demobilization | 1 | LS | $ - 0 | LS | $ - 0 |
| 2 | Demolition | 1 | LS | $ - 0 | LS | $ - 0 |
| 3 | Excavation, Grading, and Compaction | 1 | LS | $ - 0 | LS | $ - 0 |
| 4 | Sand Fill | 600 | TON | $ - 0 | TON | $ - 0 |
| 5 | Sheet-Pile Seawall | 280 | LF | $ - 0 | LF | $ - 0 |
| 6 | Gravity Wall | 56 | LF | $ - 0 | LF | $ - 0 |
| 7 | Reinforced Concrete Ramp | 338 | SY | $ - 0 | SY | $ - 0 |
| 8 | Heavy Duty Concrete | 246 | SY | $ - 0 | SY | $ - 0 |
| 9 | FDOT Type "D" Curb | 150 | LF | $ - 0 | LF | $ - 0 |
| 10 | Sidewalk | 117 | SY | $ - 0 | SY | $ - 0 |
| 11 | FDOT Aluminum Guardrail and Gate | 292 | LF | $ - 0 | LF | $ - 0 |
| 12 | Landscaping | 1 | LS | $ - 0 | LS | $ - 0 |
| 13 | Pavement Markings & Signage | 1 | LS | $ - 0 | LS | $ - 0 |
| 14 | As-Built Survey | 1 | LS | $ - 0 | LS | $ - 0 |
| 15 | Site Restoration | 1 | LS | $ - 0 | LS | $ - 0 |
| Subtotal | $ - 0 | |||||
| Payment and Performance Bond | $ - 0 | |||||
| Total Project Cost (inclusive of payment and performance bond) | $ - 0 | |||||
| Award of this project will be determined based on the lowest responsive and responsible bidder using the combined pricing submitted for Florida Shores Boulevard Vehicular Beach Ramp Reconstruction. |
| Flood Insurance Policy Pricing* | $ - 0 |
| *Pricing for Flood Insurance is required for this project; however, it will not be included as part of the evaluation. |
File details come from the government source that posted it. Updated .