2025-05-19_Bid_Schedule.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
Florida Shores Boulevard Vehicular Beach Access Ramp
Solicitation number
26-B-39IF
Issued by
Volusia County, Florida

About this file

This is a bid schedule for the Florida Shores Boulevard Vehicular Beach Access Ramp project in Volusia County, Florida, which involves the reconstruction of a beach access vehicular ramp destroyed during Hurricane Ian in 2022. The project encompasses concrete sheet pile seawall panels, concrete cap, reinforced concrete vehicular ramp, curbing, pedestrian sidewalk, and site restoration work. The project is scheduled for completion within 120 days from mobilization. Key line items include mobilization and demobilization, demolition, excavation and grading, sand fill (600 tons), sheet-pile seawall installation, gravity wall construction, reinforced concrete ramp, heavy-duty concrete (200 square yards), FDOT Type "D" curb (150 linear feet), sidewalk installation (13 square yards), landscaping, pavement markings and signage, as-built survey, site restoration, bonding, and flood insurance. Laydown areas, equipment, and materials must be maintained in the easternmost portion of the right of way, with vehicular access to adjacent properties maintained throughout construction.

The total project cost is estimated at $2,041,339, including a 20 percent contingency of $340,223. The bid schedule itemizes unit prices for each work component, with lump sum pricing for major items such as mobilization ($130,000), sheet-pile seawall ($924,000), and reinforced concrete ramp ($131,556). Unit-priced items include sand fill at $50 per ton, heavy-duty concrete at $250 per square yard, FDOT curb at $80 per linear foot, and sidewalk at $217 per square yard. Additional costs include bond ($76,244), flood insurance ($100,000), and site restoration ($60,000). The bid schedule provides a blank template for contractors to submit their own unit and lump sum pricing for evaluation and comparison purposes.

View the file

Other files

File Type Posted
Florida_Shores_Boulevard_Vehicular_Beach_Access_Ramp_(Addendum_#3_Revision).pdf PDF
Exhibit_D_-_Construction_Plans_26-B-39IF_-_REVISED_04.07.2026_-_REPLACES_ALL_PREVIOUS_VERSIONS.pdf PDF
Exhibit_G_-_Bid_Price_Sheet_26-B-39IF_-_REVISION_1_-_REPLACES_ALL_PREVIOUS_VERSIONS_-_USE_THIS_FORM_ONLY.xlsx XLSX spreadsheet
Exhibit_E_-_Technical_Specifications_26-B-39IF_-_REVISED_03.23.2026_-_REPLACES_ALL_PREVIOUS_VERSIONS.docx DOCX document
Florida_Shores_Boulevard_Vehicular_Beach_Access_Ramp_(Addendum_#1_Revision).pdf PDF
Exhibit_B_-_Prime_SubContractor_Form_26-B-39IF.xls XLS spreadsheet
Exhibit_G_-_Bid_Price_Sheet_26-B-39IF.xlsx XLSX spreadsheet
Exhibit_L_-_Installation_Floater_Affidavit_26-B-39IF.docx DOCX document
Exhibit_K_-_Federal_Contract_Provisions_26-B-39IF.pdf PDF
Exhibit_J_-_Survey_26-B-39IF.pdf PDF
Exhibit_I_-_Geotechnical_Data_26-B-39IF.pdf PDF
Exhibit_H_-_FDEP_Permit_26-B-39IF.pdf PDF
Exhibit_F_-_Sales_Tax_Exemption_Procedures.pdf PDF
Exhibit_E_-_Technical_Specifications_26-B-39IF.pdf PDF
Exhibit_D_-_Construction_Plans_26-B-39IF.pdf PDF
Exhibit_C_-_Draft_Contract_26-B-39IF.pdf PDF
Exhibit_A_-_Insurance_Requirements_26-B-39IF.pdf PDF
FLORIDA_SHORES.pdf PDF
FDEP_Permit_VO002371_AR_FO_SECURED.pdf PDF
Tech_Specs_2025-05-19_Final_Design_-_Tech_Specs_-_Florida_Shores.pdf PDF
Survey_240601_LB.pdf PDF
Geotech_G23215_Report_of_Geotechnical_Data_DSS_07-30-24.pdf PDF
PRIME-SUB_FORM_Florida_Shores_Vehicular_Beach_Ramp.xls XLS spreadsheet
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OPC

Volusia County
Florida Shores Boulevard
Vehicular Beach Access Ramp
May 19, 2025
OPC
ItemDescriptionQuantityUnit PriceCost
1Mobilization/Demobilization1LS$130,000LS$130,000
2Demolition1LS$60,000LS$60,000
3Excavation, Grading, and Compaction1LS$50,000LS$50,000
4Sand Fill600Ton$50Ton$30,000
5Sheet-Pile Seawall1LS$924,000LS$924,000
6Gravity Wall1LS$32,500LS$32,500
7Reinforced Concrete Ramp1LS$131,556LS$131,556
8Heavy Duty Concrete200SY$250SY$50,000
9FDOT Type "D" Curb150LF$80LF$12,000
10Sidewalk13SY$217SY$2,817
11Landscaping1LS$20,000LS$20,000
12Pavement Markings & Signage1LS$10,000LS$10,000
13As-Built Survey1LS$12,000LS$12,000
14Site Restoration1LS$60,000LS$60,000
15Bond1LS$76,244LS$76,244
16Flood Insurance1LS$100,000LS$100,000
Contingency 20%$340,223
Total Cost:$2,041,339
Contract Time:120 days

Bid Schedule

Volusia County
Florida Shores Boulevard
Vehicular Beach Access Ramp
May 19, 2025
OPC
ItemDescriptionQuantity0Unit Price0Cost
1Mobilization/Demobilization1LSLS
2Demolition1LSLS
3Excavation, Grading, and Compaction1LSLS
4Sand Fill600TonTon
5Sheet-Pile Seawall1LSLS
6Gravity Wall1LSLS
7Reinforced Concrete Ramp1LSLS
8Heavy Duty Concrete200SYSY
9FDOT Type "D" Curb150LFLF
10Sidewalk13SYSY
11Landscaping1LSLS
12Pavement Markings & Signage1LSLS
13As-Built Survey1LSLS
14Site Restoration1LSLS
15Bond1LSLS
16Flood Insurance1LSLS
Total Cost:
Contract Time: