2025-05-19_Bid_Schedule.xlsx
XLSX spreadsheet 16 KB Posted
- Solicitation number
- 26-B-39IF
- Issued by
- Volusia County, Florida
About this file
This is a bid schedule for the Florida Shores Boulevard Vehicular Beach Access Ramp project in Volusia County, Florida, which involves the reconstruction of a beach access vehicular ramp destroyed during Hurricane Ian in 2022. The project encompasses concrete sheet pile seawall panels, concrete cap, reinforced concrete vehicular ramp, curbing, pedestrian sidewalk, and site restoration work. The project is scheduled for completion within 120 days from mobilization. Key line items include mobilization and demobilization, demolition, excavation and grading, sand fill (600 tons), sheet-pile seawall installation, gravity wall construction, reinforced concrete ramp, heavy-duty concrete (200 square yards), FDOT Type "D" curb (150 linear feet), sidewalk installation (13 square yards), landscaping, pavement markings and signage, as-built survey, site restoration, bonding, and flood insurance. Laydown areas, equipment, and materials must be maintained in the easternmost portion of the right of way, with vehicular access to adjacent properties maintained throughout construction.
The total project cost is estimated at $2,041,339, including a 20 percent contingency of $340,223. The bid schedule itemizes unit prices for each work component, with lump sum pricing for major items such as mobilization ($130,000), sheet-pile seawall ($924,000), and reinforced concrete ramp ($131,556). Unit-priced items include sand fill at $50 per ton, heavy-duty concrete at $250 per square yard, FDOT curb at $80 per linear foot, and sidewalk at $217 per square yard. Additional costs include bond ($76,244), flood insurance ($100,000), and site restoration ($60,000). The bid schedule provides a blank template for contractors to submit their own unit and lump sum pricing for evaluation and comparison purposes.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OPC
| Volusia County | ||||||
| Florida Shores Boulevard | ||||||
| Vehicular Beach Access Ramp | ||||||
| May 19, 2025 | ||||||
| OPC | ||||||
| Item | Description | Quantity | Unit Price | Cost | ||
| 1 | Mobilization/Demobilization | 1 | LS | $130,000 | LS | $130,000 |
| 2 | Demolition | 1 | LS | $60,000 | LS | $60,000 |
| 3 | Excavation, Grading, and Compaction | 1 | LS | $50,000 | LS | $50,000 |
| 4 | Sand Fill | 600 | Ton | $50 | Ton | $30,000 |
| 5 | Sheet-Pile Seawall | 1 | LS | $924,000 | LS | $924,000 |
| 6 | Gravity Wall | 1 | LS | $32,500 | LS | $32,500 |
| 7 | Reinforced Concrete Ramp | 1 | LS | $131,556 | LS | $131,556 |
| 8 | Heavy Duty Concrete | 200 | SY | $250 | SY | $50,000 |
| 9 | FDOT Type "D" Curb | 150 | LF | $80 | LF | $12,000 |
| 10 | Sidewalk | 13 | SY | $217 | SY | $2,817 |
| 11 | Landscaping | 1 | LS | $20,000 | LS | $20,000 |
| 12 | Pavement Markings & Signage | 1 | LS | $10,000 | LS | $10,000 |
| 13 | As-Built Survey | 1 | LS | $12,000 | LS | $12,000 |
| 14 | Site Restoration | 1 | LS | $60,000 | LS | $60,000 |
| 15 | Bond | 1 | LS | $76,244 | LS | $76,244 |
| 16 | Flood Insurance | 1 | LS | $100,000 | LS | $100,000 |
| Contingency 20% | $340,223 | |||||
| Total Cost: | $2,041,339 | |||||
| Contract Time: | 120 days |
Bid Schedule
| Volusia County | ||||||
| Florida Shores Boulevard | ||||||
| Vehicular Beach Access Ramp | ||||||
| May 19, 2025 | ||||||
| OPC | ||||||
| Item | Description | Quantity | 0 | Unit Price | 0 | Cost |
| 1 | Mobilization/Demobilization | 1 | LS | LS | ||
| 2 | Demolition | 1 | LS | LS | ||
| 3 | Excavation, Grading, and Compaction | 1 | LS | LS | ||
| 4 | Sand Fill | 600 | Ton | Ton | ||
| 5 | Sheet-Pile Seawall | 1 | LS | LS | ||
| 6 | Gravity Wall | 1 | LS | LS | ||
| 7 | Reinforced Concrete Ramp | 1 | LS | LS | ||
| 8 | Heavy Duty Concrete | 200 | SY | SY | ||
| 9 | FDOT Type "D" Curb | 150 | LF | LF | ||
| 10 | Sidewalk | 13 | SY | SY | ||
| 11 | Landscaping | 1 | LS | LS | ||
| 12 | Pavement Markings & Signage | 1 | LS | LS | ||
| 13 | As-Built Survey | 1 | LS | LS | ||
| 14 | Site Restoration | 1 | LS | LS | ||
| 15 | Bond | 1 | LS | LS | ||
| 16 | Flood Insurance | 1 | LS | LS | ||
| Total Cost: | ||||||
| Contract Time: |
File details come from the government source that posted it. Updated .